1. Introduction
The recent years have seen a remarkable growth in the use of motor vehicle in many countries, being a consequence of their on-going economic growth, posing a challenge of how to ensure the required throughput of road junctions without compromising the traffic safety. Turbo roundabouts are considered a solution to this problem by offering a higher traffic throughput, as compared to conventional junctions [
1,
2]. Their main benefits include [
1,
2,
3,
4,
5,
6,
7,
8]:
- –
A higher by 150%-250% throughput, as compared to conventional single- or even double-lane roundabouts. They are also superior to the signalised junctions by eliminating waiting time at traffic lights.
- –
Traffic safety improvement by eliminating traffic conflicts, intersecting flows in particular. Worth noting is the reduction of fatalities or injuries by about 70% as compared to right-of-way intersections and by about 50% as compared to signalised intersections or conventional two-lane roundabouts. In addition, turbo roundabouts reduce the total number of road incidents by 85% and rear-end collisions by 95%.
- –
Land take comparable to double-lane approach and exit signalised intersections accommodating simultaneous movement of two tractor-trailer units in any directions during one signal cycle.
- –
Lower future maintenance costs and lower environmental and social cost of the project compared to signalised intersections, with only slightly higher project cost.
There are four conventional turbo roundabouts designs, as described in [
3,
9,
10]: Basic, Egg, Knee and Rotor. Turbo roundabouts are typically designed where a busy major road crosses a secondary local road. In these situations, Egg turbo roundabout is the recommended design option [
1,
3,
4,
5]. In suburban locations the biggest engineering challenge is limited availability of land. In the case of small Egg turbo roundabouts scarcity of land or close proximity of intersections on the approach legs may pose a challenge to design a proper, conventional turbo roundabout. Locations in the outskirts or near downtown areas aggravate the problem due to the constraints caused by the existing road network. Looking for the solution to increase throughput and ensure road safety the designer must also consider the design vehicle swept path requirement there. This is not uncommon in engineer's practice, who will not find in the literature turbo roundabout layout and design guidelines that would satisfy only some of the design principles detailed in [
1] and given in the web portal of Dirk de Baan [
10]. Examples of successfully completed turbo roundabouts despite various local constraints are shown in the following figures:
Figure 1 – homes or valuable sacral buildings located in close vicinity,
Figure 2 – presence of natural obstacles such as lakes or canals and
Figure 3 – apartment buildings located in the outskirts and large public buildings.
Four design principles have been developed for conventional turbo roundabouts [
1,
10] (based on Dirk de Baan’s web portal [
10]):
- –
Vehicles that are about to enter the roundabout through any leg are not obliged to not give way to the vehicles navigating through the roundabout on any of the two traffic lanes of the roundabout carriageway
- –
Having to give way to vehicles riding on all the three traffic lanes of the roundabout carriageway is complicated and impracticable for many road users. For this reason, larger turbo roundabouts should be provided with traffic lights as an additional traffic control measure.
- –
A raised curb installed in the separation lane allocates a specific lane for each vehicle, which it shall not change while navigating through the roundabout. There are no traffic conflicts due to weaving or crossing. Turbine roundabouts do not allow driving in circles from any direction
- –
Vehicles are gradually shifted from the inside to the outside, following spiral paths without any crossing movements. The smooth path of travel between the raised kerb separation lanes allows driving through the roundabout at a maximum speed of 35 to 40 km/h.
Dirk de Baan gives two more design principles for conventional turbo roundabouts including a separation lane featuring a raised concrete kerb (based on Dirk de Baan’s web portal [
10]):
- –
Dual lane exits should be provided on the main legs to maximise the roundabout throughput. However, with limited straight-through traffic a single exit lane may suffice.
- –
At each leg, a road user riding on the outer lane must have an option to exit or continue navigating through the turbo roundabout. A road user driving on the inner lane will have this choice on the next segment.
The above-mentioned Dutch conventional turbo roundabout design principles have been mostly departed from by Prof. Tollazzi et al. [
12,
13,
14,
15] and in the article of Ciampo et al. [
7] in the case of non-conventional turbo roundabouts described by them. The departures concern the shape of the turbo roundabout, "flattened" along the side legs axes (
Figure 3), irregular truck apron shape and a different central island shape (e.g. a conventional circle, ellipse or other).
Another departure from the above-mentioned Dutch guidelines are elliptical turbine roundabouts having a layout based on the theory of ellipses, described by Prof. Grabowski [
16]. In his article [
16] Prof. Grabowski describes how to lay out an elliptical turbo roundabout recommended for crossings between roads carrying considerably different traffic volumes, in particular where most traffic is handled by the main road. In the conclusions of the described analysis, Prof. Grabowski [
16] recommends "flattening" of the roundabout shape along the side road axis in proportion to the magnitude of this traffic volume difference. However, there are no definite guidelines giving the relationship between these two parameters. That said, in analyses where swept path is considered a design requirement, it appears to take precedence over any requirement resulting from the as yet indefinite flattening/ volume difference relationship.
Yet another issue is maximising the junction throughput in constrained areas by choosing appropriate turbo roundabout type. The throughput problem has been dealt with by a number of researchers [
2,
13,
17,
18,
19,
20,
21,
22,
23]. They adopted various hypotheses and simulation models with the purpose to calibrate the already existing methods and adjust them for various analyses with the overall objective to demonstrate superiority of turbo roundabouts over conventional roundabouts in terms of traffic handling capacity. Some authors point to the importance of full equilibrium traffic allocation among the approach legs and sometimes also the traffic lanes, e.g. [
7,
22,
23]. Others considered varied traffic flow scenarios on turning movements and analysed the effect of this variation on the final throughput. A different approach was taken in the articles [
7,
8], where traffic flow variation on the main road depending on the effect of adjacent crossing was considered beside different traffic flow scenarios on the lanes and movements on the roundabout approach legs. The main factors considered in the throughput analyses were: driving behaviour, gap acceptance distribution, delay suffered by the road users about to enter the, loss of time, queue length, etc. There are also a few articles dealing with the issue of throughput of roundabouts "flattened" along the side legs axes [
7,
14,
15,
22]. These studies showed that with a smaller traffic volume on the main approach legs turbo roundabout offered, in all cases, a higher throughput than conventional ones. Gallelli and Vaiana [
24] demonstrated the relevance of the traffic composition of the respective movements, which should be considered in traffic throughput analyses beside approach leg traffic volumes and different traffic flow allocation scenarios. Also interesting in this context is the article of Liu et al. [
6] in which a four and five-leg turbo roundabouts were superimposed on the existing large multi-lane conventional roundabout Lujiazui in Shanghai. In this case study
in situ measurements of different traffic flow scenarios were used to investigate the effect of the roundabout diameter, varied from 30 m to 80 m for both layouts under analysis, beside the total inlet volume and traffic allocation as the factors relevant to the turbo roundabout throughput. Also analysed was the relationship between the above mentioned design parameters, traffic volume and flow allocation on the roundabout inlets on the one hand and the accident potential and traffic safety indicators.
The above literature review, allowed us to pinpoint a gap in the currently available design guidelines and studies, that do not provide roundabout design guidelines maximising the throughput and traffic safety for the situations where conventional turbo roundabouts are not practicable due to constraints imposed by existing buildings, canals or other obstacles found at the project site. These issues are addressed in this article. The adopted method of analysis is presented in IMRAD diagram (
Figure 4).
Section 2 uses a case study to characterise the chosen intersection area and gives the parameters of design vehicles applied in the swept path analysis. The adopted research method, including the pre-determined determinants is also presented in this section.
Section 3 presents proposed layouts of the analysed turbo roundabouts of different types and selected fragments of the conducted swept path analysis. It also describes turbo blocks defining the layout of the selected turbo roundabouts.
Section 4 defines the primary determinants to facilitate selection of the most adequate turbo roundabout type presents a discussion of the swept path analysis results obtained for six turbo roundabouts differing in terms of land take. Pros and cons are given for each roundabout type based on the adopted determinants.
Section 5 gives the design guidelines for the respective turbo roundabout types depending on the site constraints.
4. Discussion
The analysis of the obtained turbo roundabout design, presented in section 3 above showed high geometrical diversity, requirement for traversable splitter islands and different surface areas of the required mountable aprons. Worth noting is also the unusual requirement for traversable parts after U-25 separators, between the pedestrian crossing and the beginning of the roundabout carriageway (
Figure 11 and
Figure 14). In "flattened" roundabouts traversable parts were also required in the beginning of splitter islands to avoid considerable widening of the roundabout carriageway lane (
Figure 11). Apart from the key parameters the proposed roundabouts have considerably different traffic organization, specifically the division of the roundabout carriageway into traffic lanes (
Figure 11,
Figure 14 and
Figure 17). Therefore, it is not possible to recommend a specific roundabout design from among the proposed ones, as an option of choice for severely constrained sites, based solely on the dimensional and swept path analyses.
Consequently, additional input conditions were defined by the authors in relation to the side road site characteristics using the diagram in
Figure 9:
- (a)
LUDA low urbanisation degree areas – single family housing estates or woonerf, the side road handles the local traffic composed mainly of the residents’ passenger cars and municipal service vehicles if appropriate,
- (b)
BA built-up area with a developed community infrastructure, requiring provision of pedestrian and cycle crossings running through splitter islands on the side approach legs,
- (c)
CDA highly commercially developed area along the side road, including primarily very big warehouses and wholesale markets resulting in high volumes of articulated trucks on turn movements.
For the adopted input conditions, following roundabout geometry and swept path analyses, geometrical, community and traffic engineering determinants were derived, the last related to traffic organization adopted for the roundabout carriageway and the respective approach legs. The determinant analysis results and recommended roundabout type are represented in
Figure 19.
In
Figure 19 the following colour coding system was implemented for rating the determinants:
- –
dark blue means good score i.e. lower cost, bigger pedestrian and cycling amenities, better handing of traffic in the roundabout area by adequate traffic flow allocation: two traffic lanes for the straight movements for high traffic volumes on the main road or a dedicated turn lane for a high heavy traffic volume on this movement, etc.
- –
light blue means the opposite score, i.e. less pedestrian and cyclist amenities, no dedicated right- or left-turn lanes despite a high heavy-traffic volume, etc.
- –
blue designates an intermediate score.
The geometrically related key determinants of the roundabout size in constrained sites include:
- –
number of straight-through lanes on the roundabout carriageway G1,
- –
number of traffic lanes on the main approach legs G2,
- –
spacing of splitter islands dividing measured along the side road G3.
The highest score was given to a determinant if the factor was found highly relevant to the roundabout size reduction. Lower scores were given to the size increasing determinants.
The community related determinants include:
- –
spacing of splitter islands on the main road approach legs, which, upon exceeding a certain limit, may require reconstruction of the bus stops, as may be located, for example near the analysed intersection, or longer pedestrian travel distances to these bus stops C1, this increasing the cost as a result (
Figure 11a and
Figure 17),
- –
the spacing of splitter islands on the main road approach legs increasing the pedestrian travel distances to the pedestrian crossings and the nearby parking areas S2, at the inlets of the main road, resulting in longer pedestrian crossings and longer accesses to nearby C2 car parks, this increasing the cost as a result (
Figure 11a and
Figure 17),
- –
spacing of splitter islands on the side legs, which, upon exceeding a certain limit in a constrained site may preclude provision of a cycle crossing through the side road C3, and thus the roundabout type may get the lowest score and may be discouraged for highly urbanised areas featuring a highly developed cycling infrastructure (
Figure 11a and
Figure 17),
- –
requirement of mountable apron areas over pedestrian crossing width C4, causing disturbance to pedestrian traffic, especially for people on wheelchairs, and thus this roundabout type may get the lowest score and may be discouraged for highly urbanised areas featuring a highly developed community infrastructure,
- –
requirement for traversable parts in the beginning of splitter islands C5, increasing the travel distance to pedestrian crossing and possibly affecting the traffic safety, thus resulting in a lower score given for this roundabout.
In the community related criterion the lowest scores were given to all the determinants that increase cost, compromise amenities and increase the pedestrian travel distances. As regards mountable apron areas, it was assumed that in urban areas over the pedestrian crossing widths the mountable apron surface areas should be minimised to avoid inconvenience to pedestrians with baby prams and people on wheelchairs. Thus, the determinants resulting in improved pedestrian and cyclist amenities, including shorter travel distances and small, if any, mountable apron areas facilities for pedestrians and cyclists, i.e. shorter access times and the lack or smaller areas of dirt mountable apron areas were given the highest scores.
The third criterion is related to the adopted traffic organization and has a major effect on the final throughput of the roundabout under analysis. However, focusing on the method of selection of roundabouts for constrained sites, this article does not deal with the throughput issues as such. The issue of turbo roundabout throughput estimation is presented in section 1, which is the literature review report. In deriving the traffic engineering determinants, in accordance with the conclusions of [
7,
8,
20,
22,
35], it was concluded that the roundabout type selection should be based primarily on the local site conditions, traffic flow requirements on the main or side roads, taking into account the site characteristics and the adopted traffic flow allocation. Therefore, the following traffic engineering determinants were adopted:
- –
the required number of straight-through traffic lanes on the roundabout carriageway, having a considerable effect on the roundabout throughput when dealing with high traffic volumes carried by the main road TE1,
- –
the number of the main road exit lanes, having a considerable effect on the roundabout throughput when dealing with high traffic volumes carried by the main road TE2,
- –
distance to adjacent junctions on the main road requiring provision of additional traffic lanes before them, which, in case of close proximity of such junctions, has a considerable bearing on the carriageway division into traffic lanes on the approach to the analysed roundabout and installation of appropriate road surface markings TE3,
- –
high left-turning traffic volume requiring, for example, provision of a dedicated traffic lane on the roundabout carriageway TE4,
- –
high right-turning traffic volume requiring, for example, provision of a dedicated traffic lane on the roundabout carriageway TE5.
It should also be checked whether a coordinated traffic management scheme had been applied on the main road between subsequent intersections. Where signalised junctions are in close proximity to the roundabout, two straight-through lanes on the roundabout carriageway and a hatched area after splitter island on the main approach legs were considered the best way to avoid roundabout entry queues. Then, appropriate lanes should also be provided before the next signalised junction.
Figure 19 represents the assessment of the adopted determinants, as defined above, in accordance with the roundabout selection chart in
Figure 9 for constrained project sites. The analysis of these determinants using three different assessment criteria allowed recommendation of the roundabout type depending on the site features.
Thus in the most constrained, low urbanisation degree areas LUDA, where the side road handles generally local traffic with DV1 design vehicles occurring only incidentally, type II roundabout ("flattened" turbo roundabout with a single lane on the main road approach leg) would be recommended as the option of choice. This choice will minimise the size and thus also the project cost and keep interference with the existing pedestrian and cycle infrastructure at a reasonable level. This means no mountable aprons on pedestrian and cycle crossings and the same travel distance to the roundabout, subject to correct placement. In addition, type II turbo roundabout considerably improves the flow of traffic turning from the main to the side road, resulting in a considerable increase of throughput, as compared to the existing junction.
Figure 20a shows a modified roundabout type II with no mountable aprons and smaller in size, as appropriate for traffic composed of passenger cars and municipal service vehicles DV2 only.
Figure 20b, in turn, shows the DV2 swept paths.
For built-up areas featuring well-developed community infrastructure BA requiring pedestrian and cycle crossings to run through splitter islands on the side legs, with less severe site constraints and a considerable share of heavy traffic on the left- and right-turn movements type VI roundabout (elliptical turbo roundabout with an elliptical central island and one exit lane on the main road approach leg) is recommended as the option of choice. This roundabout also provides all the pedestrian and cyclist amenities, i.e. it can be designed without mountable aprons encroaching on the pedestrian or cycle crossings. This roundabout is significantly larger (with almost two times greater splitter island spacing) than type II roundabout thus requiring less severe site restrictions.
In areas with rapidly growing commercial developments CDA type III roundabout (elliptical roundabout with two lanes on the main road approach leg) would be the option of choice owing to smaller spacing of splitter islands on the side legs. Its only advantage over the other roundabouts featuring two exit lanes on the main road approach leg is the smallest spacing of the side leg splitter islands, which in the case under analysis allows accommodating a cycle crossing on the western approach leg. The disadvantage of this option are 0.30–0.45 m wide mountable apron areas encroaching on the pedestrian crossing. However, type V roundabout was identified as the most recommended option for CDA sites when the roundabouts with two exit lanes were analysed for the three pre-determined criteria. Despite the greatest spacing of splitter islands on the main approach legs this option provides high throughput, smoother DV1 swept paths on turning movements, lack of mountable aprons on pedestrian crossing and much larger soft landscaping areas, considered an environment friendly feature. That said, one drawback can be noted in this particular case: cycle crossing cannot be provided in the quarter I due to the existing hotel car park fence. However, as mentioned, the elliptical roundabout with elliptical central island may be an option of choice only for areas with less severe constraints, this due to the large splitter island spacing (
Figure 11,
Figure 14 and
Figure 17).
Figure 1.
Examples of Egg turbo roundabouts located in constrained areas in vicinity of buildings in the Netherlands: (
a) Wierden (52°20'39.79"N, 6°34'23.27"E); (
b) Krimpen aan den IJssel (51°48'36.17"N, 4°26'7.30"E). (Source: Google Earth [
11]).
Figure 1.
Examples of Egg turbo roundabouts located in constrained areas in vicinity of buildings in the Netherlands: (
a) Wierden (52°20'39.79"N, 6°34'23.27"E); (
b) Krimpen aan den IJssel (51°48'36.17"N, 4°26'7.30"E). (Source: Google Earth [
11]).
Figure 2.
Examples of Egg turbo roundabouts located in constrained areas near lakes or canals in the Netherlands: (
a) Wierden (51°54'43.29"N, 4°38'34.10"E); (
b) Krimpen aan den IJssel (51°54'29.61"N, 4°37'23.73"E). (Source: Google Earth [
11]).
Figure 2.
Examples of Egg turbo roundabouts located in constrained areas near lakes or canals in the Netherlands: (
a) Wierden (51°54'43.29"N, 4°38'34.10"E); (
b) Krimpen aan den IJssel (51°54'29.61"N, 4°37'23.73"E). (Source: Google Earth [
11]).
Figure 3.
Examples of "flattened"roundabouts located in a constrained, built-up area in Slovenia: (
a) Koper (45°32'33.37"N, 13°44'21.78"E); (
b) Maribor (46°33'4.09"N, 15°38'59.64"E). (Source: Google Earth [
11]).
Figure 3.
Examples of "flattened"roundabouts located in a constrained, built-up area in Slovenia: (
a) Koper (45°32'33.37"N, 13°44'21.78"E); (
b) Maribor (46°33'4.09"N, 15°38'59.64"E). (Source: Google Earth [
11]).
Figure 4.
The turbo roundabout selection method for constrained areas is presented in IMRAD diagram.
Figure 4.
The turbo roundabout selection method for constrained areas is presented in IMRAD diagram.
Figure 5.
Location of the selected junction on DK13 national road in the suburbs of Szczecin. Source: own work using the Szczecin Master Plan image [
25].
Figure 5.
Location of the selected junction on DK13 national road in the suburbs of Szczecin. Source: own work using the Szczecin Master Plan image [
25].
Figure 6.
Discouraged parking options: (a) Parking on the local street; (b) Improper parking near Biedronka supermarket; (c) Entry to the "illegal" parking site from the pedestrian crossing; (d) Illegal parking site. (Photo by: A. Sołowczuk).
Figure 6.
Discouraged parking options: (a) Parking on the local street; (b) Improper parking near Biedronka supermarket; (c) Entry to the "illegal" parking site from the pedestrian crossing; (d) Illegal parking site. (Photo by: A. Sołowczuk).
Figure 7.
Constraints and selected parameters of Egg turbo roundabout located in the outskirts of Szczecin – a case study: (
a) 0.7 m wide raised separation lane, inner lane started in the old manner; (
b) 0.24 m wide separation lane, inner lane started in a new manner. Source: own work on a satellite image background, roundabout site example from Google Earth [
11].
Figure 7.
Constraints and selected parameters of Egg turbo roundabout located in the outskirts of Szczecin – a case study: (
a) 0.7 m wide raised separation lane, inner lane started in the old manner; (
b) 0.24 m wide separation lane, inner lane started in a new manner. Source: own work on a satellite image background, roundabout site example from Google Earth [
11].
Figure 8.
Examples of different separation lanes used in Poland: (a) Szczecin (53°25'16.84"N, 14°31'40.99"E) – separation lane consisting of line markings only; (b) Dziwnówek (54° 1'56.65"N, 14°48'26.53"E) – traversable splitter island and line marking as the approach separation; (c) 0.24 cm wide separation consisting of a line marking and U-25 raised separator; (d) detail of U-25 separator attached to the pavement on the line marking. (Photo by A. Sołowczuk).
Figure 8.
Examples of different separation lanes used in Poland: (a) Szczecin (53°25'16.84"N, 14°31'40.99"E) – separation lane consisting of line markings only; (b) Dziwnówek (54° 1'56.65"N, 14°48'26.53"E) – traversable splitter island and line marking as the approach separation; (c) 0.24 cm wide separation consisting of a line marking and U-25 raised separator; (d) detail of U-25 separator attached to the pavement on the line marking. (Photo by A. Sołowczuk).
Figure 9.
Turbo roundabout selection diagram step by step for constrained project sites.
Figure 9.
Turbo roundabout selection diagram step by step for constrained project sites.
Figure 10.
Turbo block to lay out "flattened" roundabouts: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 10.
Turbo block to lay out "flattened" roundabouts: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 11.
Examples of "flattened" roundabouts: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 11.
Examples of "flattened" roundabouts: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 12.
Examples of swept path analyses for "flattened" roundabouts left-turn movements: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 12.
Examples of swept path analyses for "flattened" roundabouts left-turn movements: (a) With two exit lanes on the main approach legs – I type; (b) With one lane on the main approach legs – II type. Source: own work.
Figure 13.
One exit lane at main approach legs. Turbo block for laying out elliptical turbo roundabouts: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 13.
One exit lane at main approach legs. Turbo block for laying out elliptical turbo roundabouts: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 14.
Examples of elliptical turbo roundabouts: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 14.
Examples of elliptical turbo roundabouts: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 15.
Examples of swept path analyses for elliptical roundabout left-turn movements: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 15.
Examples of swept path analyses for elliptical roundabout left-turn movements: (a) With two exit lanes on the main approach legs – III type; (b) With one lane on the main approach legs – IV type. Source: own work.
Figure 16.
Turbo block for laying out elliptical turbo roundabouts featuring elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 16.
Turbo block for laying out elliptical turbo roundabouts featuring elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 17.
Examples of elliptical turbo roundabouts with an elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 17.
Examples of elliptical turbo roundabouts with an elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 18.
Examples of swept path analyses for elliptical roundabouts featuring an elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 18.
Examples of swept path analyses for elliptical roundabouts featuring an elliptical central island: (a) With two exit lanes on the main approach legs – V type; (b) With one lane on the main approach legs – VI type. Source: own work.
Figure 19.
Analysis of the adopted determinants and selection of the turbo roundabout type for constrained site projects.
Figure 19.
Analysis of the adopted determinants and selection of the turbo roundabout type for constrained site projects.
Figure 20.
Example of "flattened" turbo roundabout with a single traffic lane on the main road approach leg, recommended for areas of low urbanisation degree LUDA – single-family neighbourhoods or woonerf: (a) Roundabout; (b) Swept path DV2. Source: own work.
Figure 20.
Example of "flattened" turbo roundabout with a single traffic lane on the main road approach leg, recommended for areas of low urbanisation degree LUDA – single-family neighbourhoods or woonerf: (a) Roundabout; (b) Swept path DV2. Source: own work.
Table 1.
Parameters of the selected DVs based on the guidelines of [
27].
Table 1.
Parameters of the selected DVs based on the guidelines of [
27].
Design vehicle data |
Vehicle Details |
L |
MABS1
|
L2 |
F |
WB |
B2 |
WB2 |
DV1 |
|
16.50 |
70 |
13.43 |
1.62 |
4.81 |
3.92 |
6.15 |
DV2 |
|
9.90 |
– |
– |
1.53 |
4.77 |
– |
– |