1. Introduction
All electrified transportation systems (ETSs) of the guideway type are affected by return current leakage from the guiding track into the soil, coupling to structures nearby. Examples of victims are sleepers and track bed [
1,
2,
3], platform screen doors and other metallic parts at platforms [
4], viaducts, bridges and building foundations [
5,
6], pipelines and reservoirs [
7,
8,
9], etc., besides corrosion of power system earthing system and saturation of transformers [
10,
11,
12]
In general the effect of current flow through the interface of a metal with an electrolyte solution (such as the soil itself, or cement for concrete structures) causes corrosion, affecting solidity and durability of said structures. The first victims are the sleepers and rail fasteners [
13,
14,
15]: in case of a local insulation loss they may become a hot spot, with a significant increase of current density, although possibly the overall track leakage is acceptable over a longer length.
For this reason preferred verification methods should be able to operate on a local basis, that is for short enough track sections, providing thus valuable indication for a rapid visual inspection and repair. However, they should be easily applicable also to longer stretches, favoring a rapid diagnostic of a long line, at least as a periodic preliminary check.
Track current insulation phenomena besides the spatial dimension develops through time, considering that testing, monitoring and evolution of insulation degradation have different time scales:
from seconds to minutes if applying test signals in off-service conditions: time intervals of seconds are necessary for polarization of electrolytes in the test circuit to take place, after which test quantities can be measured with care to reject external noise with a sufficiently long observation times;
from hours to weeks if using track electric quantities during train service:
from days to years considering the normal evolution of track insulation degradation, with aging of insulating materials, pollution of surfaces, stagnation of water, etc.
The relevance of stray current assessment in general is proven by the consequences of corrosion: weakening of structures within the right of way and nearby, impairment of track stability, spillage and breakage for pipes and reservoirs, more onerous repairs and corrective maintenance rather than a normal preventive operation.
A significant modeling and simulation effort has developed through the years in order to understand the coupling mechanisms and to globally address the problem with suitable design choices and provisions [
16,
17,
18,
19,
20]. Prevention and compensation of stray current is in fact taking place by means of various systems: optimization of a traditional track and transit system [
21,
22], passive stray current collection systems [
23], traditional track voltage limitation [
4,
24], active track potential control and redistribution of traction current [
25,
26].
Stray current monitoring systems are gaining popularity [
27] as they provide feedback on the health status of an important asset, although interpretation of collected data and identification of necessary actions with the right timing are still complex problems that are unsolved [
28].
The measurement of voltage and current quantities at track, substation negative and stray current collection is as accurate as the combination of the used probes and sampling channels. However, stray current evaluation by such system necessitates an initial tuning (and, possibly, a periodic verification) that depends on the assessment of current track insulation: sources of variability beyond instrumental uncertainty, including site conditions, are thus considered in this work focusing on standardized methods.
Track insulation measurement is disciplined by the standard EN 50122-2 [
29] (equivalent to the IEC 62128-2 that is still at its 2013 version [
30]), that distinguishes three methods:
method A.2, track insulation with civil structure: the important point that makes this less invasive compared to method A.3 is that the running rails are continuous and do not need to be sectioned; however, the test setup is more complex, with more measured quantities involved and an overall worse accuracy; the evaluation of uncertainty and optimal test conditions is discussed in
Section 2;
method A.3, track insulation without civil structure: the presence or absence of the civil structure is not the relevant point here, as the running rails must be sectioned to the desired length, either by cutting them or exploiting the presence of insulating rail joints; this is a more accurate method and should be preferred whenever possible, especially for high track insulation values;
method A.4, lateral voltage gradient method in open area sites: this method measures the voltage gradient in the soil caused by running trains, with the field laterally extending from the tracks at two points at different distances; it is suitable for large open areas, but necessitates access to soil as homogeneous as possible and may thus be disturbed by buried structures and installations, such as in an urban context.
Besides the metrological aspects, such as variability and uncertainty, the three methods have different impact and cost, in terms of organization and preparation, including the necessary operations to set up the test and to bring back the system in pristine conditions. These in fact are the real cost driving factors and, in general, methods that can be overlapped to the track without affecting its structural integrity should be preferred (in our case methods A.2 and A.4). In addition, the overall time duration to fit within the engineering hours and the compatibility with commercial traffic for systems already in operation are two other relevant aspects: method A.2 of course cannot be used in the current implementation in the presence of trains and method A.3 is absolutely not compatible with train runs, whereas method A.4 exploits the normal line traffic as the test signal (and provides track voltage information as well).
The purpose of this work is to analyze and discuss three methods for track insulation assessment that are reported in the Annex A (informative) of the EN 50122-2 standard [
29,
31]. Their description is unchanged since more than 20 years and the test experience of several years, including discussions during test campaigns, have uncovered various points that are vague, not enough detailed and, in some cases, have a significant impact on the quality of the results and their uncertainty.
Section 2,
Section 3 and
Section 4 consider the three methods separately, discussing setup and equations, providing practical considerations and identifying relevant factors, and then proceeding to the estimate of variability and uncertainty. Each section provides numerical examples and analyzes experimental data from past test campaigns. The outcomes are then summarized and discussed by confronting the three methods in the conclusions in
Section 5.
2. Method A.2: continuous track, line closed to traffic
2.1. Method description and setup
The method basically achieves the estimation of the leaking current in the track section under measurement (from now on simply “track section”) by subtracting the rail current flowing outside the track section (indicated by
,
for the leftmost position and
,
for the rightmost position) from the applied source current
. The setup annotated with the relevant electrical quantities is shown in
Figure 1.
The intensity depends on the used voltage level and the overall resistance-to-earth of the entire system, that is of the tracks that can be considered electrically continuous from the point of injection of the test current. It is evident then that the current does not change with the location and injection point. In addition, a very well insulated system will sink a low test current anyway. The use of higher test voltages of course increases the test current intensity, but this is usually done not only for this purpose, rather to provide a test level that is much larger than the internal voltage barriers due to oxidized surfaces and electrolytes, ruling them out as a major source of error. To this aim polarity reversal may be used, canceling to some extent such offset voltages. A 50 V is a common choice, as it does not poses serious problems of electrical safety.
The current flowing along the rails in the measured track section causes a voltage drop (indicated as
,
,
,
in
Figure 1) that for moderate current intensity is negligible, but in a general perspective should be included.
The rail current leaving the track section is measured either by a direct measurement or by means of the voltage drop on the rails themselves (as suggested by the EN 50122-2). The former approach is hindered by the lack of such large openable DC current sensors (Rogowski coils work in AC). The latter approach is commonly used and relies on the measurement of a small voltage drop in the order of some
. The voltage drops
,
,
,
are given by the local rail resistance
,
,
,
multiplied by the flowing current, so that the latter can be estimated by measuring or assuming the rail resistance values.
The precaution is not to include welded points in the rail segment that is used to measure each respective voltage drop. As indicated by the EN 50122-2 such welding point could add up to 5 % of longitudinal rail resistance, impacting on accuracy. In addition, the rail length
across which the voltage drop is measured, is prescribed to be 10 m [
29]. When the intensity of the test current
is not large (for example due to an overall well insulated system) and the voltage drop signal intensity is not sufficient, a doubled length brought to 20 m is a sensible compromise to increase it. In general, the rail resistance is taken from datasheets or measured at the location where tests are carried out and the resulting per-unit rail resistance value
is unique for all four voltage drop measuring points.
For DC and very low frequency the relevant rail resistance is the DC value, that can be assumed in general between about 33m
/km–40m
/km, as documented in [
32]. The most commonly used rails for e.g. metro applications are of the UIC 54 and UIC 60 type, then with different hardness levels, providing a resistance in the order of 36 m
/km and 33 m
/km, respectively. It is apparent that with a rail current flowing outside the test section of e.g. 10 A, the expected voltage drop is
mV and
mV, respectively, over a 10 m voltage drop measuring rail segment.
The final complete formula for the determination of the track-to-earth resistance
is given by
where
voltage quantities are intended as difference between the on and off condition value, i.e. for example
. Multiplication by
L expressed in
gives the per-unit insulation resistance to compare with limits.
It is observed that the EN 50122-2 [
29] reports this formula incorrectly, as the shown test setup is for the whole track (so for the estimate of the track-to-earth insulation), but the current quantities are only 2, taken for one rail only).
2.2. Practical factors
Voltage drop readings are generally affected by a significant common-mode disturbance (any time the signal is read by a non-insulated voltage probe), as well as pre-existing flowing current, e.g. at the utility frequency ( 50 Hz) or fluctuating at low frequency. The reason is the unavoidable influence of external sources, in particular if the system is already energized and operating, so that substations during engineering hours have still the negative connected to the track. The unavoidable difference of potential of the utility earth at different locations causes a current flow through the tracks.
The use of rail current probes would solve the problem of the small longitudinal voltage drop across rails and would provide a floating signal that rejects the common-mode rail potential. Possible probes are Hall effect and fluxgate ones that are large enough to embrace the rail section or Rogowski coil, provided that the test is carried out with a low-frequency AC signal, but not really a pure DC component.
In addition, if carrying out the test with a DC source, offsets are quite relevant being of the same order of magnitude of the expected voltage drop (see the previously estimated 3.3mV–3.6mV).
A general optimized arrangement for the classical setup (using voltage probes, as shown in
Figure 1) requires a short-circuit connection (cross bond) between rails, creating a reference node at the remote (A or B) location, to which both voltage drop readings are referred (shown in
Figure 2).
Galvanic isolation and rejection of common mode can be also achieved by using differential voltage probes, that, however, introduce a signal reduction (such as a 1:10 factor) and additional noise (being active devices). The use of rail current probes instead would solve the problem tout court providing a cleaner floating signal: Hall-effect or fluxgate probes of this size do not exist to authors’ knowledge, so that a Rogowski coil should be used, that requires AC test signals. Some Rogowski models have in reality a frequency response extended down to a few Hz and good droop capability, so that an alternating DC voltage could be exploited.
Using instead a real AC signal (such as provided by an amplifier) makes the method more complex (signal generator and amplifier to add), but provides a clean current measurement. It is only a formal issue accepting that track insulation resistance values measured with a pure DC current or a low-frequency AC signal are comparable. To this aim two points need to be checked regarding the equivalent circuit of a running rail.
The longitudinal impedance of a running rail is made of an internal inductance term and an AC resistance term, both accounting for AC effects such as skin effect and hysteresis, and related losses [
33,
34]; values for low current (
) amount to about
H/m and 100
/m, with the former contributing less than 25
/m of inductive reactance at 50 Hz.
The stray capacitance of a running rail amounts to less than 10 nF/m (obtained by multiplying by 2 the values shown in [
35]), providing more than 300
of capacitive reactance, easily shunted by the transversal track insulation term considered here.
We may conclude that the equivalent circuit of a running rail in AC at low frequency does not differ from that at DC for the purpose of determining the track-to-earth insulation resistance, with the exception that the longitudinal resistance (and impedance) are larger and cannot be used any longer reliably for the determination of the flowing current. The measurement of the flowing rail current could be achieved then by using Rogowski coils that ensure a complete rejection of common-mode signals and a more favorable signal-to-noise ratio. Another method of rail current measurement that allow train circulation and can be a semi-permanent installation is by means of close-up sensors, based on inductive effect [
36], arrays of such elementary sensors for better reconstruction [
37], or alternative methods such as Hall or magneto-resistive effect [
38].
The locations A and B and the central point of injection of the test signal could be separated by a hundred meters, as well as 1 km or so, so that connecting all channels to a single data acquisition system is a problem not only for the length of the necessary cables, but for the consequential noise pick up of such cables. Separate measuring stations are preferred, necessitating as a matter of fact of more personnel and instrumentation.
2.3. Variability and uncertainty analysis
Variability is considered by listing the external factors that have a significant influence on the results and that should be accounted for in the uncertainty analysis. The identification of such factors and their spread is thus a necessary initial step for the uncertainty analysis, that focuses on (
3).
The rail current
(with “X” standing for F1, F3, G1, or G3) is estimated by measuring the rail voltage drop over the rail section of length
and applying (
1). The uncertainty is then
where the uncertainty of the voltage reading
is derived directly by the employed instrumentation and that of the rail resistance
is related to its variability, and to the availability of measured values for the specific system and track section, or the use of tabular data.
For
it is observed that the reading scale is quite low, in the order of a few
, whereas the track voltage readings are in the more favorable range of tens of
. The measuring multimeter/data logger must be carefully selected as apparently good items of equipment might have quite different performance in the
range. AN overview is provided in
Table 1.
From the uncertainty estimates above, it is clear that extreme care must be adopted for the voltage drop measurement and suitable instrumentation must be selected. Medium-performance portable multimeters such as Fluke 117 are clearly inadequate, and a high-performance multimeter such as the H29S barely achieves the minimum necessary performance (about 8 % of uncertainty budgeted for the rail current measurements and the remaining 6 % for the three track voltage measurements and the test current measurement). Specialized portable data acquisition systems, such as Minilog2, achieve a satisfactory target performance of about 1 %, whereas generic ones (e.g. National Instruments card) achieve the same performance of a high-performance multimeter.
The uncertainty of the rail resistance values is not rather influenced by the instrumental uncertainty of the rail resistance measurement, but the variability between rails of the same section and in general of different sections (from different production batches or different manufacturers). The problem is discussed in [
32], where various examples of experimentally determined values are provided as well.
The expression at the denominator of (
3), where the current leaking within the track section is determined by difference of the injected test current
and the “escaping” rail currents (flowing outside the section), is inherently exposed to measurement errors especially for well insulated tracks. Let’s assume that we test with a test voltage
, resulting in a test current
, a track section of 100 m of a well insulated system, such as one with 100
km insulation, resulting in
for the measured section. Roughly the expected leaking current is given by
. The 4 escaping currents (
,
,
,
) must thus give about
A in total, so about
A each, or in the extreme case of a measurement taken near the beginning of the line, two rail currents will be at about 5 A and the other two approximately zero. A 1 % uncertainty for each of these currents will cause a measurement error
, that is exactly in the range of the target value of the leaking current. It is easy to see that a 200 % measurement error can be reached under the fair assumption of random combination of the four error terms, compared to
. The method thus provides acceptable accuracy only if:
a long track section is tested: a 10 times longer track ( 1 km) will provide a 10 times larger and the resulting errors will be this time about 20 % (large, but acceptable);
a track with poor insulation is tested: similarly an insulation level of only 10 km will provide a similar distribution of the errors, so a 10 times larger , again reaching an uncertainty in the order of 20 %.
The uncertainty of (
3) can be estimated by formally calculating the propagation of uncertainty for each of the relevant quantities. The four rail current terms at the denominator and the three track voltage terms at the numerator have identical effect and may be calculated only once.
The current terms at the denominator form a difference that is handled by using the absolute and not the relative error, so that they are not ready to be expressed in terms of uncertainty. For a difference
, the following expression holds
. It is easy to see that
A indicates
and
B indicates
, and their difference may be indicated for simplicity as
. These expressions, however, can be manipulated based on the assumption that the result is small as
and
are almost equal (quite true for a well insulated system): the difference is thus expressed as a small multiplying coefficient
k of the half sum, or of either of the two terms with an acceptable degree of approximation.
where the rightmost equality is justified by the fact that the uncertainty of the measured
is much larger than that of
when the used methods are rail voltage drop and current clamp (or shunt), respectively.
The three voltage terms at the numerator follow a similar rule, that is the summation is managed by using the absolute error, or in other words the dispersion or variance, and not its relative (or normalized) version. Assuming that they are measured with the same instrumentation (such as identical multimeter or different channels of the same data acquisition system), their variances are identical, so that the resulting variance of the average is one third of them: .
It is possible thus to estimate the uncertainty considering (
3) as a pure ratio, having introduced the factor
k:
The two terms then correspond to:
The uncertainty of
is then given by
The reciprocal of the factor k is the amplification effect observed above for the resulting uncertainty.
3. Method A.3: sectioned track, line closed to traffic
3.1. Method description and setup
This method requires the interruption of the longitudinal electrical conductivity of the rails at the two points that define the measured track section of length
. Measuring then the electrical insulation between a rail segment and the earth is a straightforward volt-amperometric measurement: a voltage
is applied between the rail and the earth at one of its ends. The measurement of the flowing current
must be accompanied by the measurement of the rail-to-earth voltage not only at some intermediate preferred position
(the EN 50122-2 indicates a minimum distance of 50 m from the injection point, but not a maximum one), but also at the opposite end, in order to estimate the voltage drop along the rail or track
. The difference between the two voltages is required by the EN 50122-2 [
29] to be less than 10 %, but nothing is said on how to remediate in case this requirement is not fulfilled. The effect on the resulting track insulation is discussed below in sec.
Section 3.2.
The method could be applied to a single rail or a whole track. The latter is a necessity in the presence of frequent rail-to-rail bonds, including coupling bonds for track circuits that at DC are short-circuit connections as well. The setup is shown in
Figure 3 for the measurement of the whole track.
The EN 50122-2 proposes a simple relationship like
where
L is expressed in
. Again, multiplication by
L expressed in
gives the per-unit insulation resistance to compare with limits.
This method is more accurate than method A.2 with a minimum number of involved quantities and no need to estimate the current flowing in each rail. Assuming again a test voltage up to 50 V, for rail segments of some hundreds meters, the flowing test current ranges from some
up to a fraction of
for the most common track insulation values and can be conveniently measured with an amperometer (multimeter). The method is exposed to some variability as a consequence of variable or not well specified parameters (earthing resistance of the test supply, distance
d of the intermediate voltmetric terminal, overall length of the track section
L) that are reviewed in
Section 3.3 based on results in [
39,
40,
41].
3.2. Practical factors
The earthing of the power supply providing the test voltage and the earth reference for the voltmetric terminals at P and Q can be implemented in various ways, based on practical convenience:
an earth electrode may be used driven into the soil at a convenient distance from the tested track (the EN 50122-2 requires 30 m minimum); the reason for such distance is avoiding distortion of the electric field in the soil if too close; the earthing resistance is quite limited anyway, for which even in good soil values lower than about 50 are difficult to achieve, so that this earthing system is suitable for the voltmetric terminals, but not for the test supply;
using the remaining part of the system before the injection point and the rail cut earthing the test supply with a resistance
usually of some
; with systems of limited length, instead,
reaches too high values; the influence of this parameter was evaluated in [
39] and is considered later in
Section 3.3;
earthed parts, such as cable trays, sharing the earthing resistance of the power distribution system, usually in the order of 1 or less, can be used for both purposes;
the concrete structure supporting the track, if provided of reinforcement which is usually accessible through bonding terminals welded to it.
Since in many cases the electrical isolation of the track section is achieved by pre-existing IRJs, choosing too a short section length (with a larger insulation resistance value) exposes the results to the influence of the far-from-the-ideal isolating performance of the IRJ. For example, a well insulated system with amounts to 1 for a section length of 100 m; the measurement could be compromised by an IRJ with insulating resistance in the order of 10 (still barely acceptable in the sense of the standard).
3.3. Variability and uncertainty analysis
This method, as the most accurate one, was assessed for sources of variability in [
39,
40,
41].
The test should be done by measuring
in on and off conditions, so compensating for pre-existing potentials. It was observed in [
39] that practical measurements show a significant rapid decay of the potential during de-polarization and that a lack of synchronization of a few seconds could cause a significant error. In fact the EN 50122-2 does not clarify the procedure to adopt to take the off-condition reading: only for insulating rail joint efficiency it specifies “directly after the switching off”, that, however, does not clarify if we are speaking of a fraction of a second or some seconds. The off potential is supposed to be subtracted from the on reading, aiming at compensating extraneous voltages, but the rapid decay (so with a steep slope) implies a significant error for timing errors in the first second or so. A better technique is that of polarity reversal, that compensates for offset voltages and other bias voltages.
The effect of rail resistance was also considered on the two terminal voltages and , and on the estimated track insulation. Considering the value of , as determined approximately by , a worst-case scenario of maximum voltage ( 50 V) and lowest track insulation ( 2 /km) would bring to . Recalling the track resistance in the order of 16.5m/km–18m/km, this causes a maximum longitudinal voltage drop of V/km, that is less than 1 % of the applied voltage. The requirement is thus always fulfilled.
The influence of the rail resistance was quantified in [
39] by simulation, using an equivalent circuit. The variability of the track-to-earth conductance
is shown in
Figure 4, for a reference case
, corresponding to 100
km. The effect of rail resistance and the consequential longitudinal voltage drop is stronger for longer track sections, as expected, as the overall rail resistance is larger and at the same time the shunt resistance to earth is smaller. For track length up to 1 km the influence of the rail resistance is below 0.5 % and can be made smaller by bringing the voltage terminal towards the mid of the section, rather than closer to the injection point.
After the variability sources related to parameters and setup have been assessed, the uncertainty
per se of (
9) is straightforwardly evaluated by propagation of uncertainty from the measured quantities for a simple V/I resistance estimate.
The expression indicates a direct dependence on the uncertainty of the voltage and current measurements, that are both carried out in ideal conditions, that is for a conveniently large value the former and with a clamp (or shunt) the latter. Total instrumental uncertainty values as low as 0.5 % can be easily attained; overall uncertainty may be estimated as low as 1 % including variability as in
Figure 4, excluding the problem related to the off potential. For this careful selection of timing is important as the off potential is not only taken for a large reading as track voltage, but also for the low-value readings of the rail voltage drop where even small errors are relevant (although de-polarization in such readings should not take place, but fluctuation do).
4. Method A.4: lateral potential gradient in normal service
This method exploits the running trains as a source of track potential fluctuations, by which estimate the track-to-earth insulation. The track is in normal conditions and does not need any special arrangement; potential is measured by connecting one conductor not interfering with the dynamic train gabarit (so with no impact on traffic and safety).
4.1. Method description and setup
This method is well suited for open areas where the track runs at grade without continuous civil structures to use as potential reference, as it may occur in urban and suburban at grade line sections. In this case a remote potential reference is taken by means of a vertical electrode driven in soil and the measurement of the current dispersion and consequential field gradient in soil is local, not distributed along the track section we have considered so far in the two previous methods.
The method is described in
Figure 5 that reports a sketch of the setup and most relevant quantities. The setup focuses on a transversal section of the line assumed of negligible longitudinal size, but minor contributions from adjacent track sections cannot be ruled out. The EN 50122-2 and the technical literature do not provide any indication on this to authors’ knowledge.
The two rails of an assumed single-track layout are separated by the quantity s (with good approximation corresponding to the track gauge, that is in reality measured between the internal edges of rail heads); the two external electrodes E1 and E2 are located in natural soil at distances a and from the nearest rail, with b the separation of the two electrodes.
The basic equation for the determination of the track-to-earth conductance
is based on the assumption of an inverse dependency with distance for the electric field in the soil.
where
is called “stray current transfer ratio”, the factor “1000” adjusts for expressing the conductance per km, and
is the soil resistivity expressed in
(discussed then below in
Section 4.2). The quantity
s takes the value of
for single-track cases and
for double-track ones.
The 2010 version of the EN 50122-2 [
31] reported two different formulations for the cases of single- and double-track layout, as shown in (
12) and (
13), respectively, using the notation
and
. The quantities
and
stand for the track gauge and the inter-track separation (measured from track axes), respectively. The new 2021 version [
29] uses only one equation (
11) and does not make such distinction, saying simply that for the single-track case the quantity
and for the double-track case the overall conductance must be divided by 2 and that the quantity
s becomes the inter-track-axes distance
.
The numerical difference between this different formulation of the two versions of the standard is considered below in
Section 4.3.
The quantity is said in the standard to be determined as the linear regression of the “rail potential gradient”, as if there is a derivative operation involved. In reality this point is not well explained, with confusion between small letters and big letters for the same quantities and introducing a “delta” symbol that is not then supported by any equation nor appears in the figures.
Simply, is the angular coefficient of the linear regression of the collected rail potentials vs. the inter-electrode potentials , using electrode E2 as reference.
The estimate must be carried out with a significant number of well distributed samples, to avoid ill conditioning of the linear regression estimate: in other words, a short time record with all potential readings having similar values causes indeterminacy, whereas a longer record with several train passages creates an elongated cloud of points that provides a more robust estimate.
4.2. Practical factors
This method is suitable for at grade scenarios in particular in suburban contexts, but requires free space laterally to the track of minimum 80 m (as per recent 2022 version of the EN 50122-2, but only 30 m in the older 2010 version, that was more manageable).
In addition, access to natural soil near the track to place the first electrode is also necessary. This distance a has no minimum specification, but the standard warns that such electrode should be far away from pits and other metallic parts near the track that could distort the field; practically speaking, as tramway and light railway tracks are often running in parallel to suburban roads, such distance is limited to a few meters maximum or, skipping the road width, it is in the order of 5m–10m.
The typical context, however, includes a problem of coordination with road traffic and interference with private property (e.g. accessible soil may be located in private gardens or access granted passing through private property). The method is minimally invasive, in that it requires digging a vertical electrode of small dimensions (e.g. m and passing of a couple of electric wires of small cross section (e.g. mm2 for mechanical robustness).
Practical constraints as well, such as the presence of a road, a parking with asphalt, a building, may prevent access to natural soil, and thus require to deviate from preferred reference values for
a and
b, so that knowledge of tolerances and sensitivity of results to such changes is needed. This is verified in
Section 4.3.
Soil resistivity values must be determined by a separate measurement using a 4-electrode method [
42]. The problems related to this quantity are many:
accessibility of the area to place the test electrodes in a line, as prescribed by the Wenner method (4 electrodes in a line, with external ones for test current and the inner ones for the voltage reading , spaced by s); the resulting apparent soil resistivity value can be calculated from the resistance reading as ; the resistivity value refers to the depth s, so that to double the probed depth the electrodes span is doubled as well;
often, the Schlumberger method is used instead, because it requires the movement of 2 electrodes only, keeping the inner ones for voltage more compact; keeping their separation s and calling p the separation between each external one and the nearest voltage electrode (with ), the resistivity may be estimated again from the calculated resistance value as and the depth is , so deeper than the previous one; in other words, for a given target depth, the Schlumberger method is more compact and faster;
specifically focusing on the track geometry and roads nearby, keeping s in the order of 1m–2m, the separation p may increase to what allowed by the areas nearby (e.g. 5m–20m); depth values to focus on are in this range and they should be supported by a careful analysis of resistivity values behavior to determine abnormal distributions and lack of homogeneity;
it is in fact observed that interference by other metallic/conductive buried structures is almost certain in a urban/suburban context and larger volumes of soil (going deeper) help averaging the contributions.
4.3. Variability and uncertainty analysis
Variability and uncertainty issues of the method are considered from three standpoints:
first, a practical example of an extensive test campaign carried out along a tramway line is considered, in order to focus on data dispersion, determination of the linear regression slope
, etc.; results are reported in the next
Section 4.4 for homogeneity with previous sections;
then, formulations are analyzed for sensitivity to the parameters and to robustness to extreme situations caused by practical issues, such as issues in placing electrodes;
last, propagation of uncertainty is calculated along the given formulations, having already evaluated the behavior for uncommon values of parameters.
The determination of is quite robust to outliers and even to a small fraction of corrupted data, provided the recording is long enough to have a statistically significant set of good cases representing the typical dynamics of the system. As a rule of thumb we have used in the past multiples of the headway time, that correspond each to single tram/train passages. Deviations are possible but for the purpose of the determination of they are not relevant, unless when two trams/trains pass in front of the electrodes almost at the same time. In this case, repeated occurrences are necessary so that recording lengths of some hours are suitable. In the examples shown in the next section the number of samples was cut to two hours. Sampling time is not of such importance, and the 2 Hz sampling time suggested by the EN 50122-2 for stray current monitoring could be used.
The EN 50122-2 has changed the two separate formulas of the 2010 version, adopting a unique formulation for both single- and double-track configurations, as introduced in
Section 4.1.
Figure 6 reports the comparison between formulas for a single and a double-track configuration, having fixed the inter-track separation
, with
.
Considering (
11), propagation of uncertainty is operated using partial derivatives, but focusing on the quantities that are subject to the largest uncertainty (
and
), as the geometrical quantities
a,
b and
s can be measured with high accuracy. Their uncertainty in fact is much less than 1 % as
a and
b have errors lower than 1 cm over several meters, and
s is almost “exact”, for mechanical and safety reasons (rail gauge is periodically checked to
m between internal edges; the inter-track gap is also stable and constant as the track was position with accuracy in other order of
).
The two terms then correspond to:
The uncertainty after normalization by
is then, as expected,
Evaluating the basic uncertainty of the two quantities and is a complex task:
For
it’s a matter of propagating the uncertainty of
and
through the least-mean-square (LMS) regression, as it was done in [
43] for the determination of stray capacitance (as the intercept and not the slope, as in the present case).
For it is not a matter of uncertainty alone: the measurement itself is carried out by automatic volt-amperometric measurements at undisturbed frequencies, and the calibration with reference resistors indicates an instrumental uncertainty on the order of 1%–2% depending on resistance values. Variability of soil resistivity instead should be accounted for, as depending on location, depth and environmental/seasonal conditions. The latter may be ruled out if soil resistivity is measured immediately before (or after) the track measurements. The former can be accounted for by repeated measurements and taking then a weighted average as the value, and their dispersion as a Type A estimate of their uncertainty.
4.4. Application to a tramway system
Method A.4 has been successfully applied to a new freshly commissioned tramway for the urban sections with embedded rail, that were nevertheless characterized by a large amount of green areas nearby (and access to natural soil). Other sections near the end of the line were instead tested during construction with method A.3, being the running rails still not welded at several points. For the last portion of the line near the port with no access to public soil the method A.2 was instead used during short time intervals during the day with suspension of trial service.
Method A.4 brought along the information of track voltage values as added value. The results shown in
Figure 7 report the voltages of the track and electrode E1 with respect to electrode E2 on the left and the estimated angular coefficient (stray current ratio
) by linear regression on the right, providing a graphical representation of the dispersion of the data points. The orange line is the LMS regression line whose angular coefficient corresponds to
: the plot of the three locations at the same vertical scale (although the
potential was much different, allows to appreciate the change of slope between locations, also due to different values of
a and
b, as due to practical constraints for soil accessibility.
Table 2 then reports the numeric values of the estimated track conductance
and coefficient
, together with the parameters of the geometry (namely electrode positions) and soil resistivity.
Resulting values are quite compact being a 4:1 proportion between the two extreme values and for an embedded track in North Europe climate conditions they are quite satisfactory, being an order of magnitude below the EN 50122-2 limit of 2 S/km (embedded tramway track).
5. Discussion and Conclusions
This work has considered the three methods for track insulation measurement, standardized by the EN 50122-2 (or IEC 62128-2). Each method has advantages and disadvantages in a system level perspective: method A.3 requiring the electrical interruption of the running rails, oppositely to method A.2; in addition, method A.4 not only uses the track unaltered, but exploits the normal traffic as a driving signal, thus compatible with commercial service hours oppositely to methods A.2 and A.3 that necessitate a free line and thus are applicable during construction or engineering hours.
More in detail, each method is based on a certain number of electrical quantities and is characterized by some level of complexity. Method A.3 is the least complex, related directly to the definition of track insulation resistance, and carries out a simple volt-amperometric measurement of the track-to-earth resistance, measuring the track (or rail) voltage at an intermediate point at some distance away from the point of application of the test voltage. The uncertainty is minimal (one voltage and one current measurement), but there exist an albeit small variability vs. the earthing resistance of the test supply and vs. the positioning of the voltage terminal. The other two methods are, however, less invasive not necessitating the physical sectioning of the running rails and being method A.4 compatible with normal traffic.
An acceptable uncertainty for track insulation assessment is never clearly made explicit in standards and contractual specifications. Considering all sources of variability and instrumental uncertainty, a 10 % to 20 % standard uncertainty level may be acceptable.
Variability and uncertainty of the methods cannot be thought as separate, as many parameters that implicitly or explicitly are part of the track insulation equation are determined with high uncertainty (e.g. soil resistivity), are subject to change (e.g. with temperature, on a seasonal base, etc.), or are not sufficiently constrained and depend somewhat on operator’s choice (position of the voltage terminal, distance of the electrodes from the track, etc.). In other words, instrumental uncertainty is often a factor of lesser importance, except when rail current is determined by voltage drop measurements (that is the most uncertain measurement method). In this case it was shown in
Table 1 that multimeters in general may perform poorly if not specifically designed for such task, i.e.
scale reading. The accuracy of method A.2, that relies heavily on 2 or 4 rail current measurements, is thus significantly affected: track length is thus subject to an additional constraint of minimum length to allow for a current leakage estimate with sufficient accuracy (a ); such minimum length is discussed and found to be in the range of some hundreds m to 1 km depending on the track insulation level.
Having assessed the metrological characteristics of such methods, together with other characteristics such as impact on system operation and complexity of setup, the conclusion is that methods that do not require rail sectioning should be preferred, despite their lower accuracy (intended as including variability and uncertainty). So, research effort should be in the direction of improving repeatability and uncertainty, and in particular make methods with a better spatial resolution: method A.2 in fact is subject to the identified minimum track length requirement to preserve a minimum acceptable uncertainty level, whereas method A.4 has no clear relationship with the portion of track included in the so determined track insulation value.
Another research direction is specifically the improvement of the rail current measurement, avoiding the use of rail voltage drop, providing an immediate benefit for method A.2 in terms of uncertainty: current sensors able to measure rail current are unfortunately of the AC type (such as Rogowski coils and close-up magnetic sensors), so that a study should be carried out of equivalence of DC and AC measurements to the aim of track insulation determination for stray current assessment.
Method A.4 finally is very promising for measurements on existing systems under normal traffic conditions (so in real exploitation conditions) and should be further investigated also in terms of the effect of influence of buried conductive parts and behavior of the electric field in the soil with respect to soil inhomogeneity and, as a consequence, required resolution and extent of soil resistivity mapping.
Funding
This research received no external funding.
Institutional Review Board Statement
Not applicable.
Informed Consent Statement
Not applicable.
Conflicts of Interest
“The authors declare no conflict of interest.”
References
- Vranešić, K.; Lakušić, S.; Serdar, M. Corrosion and stray currents at urban track infrastructure. Journal of the Croatian Association of Civil Engineers 2020, 72, 593–606. [Google Scholar] [CrossRef]
- Xu, W.; Zhang, B.; Deng, Y.; Wang, Z.; Jiang, Q.; Yang, L.; Zhang, J. Corrosion of rail tracks and their protection. Corrosion Reviews 2020, 39, 1–13. [Google Scholar] [CrossRef]
- Vranešić, K.; Lakušić, S.; Serdar, M. Influence of Stray Current on Fastening System Components in Urban Railway Tracks. Applied Sciences 2023, 13, 5757. [Google Scholar] [CrossRef]
- Mariscotti, A. Electrical Safety and Stray Current Protection With Platform Screen Doors in DC Rapid Transit. IEEE Transactions on Transportation Electrification 2021, 7, 1724–1732. [Google Scholar] [CrossRef]
- Jin, H.; Yu, S. Effect of DC stray current on rebar corrosion in cracked segment of shield tunnel. Construction and Building Materials 2021, 272, 121646. [Google Scholar] [CrossRef]
- Ai, H.; Li, G.; Wang, B.; Panesar, D.K.; He, X. Degradation mechanism of cement-based materials under the effects of stray current, chloride and sulfate. Engineering Failure Analysis 2022, 142, 106746. [Google Scholar] [CrossRef]
- Qian, S.; Cheng, Y.F. Accelerated corrosion of pipeline steel and reduced cathodic protection effectiveness under direct current interference. Construction and Building Materials 2017, 148, 675–685. [Google Scholar] [CrossRef]
- Mujezinović, A.; Martinez, S.; Kekez, K. Estimating harmful effect of dynamic stray currents on pipeline by simultaneous multiparametric field measurements, continuous wavelet cross-correlation analysis, and frequency plots. Materials and Corrosion 2018, 70, 357–365. [Google Scholar] [CrossRef]
- Szymenderski, J.; Machczyński, W.; Budnik, K. Modeling Effects of Stochastic Stray Currents from D.C. Traction on Corrosion Hazard of Buried Pipelines. Energies 2019, 12, 4570. [Google Scholar] [CrossRef]
- Yu, K.; Ni, Y.; Zeng, X.; Peng, P.; Fan, X.; Leng, Y. Modeling and Analysis of Transformer DC Bias Current Caused by Metro Stray Current. IEEJ Transactions on Electrical and Electronic Engineering 2020, 15, 1507–1519. [Google Scholar] [CrossRef]
- Du, L.; Chang, S.; Wang, S. The Research on DC Loop of Regional Power Grid Caused by the Operation of the Subway. Electronics 2020, 9, 613. [Google Scholar] [CrossRef]
- Li, C.; Du, Q.; Guo, Y.; Liu, Y.; Yang, F.; Chen, L.; Zhang, X.; Huang, G.; Gao, G.; Wu, G. Modeling of Stray Currents From Metro Intruding Into Power System Considering the Complex Geological Conditions in Modern Megacities. IEEE Transactions on Transportation Electrification 2023, 9, 1653–1663. [Google Scholar] [CrossRef]
- Isozaki, H.; Oosawa, J.; Kawano, Y.; Hirasawa, R.; Kubota, S.; Konishi, S. Measures Against Electrolytic Rail Corrosion in Tokyo Metro Subway Tunnels. Procedia Engineering 2016, 165, 583–592. [Google Scholar] [CrossRef]
- Vranešić, K.; Serdar, M.; Lakušić, S.; Kolář, V.; Mariscotti, A. Dynamic Stray Current Measuring Methods in Urban Areas. The Baltic Journal of Road and Bridge Engineering 2022, 17, 146–170. [Google Scholar] [CrossRef]
- Regula, M.; Siranec, M.; Otcenasova, A.; Hoger, M. Possibilities of the stray current measurement and corrosive risk evaluation. Electrical Engineering 2022, 104, 2497–2513. [Google Scholar] [CrossRef]
- Fichera, F.; Mariscotti, A.; Ogunsola, A. Evaluating stray current from DC electrified transit systems with lumped parameter and multi-layer soil models. Eurocon 2013. IEEE, 2013. [CrossRef]
- Wang, C.; Li, W.; Wang, Y.; Xu, S.; Li, K. Evaluation Model for the Scope of DC Interference Generated by Stray Currents in Light Rail Systems. Energies 2019, 12, 746. [Google Scholar] [CrossRef]
- Bhagat, S.; Yang, X.; Wang, M.; Mariscotti, A. Review and Evaluation of Stray Current Mitigation for Urban Rail Transit. Diangong Jishu Xuebao/Transactions of China Electrotechnical Society 2021, 36, 4851–4863. [Google Scholar] [CrossRef]
- Zhou, Q.; Lin, S.; Lin, X.; Wang, A. A Uniform Model for Stray Current of Long-Line DC Metro Systems. IEEE Transactions on Transportation Electrification 2022, 8, 2915–2927. [Google Scholar] [CrossRef]
- Du, G.; Zheng, Z.; Li, Q.; Xu, F.; Zhang, T.; Zhang, D.; Zhang, X.; Huang, W. Multi-state unified calculation model of rail potential and stray current in DC railway systems. IET Electrical Systems in Transportation 2023, 13. [Google Scholar] [CrossRef]
- Bahra, K.; Catlow, R.E. Control of Stray Currents for DC Traction Systems. International Conference on Electric Railways in a United Europe, 1995, pp. 136–142.
- Liu, W.; Li, T.; Jie, Z.; Weiguo, P.; Yichen, Y. Evaluation of the Effect of Stray Current Collection System in DC-Electrified Railway System. IEEE Transactions on Vehicular Technology 2021, 70, 6542–6553. [Google Scholar] [CrossRef]
- Juybari, E.Z.; Keypour, R.; Niasati, M. Voltage distribution indices method to analyse the performance of various structures of stray current collectors in direct current transit lines. IET Electrical Systems in Transportation 2021, 11, 322–332. [Google Scholar] [CrossRef]
- Kampeerawat, W.; Jongudomkarn, J.; Kirawanich, P.; Sumpavakup, C. Effect of Voltage Limiting Device Operation on Rail Potential and Stray Current in DC Railway Systems. GMSARN International Journal 2023, 17, 213–219. [Google Scholar]
- Gu, J.; Yang, X.; Zheng, T.Q.; Xia, X.; Zhao, Z.; Chen, M. Rail Potential and Stray Current Mitigation for Urban Rail Transit With Multiple Trains Under Multiple Conditions. IEEE Transactions on Transportation Electrification 2022, 8, 1684–1694. [Google Scholar] [CrossRef]
- Wei, L.; Jie, Z.; Tian, L.; Siwen, L.; Long, Y. The Influence of Drainage Device on Stray Current Distribution in DC Traction Power Supply System. Transactions of China Electrotechnical Society 2022, 37, 4565–4574. [Google Scholar] [CrossRef]
- Peng, P.; Zeng, X.; Leng, Y.; Yu, K.; Ni, Y. A New On-line Monitoring Method for Stray Current of DC Metro System. IEEJ Transactions on Electrical and Electronic Engineering 2020, 15, 1482–1492. [Google Scholar] [CrossRef]
- Mariscotti, A. Stray Current Protection and Monitoring Systems: Characteristic Quantities, Assessment of Performance and Verification. Sensors 2020, 20, 6610. [Google Scholar] [CrossRef]
- EN 50122-2. Railway applications — Fixed installations — Electrical safety, earthing and the return circuit. Part 2: Provisions against the effects of stray currents caused by DC traction systems. CENELEC, Brussels, Belgium, 2021.
- IEC 62128-2. Railway applications — Fixed installations — Electrical safety, earthing and the return circuit. Part 2: Provisions against the effects of stray currents caused by DC traction systems. IEC, Geneva, Switzerland, 2013.
- EN 50122-2. Railway applications — Fixed installations — Electrical safety, earthing and the return circuit. Part 2: Provisions against the effects of stray currents caused by DC traction systems. CENELEC, Brussels, Belgium, 2010.
- Mariscotti, A. Impact of rail impedance intrinsic variability on railway system operation, EMC and safety. International Journal of Electrical and Computer Engineering (IJECE) 2021, 11, 17. [Google Scholar] [CrossRef]
- Mariscotti, A.; Pozzobon, P. Measurement of the internal impedance of traction rails at 50 Hz. IEEE Transactions on Instrumentation and Measurement 2000, 49, 294–299. [Google Scholar] [CrossRef]
- Mariscotti, A.; Pozzobon, P. Resistance and Internal Inductance of Traction Rails at Power Frequency: A Survey. IEEE Transactions on Vehicular Technology 2004, 53, 1069–1075. [Google Scholar] [CrossRef]
- Mariscotti, A.; Pozzobon, P. Determination of the Electrical Parameters of Railway Traction Lines: Calculation, Measurement, and Reference Data. IEEE Transactions on Power Delivery 2004, 19, 1538–1546. [Google Scholar] [CrossRef]
- Mariscotti, A. Rail Current Measurement With Noninvasive Large Dynamic Probe. IEEE Transactions on Instrumentation and Measurement 2009, 58, 1610–1616. [Google Scholar] [CrossRef]
- Rienzo, L.D.; Li, D.; Pignari, S.A.; Fedeli, E. Array of rectilinear solenoids for rail current measurement. International Symposium on Electromagnetic Compatibility - EMC EUROPE. IEEE, 2012. [CrossRef]
- Xu, X.; Chen, H.; Liu, T.; Zhu, M.; Wang, J. On-Line Detection of Railway Power Frequency Current Based on Tunnel Magnetoresistance. IEEE Transactions on Instrumentation and Measurement 2023, 72, 1–9. [Google Scholar] [CrossRef]
- Bongiorno, J.; Mariscotti, A. Accuracy of railway track conductance and joint efficiency measurement methods. ACTA IMEKO 2015, 4, 82. [Google Scholar] [CrossRef]
- Bongiorno, J.; Gianoglio, C. Experimental variability of track to ground conductance measurements. Journal of Physics: Conference Series 2018, 1065, 052015. [Google Scholar] [CrossRef]
- Bongiorno, J.; Mariscotti, A. Variability of measured railway track conductance due to test set-up. ACTA IMEKO 2019, 7, 21. [Google Scholar] [CrossRef]
- IEEE Std. 81. IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System, 2012.
- Mariscotti, A. Measuring the Stray Capacitance of Solenoids with a Transmitting and a Receiving Coil. Metrology and Measurement Systems 2011, 18, 47–56. [Google Scholar] [CrossRef]
|
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).