1. Introduction
The cantilever pouring the construction method of the bridge was one of the most important methods to solve the construction problems of river crossing bridge. The rhombic hanging basket had stable structure, high utilization efficiency, convenient disassembly, movement, so it was most widely used in cantilever the construction (Hyo and Je, 2004; Won et al., 2008); the method generally adopted the hanging basket the construction technology. The hanging basket can bear the load and beam weight in the construction process. It was designed without a unified, systematic and perfect standard. Hence, before the application of the hanging basket, a reasonable design and accurate mechanical checking calculation can be carried out to ensure its safety in the construction process (Liu et al., 2019; Zhao et al., 2017).
In the meantime, domestic and foreign scholars have carried out relevant research (Mashal and Palermo, 2019; Li et al., 2020). Li (2018) used a prestressed concrete continuous beam bridge as a support during the the construction of the Mao-ji-te Bridge and introduced the differences due to the difference in the load-bearing structure. Four types of hanging baskets were listed. The main structure and force characteristics of different structural types of hanging baskets were analysed in detail. In addition, the different characteristics of specific projects were combined to select the hanging basket structure suitable for the actual project (Li, 2018). Gao (2016) shortened the length of the hanging basket by setting a triangular truss on the cast-in-place main beam. He combined the advantages of the front fulcrum hanging basket and the middle fulcrum hanging basket and proposed a short platform composite traction rope hanging basket to improve the problem that the main beam section can be changed when the long platform traction rope hanging basket walked (Gao, 2016); the above studies were the introduction of different hanging basket structures during cantilever beam pouring and summarized the matters needing attention to ensure the safe the construction of hanging basket. However, there was still a lack of finite element modeling analysis and discussion on hanging basket the construction and walking. Chen et al. (2013) described the key points of the main truss of the triangular hanging basket in the design process and carried out spatial modeling, analysis and calculation of the structure through MIDAS / civil program, which put forward theoretical support for the finite element simulation of cantilever hanging basket the construction in the future (Chen, 2013); An et al. (2018) proposed that the high pier long-span continuous rigid frame aqueduct in Xujiawan was constructed by cantilever method, and the first-order method of ANSYS was used for optimization calculation (An, 2018). The original rhombic hanging basket was transformed. Apart from these, a cable-stayed combined light rhombic hanging basket combining the traditional rhombic hanging basket and the sliding cable-stayed hanging basket was raised, which reduced the quality of the hanging basket and improved the utilization coefficient; Gu et al. (2019) added the transportation system and hoisting system to the traditional hanging basket structure. After the corrugated steel web was lifted to the poured beam surface, the transportation system moved it to the hanging basket hoisting starting point (Gu, 2019). And then the corrugated steel web was installed through the hoisting system. The feasibility of the composite structure was verified through calculation and finite element simulation; in order to overcome the shortcomings of traditional balanced cantilever the construction, He et al. (2020) introduced a new asynchronous pouring the construction technology. It made full use of the excellent shear resistance of corrugated steel webs to support the hanging basket, optimized the walking system, increased the construction platform, effectively accelerated the the construction speed, reduced the construction load, and saved the project cost (He et al., 2020); Zhou et al. (2020) combined with the excellent shearing capacity of the corrugated steel mesh and introduced asynchronous pouring and rapid the construction methods. A significant change was that it used the corrugated steel mesh itself as the main load-bearing member to support the hanging basket and beam sections. In the new method, the balance state of the new hanging basket system was optimized from the cantilever to the pure support state, and the walking system was optimized in the meantime, which greatly shortened the construction time and ensured the safety of the project (Zhou et al., 2020).
Generally speaking, the research so far has mainly focused on the optimization and transformation of the main truss structure of the cradle. The shortcomings of the walking system of the cradle still existed, and there were few studies in this area. Relevant industrial standards have not yet been established and were difficult to be set up in hanging basket-related equipment. Consequently, it is indispensable to calculate and simulate the mechanical properties of different equipment in order to ensure the safety of the construction process. Relying on the Tianjin Haihe Bridge project, this paper proposed a new type of traveling rail for the cradle and optimized the structure of the main truss of the rhombus cradle, which solved the problem of low efficiency in the construction of the traditional cradle. Through calculation and finite element simulation, the hanging basket met the engineering requirements.
4. Discussion
The traditional hanging basket walking mechanism was to lay steel rails on the box girder working panels, which were fixed by front and rear supports and prestressed steel bars. The height of the steel rails was higher, which was increased the overall center of gravity of the equipment and raised the overturning of the hanging basket during the construction. In addition, the walking track was long and heavy, and the process of paving and dismantling was complicated, which limited the improvement of the efficiency of bridge the construction. Relying on the Tianjin Haihe Bridge, this paper designed a novel rhombus traveling track of hanging basket, which had higher tensile strength, higher compressive strength and better impact resistance than traditional rails. The design and analysis of the force state of the rhombus hanging basket running under different working conditions, and the finite element simulation and calculation were carried out; based on the simulation and calculation results, the suitable hanging basket transformation for the project was proposed and verified. The scheme optimized the structure of the hanging basket components, reduced weight and saved costs, shortened the the construction period, and improved the construction efficiency.
Using Midas/Civil software, the mechanical properties of the rhombus hanging basket under three working conditions, fully loaded and unloaded, were analyzed. In working condition 1, the maximum beam unit internal force of 149.69Mpa occurred at the joint between the front upper beam and the main truss, which was less than the allowable stress of Q235 steel 175Mpa. In working condition 2,the maximum stress occurred in the No.1 suspender with a value of 295.4Mpa, which was less than the allowable stress of 650Mpa. In working condition 3, the anti-overturning safety factor of the hanging basket was 2.5 to meet the requirements, and the strength and distortion of the walking mechanism were within the specified range; the key components were calculated and compared with the finite element calculation, and it was found that the finite element calculation was reliable and the structure performance was 30% left and right redundancy. In order to further improve the utilization efficiency of the suspended pouring basket, the main truss and the pouring stage were optimized. It was found that when the front elevation angle of the main truss was 20°, the steel consumption was the least, the member stress was small, and the stress of each member was relatively uniform and small vertical distortion; when the pouring section was extended by 0.5m, the heaviest section was extended to 5m, and the working condition when the weight was increased to 229.96t, the working condition still met the requirements. The research results of this paper can provide references to the structural optimization and improvement of the rhombus hanging basket and similar cantilever the construction projects.
Figure 1.
The longitudinal section of the main bridge.
Figure 1.
The longitudinal section of the main bridge.
Figure 2.
Cross section of suspended pouring block.
Figure 2.
Cross section of suspended pouring block.
Figure 3.
New type of walking track chain plate structure.
Figure 3.
New type of walking track chain plate structure.
Figure 4.
Twin screw extruder and granulation.
Figure 4.
Twin screw extruder and granulation.
Figure 5.
Load bearing chain plate track.
Figure 5.
Load bearing chain plate track.
Figure 6.
New materials in tensile test: (a) Before the test (Left), (b) After the test (Right).
Figure 6.
New materials in tensile test: (a) Before the test (Left), (b) After the test (Right).
Figure 7.
Time and test force curve of tensile test sample.
Figure 7.
Time and test force curve of tensile test sample.
Figure 8.
Compression test specimen.
Figure 8.
Compression test specimen.
Figure 9.
Specimen collapsed in the compression test.
Figure 9.
Specimen collapsed in the compression test.
Figure 10.
Time and force curve of compression test.
Figure 10.
Time and force curve of compression test.
Figure 11.
New material in impact resistance test.
Figure 11.
New material in impact resistance test.
Figure 12.
Sample broken after test.
Figure 12.
Sample broken after test.
Figure 13.
Dimensions of the main truss.
Figure 13.
Dimensions of the main truss.
Figure 14.
Overall calculation model of hanging basket.
Figure 14.
Overall calculation model of hanging basket.
Figure 15.
Missing points of internal material.
Figure 15.
Missing points of internal material.
Figure 16.
Boundary conditions and uniform load of chain plate.
Figure 16.
Boundary conditions and uniform load of chain plate.
Figure 17.
Mechanical simulation results.
Figure 17.
Mechanical simulation results.
Figure 18.
Z-direction distortion nephogram of the whole structure of the hanging basket under condition 1.
Figure 18.
Z-direction distortion nephogram of the whole structure of the hanging basket under condition 1.
Figure 19.
Stress nephogram of overall structure of hanging basket under condition 1.
Figure 19.
Stress nephogram of overall structure of hanging basket under condition 1.
Figure 20.
Distortion nephogram of main truss structure under condition 1.
Figure 20.
Distortion nephogram of main truss structure under condition 1.
Figure 21.
Stress nephogram of main truss structure under condition 1.
Figure 21.
Stress nephogram of main truss structure under condition 1.
Figure 22.
Structural distortion nephogram of front upper crossbeam under condition 1.
Figure 22.
Structural distortion nephogram of front upper crossbeam under condition 1.
Figure 23.
Stress nephogram of front upper crossbeam structure under condition 1.
Figure 23.
Stress nephogram of front upper crossbeam structure under condition 1.
Figure 24.
Cloud diagram of structural distortion of bottom basket under condition 1.
Figure 24.
Cloud diagram of structural distortion of bottom basket under condition 1.
Figure 25.
Stress nephogram of bottom basket structure under condition 1.
Figure 25.
Stress nephogram of bottom basket structure under condition 1.
Figure 26.
Nephogram of suspender distortion under condition 1.
Figure 26.
Nephogram of suspender distortion under condition 1.
Figure 27.
Nephogram of suspender stress under condition 1.
Figure 27.
Nephogram of suspender stress under condition 1.
Figure 28.
Cloud diagram of Z-direction distortion of overall structure of hanging basket under condition 2.
Figure 28.
Cloud diagram of Z-direction distortion of overall structure of hanging basket under condition 2.
Figure 29.
Cloud diagram of overall structural stress of hanging basket under working condition 2.
Figure 29.
Cloud diagram of overall structural stress of hanging basket under working condition 2.
Figure 30.
Cloud diagram of main truss structure distortion under condition 2.
Figure 30.
Cloud diagram of main truss structure distortion under condition 2.
Figure 31.
Cloud diagram of main truss structure distortion under working condition 2.
Figure 31.
Cloud diagram of main truss structure distortion under working condition 2.
Figure 32.
Cloud diagram of structural distortion of front upper beam under working condition 2.
Figure 32.
Cloud diagram of structural distortion of front upper beam under working condition 2.
Figure 33.
Nephogram of structural distortion of the front upper beam under condition 2.
Figure 33.
Nephogram of structural distortion of the front upper beam under condition 2.
Figure 34.
Cloud diagram of structural distortion of bottom basket under working condition 2.
Figure 34.
Cloud diagram of structural distortion of bottom basket under working condition 2.
Figure 35.
Cloud diagram of structural distortion of bottom basket under working condition 2.
Figure 35.
Cloud diagram of structural distortion of bottom basket under working condition 2.
Figure 36.
Cloud diagram of suspender structure distortion under working condition 2.
Figure 36.
Cloud diagram of suspender structure distortion under working condition 2.
Figure 37.
Cloud diagram of suspenderr structure distortion under working condition 2.
Figure 37.
Cloud diagram of suspenderr structure distortion under working condition 2.
Figure 38.
Front lower beam and bottom longitudinal beam.
Figure 38.
Front lower beam and bottom longitudinal beam.
Figure 39.
Calculation stress diagram of bottom longitudinal beam under Web.
Figure 39.
Calculation stress diagram of bottom longitudinal beam under Web.
Figure 40.
Deflection diagram of bottom longitudinal beam under Web.
Figure 40.
Deflection diagram of bottom longitudinal beam under Web.
Figure 41.
Calculation stress diagram of bottom longitudinal beam under bottom plate.
Figure 41.
Calculation stress diagram of bottom longitudinal beam under bottom plate.
Figure 42.
Deflection diagram of bottom longitudinal beam under bottom plate.
Figure 42.
Deflection diagram of bottom longitudinal beam under bottom plate.
Figure 43.
Front elevation of main truss.
Figure 43.
Front elevation of main truss.
Figure 44.
Schematic diagram of model parameters change caused by the change of front elevation angle.
Figure 44.
Schematic diagram of model parameters change caused by the change of front elevation angle.
Figure 45.
Stress variation of model member caused by change of front elevation angle.
Figure 45.
Stress variation of model member caused by change of front elevation angle.
Figure 46.
Distortion of important members of the model.
Figure 46.
Distortion of important members of the model.
Figure 47.
Hanging basket structure with a front elevation angle.
Figure 47.
Hanging basket structure with a front elevation angle.
Figure 48.
Z-direction distortion nephogram of overall optimized structure of hanging basket for extended casting segment.
Figure 48.
Z-direction distortion nephogram of overall optimized structure of hanging basket for extended casting segment.
Figure 49.
Stress nephogram of overall optimization structure of hanging basket for extended casting segment .
Figure 49.
Stress nephogram of overall optimization structure of hanging basket for extended casting segment .
Table 1.
Tensile property test schedule.
Table 1.
Tensile property test schedule.
Experimental instrument |
Electronic universal testing machine |
Experimental temperature |
20℃ |
Stretching speed |
50mm/min |
Test repetition times |
5 |
Number of test samples |
5 |
Table 2.
Schedule of compression performance test.
Table 2.
Schedule of compression performance test.
Experimental instrument |
Electronic universal testing machine |
Experimental temperature |
20℃ |
Compression speed |
10mm/min |
Test repetition times |
5 |
Number of test samples |
5 |
Table 3.
Impact resistance test schedule.
Table 3.
Impact resistance test schedule.
Experimental instrument |
Impact testing machine |
Experimental temperature |
20℃ |
Pendulum energy |
7.5J |
Impact speed |
3.8m/s |
Test repetition times |
5 |
Number of test samples |
5 |
Table 4.
Summary of impact test results.
Table 4.
Summary of impact test results.
Experiment |
Elevation [°] |
Air attack angle[°] |
Impact angle[°] |
Absorbed energy[J] |
Impact strength [kJ/m2] |
1 |
160 |
158.40 |
101.92 |
2.797 |
69.92 |
2 |
160 |
158.40 |
103.63 |
2.685 |
67.12 |
3 |
160 |
158.40 |
107.23 |
2.452 |
61.30 |
4 |
160 |
158.40 |
98.55 |
3.022 |
75.55 |
5 |
160 |
158.40 |
105.36 |
2.575 |
64.37 |
Table 5.
Analysis of each member of main truss under condition 1.
Table 5.
Analysis of each member of main truss under condition 1.
Member name |
Max stress [Mpa] |
Max vertical distortion [mm] |
Allowable stress [Mpa] |
Allowable distortion [mm] |
AB |
92.6 |
0.25 |
175 |
11.75 |
CD |
149.7 |
12.53 |
175 |
13.25 |
BD |
55.0 |
0.41 |
175 |
9.00 |
AD |
103.9 |
0.60 |
175 |
14.91 |
BC |
134.2 |
10.33 |
175 |
15.25 |
Table 6.
Distortion and stress information of suspender in condition 1.
Table 6.
Distortion and stress information of suspender in condition 1.
Suspender name |
Max distortion [mm] |
Max stress [Mpa] |
Allowable stress[Mpa] |
1 |
2.83 |
470.1 |
650 |
2 |
11.39 |
320.7 |
650 |
3 |
16.11 |
261.6 |
650 |
4 |
11.52 |
320.3 |
650 |
5 |
2.83 |
347.8 |
650 |
Table 7.
Analysis of the members of main truss under condition 2.
Table 7.
Analysis of the members of main truss under condition 2.
Member name |
Maximum stress |
Maximum vertical distortion/mm |
Allowable stress/Mpa |
Allowable distortion/mm |
AB |
137.1 |
16.9 |
175 |
11.75 |
CD |
118.7 |
9.9 |
175 |
13.25 |
BD |
49.1 |
0.12 |
175 |
9.00 |
AD |
103.0 |
7.0 |
175 |
14.91 |
BC |
62.2 |
9.7 |
175 |
15.25 |
AE |
114.9 |
7.1 |
175 |
11.25 |
Table 8.
Suspender distortion and stress information under condition 2.
Table 8.
Suspender distortion and stress information under condition 2.
Suspender name |
Maximum distortion/mm |
Maximum stress/Mpa |
Allowable stress/Mpa |
1 |
17.13 |
295.4 |
650 |
2 |
19.37 |
218.8 |
650 |
3 |
21.76 |
260.1 |
650 |
4 |
22.94 |
162.3 |
650 |
5 |
23.18 |
167.9 |
650 |
Table 9.
Comparison of finite element calculation results and allowable values of members.
Table 9.
Comparison of finite element calculation results and allowable values of members.
Member |
Finite element analysis results |
Allowable value |
Performance redundancy |
Stress [Mpa] |
Distortion [mm] |
Stress [Mpa] |
Distortion [mm] |
Stress [%] |
Distortion [%] |
Main Trusses |
AB |
92.6 |
0.21 |
175 |
11.75 |
47.09 |
98.21 |
AD |
103.9 |
0.60 |
175 |
14.91 |
40.63 |
95.98 |
BC |
134.2 |
10.33 |
175 |
15.25 |
23.31 |
32.26 |
BD |
55.0 |
0.41 |
175 |
9.00 |
68.57 |
95.44 |
CD |
119.7 |
12.53 |
175 |
13.25 |
31.60 |
5.43 |
Front upper crossbeam |
113.8 |
12.47 |
175 |
18.13 |
34.97 |
31.22 |
Bottom longitudinal beam |
Under the Web |
71.32 |
9.05 |
175 |
15.25 |
59.25 |
40.66 |
Under the floor |
57.99 |
13.67 |
175 |
15.25 |
66.86 |
10.36 |
Lower cross beam |
Front lower beam |
52.93 |
16.12 |
175 |
18.00 |
69.75 |
10.44 |
Lower rear beam |
48.59 |
9.80 |
175 |
18.00 |
72.23 |
45.56 |
Table 10.
Model parameters for changing front elevation angle.
Table 10.
Model parameters for changing front elevation angle.
Front elevation angle |
35° |
30° |
25° |
20° |
15° |
10° |
5° |
BC+BD Pole length[m] |
11.161 |
10.824 |
10.675 |
10.628 |
10.664 |
10.768 |
10.935 |
BC+BD Rod steel amount[kg] |
1421.5 |
1378.5 |
1359.6 |
1353.6 |
1358.1 |
1371.4 |
1392.7 |
Table 11.
Comparison table of optimized main truss member information.
Table 11.
Comparison table of optimized main truss member information.
|
Original dimension of pole /mm |
Optimized pole size /mm |
Reduced steel consumption /kg |
AB pole |
□400×300×12mm |
□380×280×12mm |
3.744 |
AD pole |
□420×300×12mm |
□400×280×12mm |
7.488 |
BD pole |
□350×250×12mm |
□330×230×12mm |
3.744 |