For the I33 system, it could be observed from results that the averaged probabilities during the day are increased by around 1.4 % (RPO) and 35 % (VPO) for demand and by around 1.1 % (RPO) and 20 % (VPO) for irradiance compared to the deterministic case. The location of the PV unit changed from node 8 to nodes 17 and 12 under RPO and VPO respectively. Its capacity was kept near the upper bound in the deterministic and VPO cases, while it suffered an
reduction with the RPO, suggesting that, even under uncertainty, DER units should be located in the most congested branch (the active power load is distributed to
in branch 2-6,
in branch 7-18,
in branch 19-22,
in branch 23-25 and
in branch 26-33). The minimum power loss was achieved in the deterministic case, followed by a
increase for the RPO and a
increase for the VPO, approximately, showing how sensitive can be the analysis to uncertain values: Although demand and irradiance profiles suffered small deviations compared to the expected values, the system losses were affected much more negatively compared to the improvements gained in probabilities, even when deploying DER optimally. The results for the VPO can be interpreted as an approximation to the worst-case scenario since, as observed in
Figure 5 and
Figure 6, the obtained demand and irradiance coefficients are considerably higher and lower than the mean values, respectively, and both probabilities (to have lower demand and greater irradiance coefficients) are very high (
for demand and
for irradiance on average). In other words, the probability of the losses being lesser than
is on an hourly average greater than
, compared to the
on hourly average resulted from estimating the random variables to the mean values. In contrast to the RPO analysis, a drastic increase in power losses was accompanied with increases in probabilities comparing with the deterministic case. These results allow also the analysis of other operating constraints, such as voltage magnitudes. It could be observed, that the operational voltage limit constraint might be violated (especially the lower bound) if considering scenarios with worsened conditions, as in VPO, i.e., if the demand coefficients from VPO were considered for power flow analysis (without PV), the lower
bound would not be complied (see
Table 3). However, the installation of the PV unit kept voltage magnitudes within the lower
bound. Evidently, tighter bounds in voltages might take the problem to infeasibility regions or, in a practical scenario, make the grid non-compliant of operative constraints under uncertainty, which might represent economic losses due to penalties. For the J23 system, results were somewhat similar to the I33 ones. RPO and VPO probabilities increased by
and
for demand and by
and
for irradiance respectively compared to the deterministic case. This indicates that probabilities are not very affected by the system even though the random variables affect directly the power losses, which at the same time depends on the grid’s configuration and its parameters (size, redundancy, line impedances, load distribution, voltage level). As in the I33, the PV units were located in the most congested branch, in contrast to the deterministic case that located it in the second most congested branch (the active power load is distributed to
in branch 2-11,
in branch 12-25,
in branch 26-43 and
in branch 28-32). Regarding PV capacity, an important reduction happened when comparing both systems. In the I33 system the PV capacity was kept capped but in the RPO case when it was reduced
, yet in the J23, PV capacity reached near the
of the maximum capacity in the deterministic case, and decreased under uncertainty to the
of the maximum with both RPO and VPO approaches. Similar to the results for the I33 system, the J23 system gathered the minimum energy losses from the deterministic case, and were progressively worsening under uncertainty (
and
increases for the RPO and VPO respectively). Probabilities were increased likewise as in the analyses for the I33. Regarding voltages, the J23 system has significantly lower losses than the I33 system in the power flow analysis (PF). This is also reflected in the voltage envelopes shown in the different OPF analysis, where the minimum voltage remained almost unaltered within the
range even in cases with greater demand and lower irradiance (VPO). This explains that the J23 grid has the capability to sustain greater loads under uncertainty, possibly with greater hosting capacities, while operating safely. In
Figure A1 and
Figure A2 for the I33, and
Figure A3 and
Figure A4 for the J23 on the Appendix, it is possible to observe how the probability of coefficient profiles under RPO and VPO is compared to the probability under the opposite approach, i.e. the probability of the demand and irradiance profiles obtained from RPO compared to the probability of those profiles under VPO and vice-versa. Those illustrations show that probabilities are greater when calculated with the profiles obtained from their respective analysis than with the opposite. However, for irradiance profiles, the differences between the probabilities are noticeable, especially when comparing VPO probabilities, indicating that RPO irradiance coefficients and mean values are overestimated. Whereas, the VPO profiles show lower RPO probabilities but establish a case with higher probabilities of being more favorable, since the range in which the random variable could fall is much wider. To summarize, mean value estimations have lower probabilities, resulting in important power loss underestimations, whereas, under the RPO approach, a better estimation is obtained even though the irradiance is clearly overestimated. Under the VPO approach, an even more probable case is defined by estimating worsened conditions for the objective, showing that both Deterministic and RPO approaches underestimate the losses with less likely conditions. Finally, the formulation of the proposed convex stochastic programs, allowed to obtain global optimal solutions. Although most of the variables in the proposed stochastic programs are integer, the problem size (directly related to the grid’s size) hadn’t had any considerable impact on the solving time. On the contrary, for the I33 stochastic AC-OPFs, it took longer to find the solution. An explanation for this is that variations in the variables within the PCI (which contains the majority of integer variables and has the same dimensions for each test case), produce greater effects in power losses due to line lengths (impedance) and distribution of greater demands, requiring more intensive Branch-and-Bound steps until the difference between the objective upper and lower bounds, respectively set by the improvements in root relaxation and the incumbent solution, lies within the parameterized relative gap.