The paper aimed to assess the performance of the designed systems under various operating conditions. Some of the simulated instances for performance evaluation include stand-alone mode, grid-connected mode, and transition from one mode of operation to another. In each case, normal operation, fault occurrences, increase in power generation, increase in loading system, and sudden de-energized of RESs are some of the simulated and evaluated in each instance.
5.1. Stand-alone mode of operation
In this scenario, the utility grid is intentionally decoupled from the microgrid so that both networks supply power to the connected loads independently. In this mode, two cases were simulated and analyzed.
The system parameters were simulated without considering any disturbances on the utility and microgrid. The storage systems were set to charging modes. The simulation results are shown in
Figure 11 (a)–(c).
Figure 11 (a) shows the voltage, current, and power (active and reactive) measured at the PCC; Figure11 (b) shows the voltage and current measured at some selected buses from the main grid and MG, and Figure11 (c) shows the utility grid and community (microgrid) battery energy storage characteristics. As indicated in
Section 4.4, the designed system must be operating within the acceptable minimal and maximal voltage ranges of 0.88 pu and 1.1 pu respectively. From
Figure 11 (a) and (b), the systems complied with the maximum and minimum voltage ranges because there were no disturbances, such as faults or changes in the loading system, on the grids.
In this case, the system is subjected to a three-phase fault at line 4 between bus 3 and bus 4 on the utility grid side.
Figure 12 (a–b) shows the response of the system at PCC and the selected buses on the utility grid and microgrid during the fault. According to the waveforms in
Figure 12 (a-b), the fault affected only the utility grid for a period of 0.08 to 1.12 seconds and did not influence the microgrid side, as indicated in Figure (b) microgrid voltage and current.
5.2. Grid-connected mode
The system's grid-integrated simulation results are presented in this section. The case studies include faults, transitions from autonomous mode to grid-connected, increases in total generation on the microgrid, sudden disconnection of a micro-source, and changes in the loading system of the microgrid.
The system is exposed to a three-phase fault between Bus 5 and Bus 6 on the utility grid.
Figure 13 (a–b) shows the performance of the system during the fault. The voltage, current, and power waveforms at PCC are shown in
Figure 13 (a), while
Figure 13 (b) shows the voltage and current waveforms on the utility and microgrid. The fault is set to occur within 0.08 seconds and 0.12 seconds on the system, and it was observed that the fault effect spread all over the utility grid and microgrid, as shown in
Figure 13 (b).
Case 2: Transition from stand-alone to grid connected.
This section evaluates the grid performance during the transition from grid-connected to standalone.
Figure 14 (a-c) shows the voltage-current waveforms from the utility grid, while
Figure 14 (a-b) shows the microgrid performance during the transition mode of operation.
To ensure a smooth transition and ensure grid stability, storage systems were activated to support the grid. As can be observed in
Figure 14(b), after a few seconds of transition, the utility grid storage system was engaged to deliver extra power to the MG. The upward movement of the SOC indicates the charging mode of the battery, while the downward movement indicates that the battery was discharging, delivering extra supply to the system. To avoid overvoltage on the microgrid side, the utility battery was switched to charging mode, as shown in
Figure 14 (d).
Figure 14(a) shows voltage, current, and powers at PCC during the transition from grid-connected to stand-alone mode of operation. At t = 0.08s, the shift from grid-connected to stand-alone mode was activated during this period, and there were occurrences of ripple on the entire system voltage before the system became stable again.
In this case, the small hydropower plant source increases its power generation by 0.9 MW at 0.12 s for almost half a second, after which the storage systems are activated to provide support to the grid.
Figure 15 (a–d) shows the system performance during an increase in microgeneration sources.
For a period of 0.1 s, the microgrid experienced overvoltage before the storage system was activated, as seen in
Figure 15 (c).
Figure 15(a) is the PCC voltage, current, and power during an increase in microgrid generation.
Figure 15(a) depicts the PCC voltage, current, and power experience during the activation of the storage system for storing the excess power. The active and reactive power increased before the system storage was activated, and the microgrid system also switched to grid-connected mode. To ensure system stability during the increase in power generation, energy storage system switches were energized to charging mode to store the excess power generated, as shown in
Figure 15 (b and d).
The scenarios of increases and decreases in microgrid system loading are discussed and analyzed in this section.
Figure 16(a-b) shows the performance of the system during an increase in the microgrid loading system, while
Figure 17(a-d) shows the operation of the system during a reduction in system loading.
Figure 16(a) shows the voltage, current, and powers at PCC from 0s to 0.08s, while
Figure 16(b) shows the utility grid and microgrid voltage and current. During an increase in microgrid system load, there is a reduction in microgrid voltage and current during the increase in load from 0s to 0.8s; on the contrary, the utility grid maintains its normal voltage and current level during the period of 0s to 0.08s. At 0.08 s, energy storage systems were activated to discharge mode to provide support to the microgrid; during this period, the microgrid system adjusted itself back to normal voltage and current, as can be seen in
Figure 16(b), nevertheless, the microgrid voltage experienced a little ripple. However, the utility grid suffers a reduction in voltage and current due to the transition from stand-alone mode to grid-connected mode; however, the voltage and current still operate within the acceptable range of 0.85 pu to 1.0 pu.
Figure 17(a-b) shows the performance of the system during a reduction in the microgrid loading system.
As stated in
Section 3.1, each load in the microgrid system represents a street in a community; thus, it is assumed that one street is suddenly out of service in the community supplied by the microgrid system. The response of the system to this situation is presented in this section.
Figure 17 (b) shows that the microgrid maintain normal and acceptable voltage and current limit until 0.09 s when a street in the community was suddenly out of service for a period of 0.14 s when the storage systems were activated to ensure stability on the grid. However, the microgrid experienced overvoltage during the period when the street was out of service, as seen in Figure (b). As soon as the utility grid was activated and connected to the microgrid and energy storage systems were activated to charging mode to store the excess power, the microgrid system voltage and current were restored to their normal operation, as seen in
Figure 8(b), from 0.14s to 0.2s.
In this case, the small hydropower plant was suddenly out of service.
Figure 18 (a–b) shows the system's response to the situation.
Figure 18(a) shows single-phase voltage and current at the PCC. As can be seen, the system experiences a voltage and current reduction for a period of 0.1s when the micro-source is deactivated. Furthermore,
Figure 18(b) shows the voltage and current, of the utility grid, the system experiences voltage and current reduction from the period of the micro-source deactivation. Also, the microgrid experiences voltage sag during the period of deactivation (0.08s to 0.1s). However, the microgrid was unable to restore to its normal operating condition even though the storage systems were active in charging mode, as shown in
Figure 18(b).
-
1.
Overview of microgrid limitation
The inconsistency of power supply from diverse RESs, like solar and wind, poses a restriction to renewable energy-based MGs. It is also challenging to resynchronize and coordinate the microgrid with the utility grid when the fault on the grid has been cleared. Another limitation to the utilization of microgrids is the implementation of an effective protection mechanism. Furthermore, power quality issues are another limitation of microgrids [
110].
Conclusion and Future Works
This paper presents a comprehensive review of MGs and evaluates the system performance when integrated into the low-voltage distribution network, considering different operating scenarios. The paper evaluates the system performance both in grid-connected and island modes of operation. Normal operation, fault analysis, an increase in the generating capacity of microgrids, an increase in system loading, and a sudden loss of energy sources from microgrids are some of the simulated and evaluated cases considered in the paper. In addition, the transition from grid-connected to stand-alone mode, as well as re-synchronization with the main grid, were validated. Finally, the limitations of microgrid implementation were reviewed. Power quality issues and grid synchronization and protection during the transition from the grid-connected mode to stand-alone modes are some of the challenges identified during the performance evaluation carried out in this paper. It was observed that the effects of the fault escalated throughout the system during fault analysis on either side of the system during grid-connected mode. Therefore, microgrid stability, prevention of power quality issues, and effective energy storage systems for grid stability at low-voltage distribution networks are some of the proposed topics for future work.