1. Introduction
The construction industry encounters interface risks which are complex, difficult and diverse to solve and manage. interface risk management (IRM). Interface risks are the most encountered problem in the industry. In the highly risky and complex environment of a construction project, if effective decisions are not made in the conceptualisation, planning, design, contracting, procurement, execution phases, disagreements, loss of profit, claims, industrial actions, disputes, conflicts, change orders, and claims can occur at any phase of the construction project. The traditional construction industry usually depends on the project participants’ work experiences to solve interface risks problems, including designers, owners, project team members, main contractors, subcontractors, host communities, licensing and regulatory bodies, vendors, maintenance contractors, and material suppliers related issues.
Interface risk management is primarily overseen and regulated by project managers. However, the intricate handling of these interface incidents is frequently evaluated and appraised based on the expertise of engineers. The involvement of a systematic approach to interface problems is infrequent. In essence, the conventional approach to interface problem solving lacks objectivity, relies heavily on subjective experiences, and lacks a systematic framework for identifying interface issues and proposing comprehensive solutions. The professionalisation of interface risk management (IRM) practise has been shown to have a positive impact on the project performance of construction projects [
1]. This, in turn, leads to enhanced social benefits for public projects. While the advantages of Interface Risk Management (IRM) may be more readily apparent in large-scale projects, the effective management of interfaces is considered significant for projects of all sizes and levels of complexity. Furthermore, recent research conducted by [
2,
3] has revealed that project managers have utilised Building Information Modelling (BIM) to effectively oversee extensive construction projects and address the challenges associated with interfaces. In addition to its academic significance, this study also demonstrates its social relevance by potentially contributing to the professionalisation of IRM. The academic literature suggests that IRM holds promising benefits. One can anticipate several benefits from improving the exchange of information and reducing costs associated with interface issues, such as the promotion of inter-organizational collaboration [
1,
4].
Construction projects employ principles and protocols that encompass a multitude of complexities in the management of various stakeholders, including owners, technical clients, and engineering, procurement, and construction (EPC) contractors. The reason for this is that the phases of the construction project encompass numerous contracts that involve a diverse range of contractors. According to [
5], therefore, it is important to recognise that the application of principles and approaches may vary among different stakeholders, both internal and external. Firstly, it is not feasible to effectively manage the relational connections between a singular project team consisting of the general contractor, client, designer and customer [
6]. Furthermore, the premise of a singular project team is predicated on the explicit consideration of the individual interests and objectives of all the participants [
7]. In practical application, the interests of the individuals engaged in a construction endeavour exhibit variation and frequently encompass multiple facets. This phenomenon arises in scenarios where the proprietor aims to reduce the expenses associated with construction, while the general contractor or subcontractor seeks to augment the construction costs. Additionally, the technical customer plans to delegate the tasks and coordination work to the design firm, thereby necessitating supplementary compensation [
8]. According to [
9], when considering the selection of the most economically efficient alternatives, the practicality of implementing a sole project team is questionable. The contractor expresses a favourable perspective regarding the evaluation of the most financially advantageous construction project. Nevertheless, the limited availability of construction orders to contractors can be attributed competition from other industry players and market conditions. The primary concern for customers is the fulfilment of technical construction orders. Interface risk management is commonly employed in intricate projects and overseen by multiple stakeholders with diverse areas of expertise, resulting in a multitude of overlapping activities. Interface risk management is a potential solution for effectively managing the complexities of construction projects. It primarily involves the management of communications, relationships, and deliverables among project stakeholders. By establishing improved methods for identifying, documenting, monitoring, and tracking project interfaces and the associated risks, interface risk management can contribute to the successful execution of construction projects. The present study undertakes a comprehensive review of relevant literature in order to establish a solid theoretical foundation for the research. The term "interfaces" in the context of construction projects refers to the points of connection or interaction between different components, systems, or stakeholders involved in the project. These interfaces play a crucial role in ensuring the successful coordination and integration of various elements within the construction process. Interfaces are significant for the overall project execution.
4. Findings and Analysis
The study employed the Kaiser-Meyer-Olkin (KMO) measure and Bartlett's Test to assess the interrelationships among variables, thereby informing the decision to proceed with the factor analysis of the collected data. A comprehensive set of 205 responses was obtained from the designated target population, which primarily comprises individuals within the construction industry as described in the context of questionnaire design and target group identification.
Table 1 below shows the summary of the biographical data of the respondents who participated in the online survey.
From
Table 1 above, out of the 205 responses from the online questionnaire, 16 respondents were quantity surveyors, 9 were architects, 7 were builders, 8 were project engineers, 9 were project administrators, 10 were safety officers/engineers/managers, 10 were risk managers, 20 were mechanical engineers, 13 were construction engineers, 18 were project managers, 8 were estate managers, 22 were electrical engineers, 25 were construction managers, 27 were civil/structural engineers and 3 respondents were other construction professionals.
Table 2 below shows age distribution of participants.
From the
Table 2 above, out of the 205 respondents, 4 respondents were in the age group of 21 – 25 years, 16 were in the age group of 26 - 30 years, 32 were in the age group of 31 - 35 years, 42 were in the age group of 36 - 40 years, 53 were in the age group of 41 – 45 years, 46 respondents were in the age group of 46 years and above.The
Table 3 below shows the academic qualifications of the respondents.
From
Table 3 above, 11 respondents out of the 205 respondents which represented 5.4% of the respondents have post matric or diplomas as their highest academic qualifications, 55 (26.8%) had bachelor's degrees, 28 (13.7%) have honours degrees, 70 (34.1%) have master’s degrees while 41 respondents which represented 20.0% of the total respondents have doctoral degrees.
Table 4 below shows the organizational size of the respondents.
From the
Table 4 below, 72 respondents which represent 35.1% of the total respondents work in the small-sized industries and 74 which represent 36.1% work at medium-sized industries while 59 of the respondents which represent 28.8% work in the large-scale construction industries.
Table 5 below represents the frequency distribution for question 1 (How often do you encounter interface risks between project stakeholders in a project?)
From
Table 5 above, 11 (5,4%) respondents chose rarely, 63 (30,7%) chose sometimes, 66 (32,2%) chose often and 65 (31,2%) of the total respondents chose always.
Table 6 below shows the mean and standard deviation for research question 1.
From
Table 6 above, the mean was 3,90, which was slightly below often (4) and most people answered between sometimes (3) and always (5). The median was 4,00 which means half of the respondents chose between often and always and the other half chose between often and always. The mode was 4 which means most people chose often.
Table 7 below shows the responses for the research questions 2 on work cultures related to interface risks.
Table 7 above represented the responses for questions on work culture related to interface risks. The respondents were asked to answer the questions and rank them according to their level of agreement.
For the first question (Interface risks between project stakeholders can be classified as uncertainties), 1 respondent strongly disagreed with the statement which represented 0,5% of the total responses, 15 (7,3%) respondents disagreed, 39 (19,0%) respondents were neutral, 129 (62,9%) agreed while 21 (10,2%) of the respondents strongly agreed.
For the second question (Interface risks between project stakeholders can be classified as unidentified risks?), 1 respondent strongly disagreed with the statement which represented 0,5% of the responses, 12 (5,9%) disagreed with the statement, 57 (27,8%) respondents were neutral, 118 (57,6%) agreed while 17 (8,3%) respondents strongly agreed.
For the third question (Identification of hard interface risks encourages effective collaboration between project stakeholders), 1 respondent strongly disagreed with the statement which represented 0,5% of the responses, 2 (1,0%) disagreed with the statement, 11 (5,4%) respondents were neutral, 119 (58,0%) agreed while 72 (35,1%) respondents strongly agreed.
For the fourth question (Identification of soft interface risks encourages effective collaboration between project stakeholders), no respondent strongly disagreed with the statement which represented 0,0% of the responses, 6 (2,9%) disagreed with the statement, 27 (13,2%) respondents were neutral, 107 (52,2%) agreed while 65 (31,7%) respondents strongly agreed.
Table 8 below shows the KMO and Bartlett’s test for research objective 1 (consequences of poor and ineffective interface risks management approach).
From
Table 8 above, the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,898 which was bigger than 0,6 which shows that factor analysis can be carried out. For the Bartlett's Test of Sphericity, the significance which is the p value was less than 0,001 which was less than 0,05 and this supports its factorability.
Table 9 below shows the KMO and Bartlett’s test for research objective 2 (interface risks management approaches by organisations)
From
Table 9 above, the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,915 which was bigger than 0,6 therefore, the factor analysis can be done. For the Bartlett's Test of Sphericity, the significance which is the p value is 0,000 which was less than 0,05 and this supports its factorability.
Table 10 below represents KMO and Bartlett’s test for research objective 3 (causes of interface risks)
From
Table 10 above, the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,917 which was bigger than 0,6 which shows that the factor analysis can be done. For the Bartlett's Test of Sphericity, the significance which is the p value was 0,000 which was less than 0,05 and this supports its factorability.
Table 11 below shows the responses received for research objective 1 for B2 related to consequences of a poor and ineffective interface risks management approach. The respondents were asked to rank them according to the extent scale.
From
Table 11 above, project delays, extension of project delivery time, poor safety standards, stakeholders’ complaints, project overall failure, poor workflow planning and developmentloss of profit, additional costs, reputational damage of an organisation and claims for damage were identified as the major consequences of a poor and ineffective interface risks management approach in construction projects according to the responses received.
Table 12 below shows the responses received for research objective 2 - the extent in which interface risks management approaches influence project goals and objectives and the successful execution of construction projects in South Africa. The respondents rated their answers with the extent scale.
From
Table 12 above, alliancing and partnering agreements, identification of construction supply chain risks during interfaces establishments, conflicts resolution carried out by parties involved, clash detection as an integral part of the construction process for interface risk management, interface risks management by all the parties involved, clash detection as an integral part of the design process for interface risk management, assessing third parties’ dependencies to identify new interfaces, identification of interface risks in the conceptualisation stage of a project, identification of interface risks in the interface’s establishment phases, identification of interface risks in the execution stage, defining standard methods and procedures, establishing a building information modelling (BIM) volume strategy and creating a virtual construction model during the construction phase were identified as the major interface risks management approaches that have most impacts on project goals and objectives and the successful execution of construction projects in South Africa.
Table 13 below shows the responses received to what extent are the following the causes of interface risks on construction projects.
From
Table 13 above, the responses indicated that disorganized construction supply chain management, incompetency, poor workflow planning and development, subcontractors’ negative attitudes towards teamwork, unpredictable and low delivery reliability, poor inventories, lack of knowledge sharing, procurement delays, ineffective communication in site layout changes with stakeholders, poor understanding of the construction project process among project stakeholders, not updating changes in site layout with stakeholders and disorganized construction supply chain management were identified as the major causes of interface risks in construction projects..
4.1. Exploratory Factor Analysis
Since the sample size was 205, this was done to reduce the data or summarise using a smaller set of factors or components. This was achieved by looking for groups among the intercorrelations of a set of variables. By using factor analytic techniques, data was refined and reduced to form a smaller number of related variables to a more manageable number before using them in other analysis. Factorability of the correlation matrix: to be considered suitable for factor analysis, the correlation matrix should show at least have some correlations of r = 0,3 or greater. Barlett’s test of sphericity should be statistically significant at p<0,05 and the Kaiser-Meyer-Olkin values should be 0,6 or above. These values are presented as part of the output from factor analysis.
Table 14 below depicts the exploratory factor analysis for research objective 1.
From
Table 14 above, the consequences of poor and ineffective interface risks management approach were loaded on two factors with eigenvalues of 6,206 and 1,438. These two factors explained 58,805% of the variance before rotation and 51,576% of the variance after rotation and the represent major and minor consequences of poor and ineffective interface risks management approaches.
Table 15 below represents the exploratory factor analysis for research objective 2 (What are the interface risks management approaches by organisations)
From
Table 15 above, Interface risks management approaches by organisations were loaded on four factors with eigenvalues of 11,460, 2,787, 1,581 and 1,209. These four factors explained 70,987% of the variance before rotation and 65,383% of the variance after rotation.
Table 16 below represents the exploratory factor analysis for research objective 3 (causes of interface risks).
From
Table 16 above, causes of interface risks were loaded on three factors with eigenvalues of 9,587, 1,960 and 1,194. These three factors explained 67,061% of the variance before rotation and 61,014% of the variance after rotation.
4.2. Reliability Statistics of Data Collected
In order to establish the consistency of data, the value of the Cronbach’s Alpha (coefficient alpha was determined).
Table 17 below shows the reliability statistics for research objective 1, Cronbach’s alpha coefficients must be greater than 0,7 to confirm reliability and internal consistency.
From the above
Table 17, the Cronbach Alpha was 0,907 which was above 0,7 therefore it was reliable.
Table 18 below shows the item-total statistics for research objective 1
Table 18 above contains total statistics for all the items in B2 for research objective1.
Table 19 above shows a Cronbach alpha value of 0,952, which was above 0,7 therefore it was reliable.
Table 20 below shows the item-total statistics for research objective 2.
Table 20 above contains total statistics for all the items in B3 for research objective 2.
Table 21 below depicts the reliability statistics for research objective 3 - B4.
From
Table 21 above, the Cronbach Alpha was 0,945, therefore it was reliable.
Table 22 below shows the item-total statistics for research objective 3 – B4 (causes of interface risks).
Table 22 above contains total statistics for all the items in B4 for research objective 3.
5. Results and Discussion
The respondents were asked to answer questions on work culture related to interface risks.As depicted by
Table 7 above, 1 respondent strongly disagreed that interface risks between project stakeholders can be classified as uncertainties which represented 0,5% of the total responses, 15 (7,3%) respondents disagreed, 39 (19,0%) respondents were neutral, 129 (62,9%) agreed while 21 (10,2%) of the respondents strongly agreed. 1 respondent strongly disagreed that interface risks between project stakeholders can be classified as unidentified risks which represented 0,5% of the responses, 12 (5,9%) disagreed with the statement, 57 (27,8%) respondents were neutral, 118 (57,6%) agreed while 17 (8,3%) respondents strongly agreed with the statement. The responses showed that 119 (58%) respondents agreed that the identification of hard interface risks encourages effective collaboration between project stakeholders while 72 (35,1%) respondents strongly agreed. 107 (52,2%) respondents agreed that the identification of both soft interface risks encourages effective collaboration between project stakeholders while 65 (31,7%) respondents strongly agreed.
For the research objective 1, the Spearman’s Rho showed that there is correlation between the consequences of poor and ineffective interface risks management approach and their influences on the project since the values of the Spearman’s coefficient are bigger than 0,3 and from
Table 8 above, for the Bartlett's Test of Sphericity, the significance, p value was less than 0,001 which was less than 0,05, which means the higher the probability of the consequences such as project delays, poor quality, industrial actions, additional costs etc., the higher the impacts on the project and the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,898 which was bigger than 0,6 which shows that factor analysis can be carried out.
For the research objective 2, the Spearman’s Rho showed that there was correlation between the interface risks management approaches and their influences on the project goals and objectives and the successful execution of construction projects since the values of the Spearman’s coefficient were bigger than 0,3 and from
Table 9 above, for the Bartlett's Test of Sphericity, the significance, p value was 0,000 which was less than 0,05, which means the higher the probability of the interface risks management approaches such as defining standard methods and procedures, creating a virtual construction model during the construction phase, establishing a building information modelling (BIM) volume strategy etc , the higher the impacts on the project goals and objectives and the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,915 which was bigger than 0,6 which shows that factor analysis can be done.
For the research objective 3, the Spearman’s Rho showed that there was correlation between the extent in which the following causes of interface risks on construction projects and the influences on the project since the values of the Spearman’s coefficient are bigger than 0,3 and from
Table 10 above, for the Bartlett's Test of Sphericity, the significance, p value was 0,000 which was less than 0,05, which means the higher the probability of the causes of interface risks such as incompetency, poor inventories, lack of knowledge sharing, procurement delays etc., the higher the impacts on the project execution and the Kaiser-Meyer-Olkin Measure of Sampling Adequacy was 0,917 which was bigger than 0,6 which shows that factor analysis can be carried out.
6. Conclusions
Interface risk is one of the major challenges facing the construction industry because construction projects are complex by nature involving a lot of activities and participants with different responsibilities and tasks. It is crucial to carefully identify and manage these risks arising from the interfaces since they are inherent in all the construction project phases according to the findings of the survey. The study indicated that most construction projects encounter interface risks throughout the project life cycle and if they are not carefully and properly identified and managed in the project, they have negative influences on project objectives and can evidently lead to project failure or abandonment. Interface risks must be continually identified and managed during the conceptualisation, planning, interface establishment phases and carefully assessed, monitored and managed throughout the project. Effective communication, knowledge and information sharing among project stakeholders have positive impacts on the success of the project as well as identifying both soft and hard interface risks as this will encourage effective collaboration, alliancing and partnering agreements between project stakeholders, mitigate conflicts and clashes among stakeholders. Effective interface risks management in construction projects will minimise and save cost and time, mitigate industrial, actions, claims for damage, improve and maintain project quality and safety, protect the environment, facilitate good workflow planning and development, protect the reputation of the organisation that would have been damaged as a result of regulatory infringements, industrial actions, claims for damages, extended projected delivery time, stakeholders complaints, project abandonment and failure. Identifying and assessing parties’ dependencies to identify and manage new interfaces is important for project success. For effective interface risks management, standard methods and procedures must be defined, building information modelling volume strategy must be established and virtual construction model must be created. Regular meeting with stakeholders facilitates effective interface risks management. Stakeholders attitude towards project coordination is vital to project success. Clash detection and avoidance must be integrated in the planning, design and construction stages and conflicts must be resolved by every party involved. Effective construction supply chain management is important in project delivery and procurement deliveries must be timely, predictable and reliable and inventories must be updated regularly for effective project site coordination and workflow. Incompetent labour force, poor understanding of construction project processes, contractors, clients and subcontractors’ negative attitudes generate a lot of interface risks and these must be carefully identified and managed during the planning and contracting stages of the projects. Changes in site layouts must be updated and communicated among project participants. To save time, minimise cost, maintain anticipated project quality, safety and standards, interface risks must be carefully identified and managed by project participants and every stakeholder must participate in project coordination meetings and comply with the project guidelines and actively participate in identifying and managing interface risks throughout the project for the successful execution of the project.
Table 1.
Survey participants professions in the South African construction industry.
Table 1.
Survey participants professions in the South African construction industry.
Profession |
Frequency |
Percent |
Valid Percent |
Cumulative Percent |
Quantity surveyor |
16 |
7,8 |
7,8 |
7,8 |
Architect |
9 |
4,4 |
4,4 |
12,2 |
Civil engineer/structural engineer |
27 |
13,2 |
13,2 |
25,4 |
Builder |
7 |
3,4 |
3,4 |
28,8 |
Construction manager |
25 |
12,2 |
12,2 |
41,0 |
Electrical engineer |
22 |
10,7 |
10,7 |
51,7 |
Mechanical engineer |
20 |
9,8 |
9,8 |
61,5 |
Estate manager |
8 |
3,9 |
3,9 |
65,4 |
Project manager |
18 |
8,8 |
8,8 |
74,1 |
Construction engineer |
13 |
6,3 |
6,3 |
80,5 |
Project engineer |
8 |
3,9 |
3,9 |
84,4 |
Project administrator |
9 |
4,4 |
4,4 |
88,8 |
Safety officer/engineer/manager |
10 |
4,9 |
4,9 |
93,7 |
Risk manger |
10 |
4,9 |
4,9 |
98,5 |
Other construction professionals |
3 |
1,5 |
1,5 |
100,0 |
Total |
205 |
100,0 |
100,0 |
|
Table 2.
Age distribution of respondents.
Table 2.
Age distribution of respondents.
Age group |
Frequency |
Percent |
Valid Percent |
Cumulative Percent |
21-25 years |
4 |
2,0 |
2,0 |
2,0 |
26-30 years |
16 |
7,8 |
7,8 |
9,8 |
31-35 years |
32 |
15,6 |
15,6 |
25,4 |
36 -40 years |
42 |
20,5 |
20,5 |
45,9 |
41-45 years |
53 |
25,9 |
25,9 |
71,7 |
46 years and above |
58 |
28,3 |
28,3 |
100,0 |
Total |
205 |
100,0 |
100,0 |
|
Table 3.
academic qualifications of the respondents.
Table 3.
academic qualifications of the respondents.
Highest Academic Qualification |
Frequency |
Percent |
Valid Percent |
Cumulative Percent |
Post Matric Certificate or Diploma |
11 |
5,4 |
5,4 |
5,4 |
Bachelor’s degree |
55 |
26,8 |
26,8 |
32,2 |
Honours Degree |
28 |
13,7 |
13,7 |
45,9 |
Master’s degree |
70 |
34,1 |
34,1 |
80,0 |
Doctorate Degree |
41 |
20,0 |
20,0 |
100,0 |
Total |
205 |
100,0 |
100,0 |
|
Table 4.
Size of organizations of respondents.
Table 4.
Size of organizations of respondents.
Organisational Size |
Frequency |
Percent |
Valid Percent |
Cumulative Percent |
Small (1 – 100 staff) |
72 |
35,1 |
35,1 |
35,1 |
Medium (101 – 500) |
74 |
36,1 |
36,1 |
71,2 |
Large (501 – 5000+) |
59 |
28,8 |
28,8 |
100,0 |
Total |
205 |
100,0 |
100,0 |
|
Table 5.
frequency distribution for research question 1.
Table 5.
frequency distribution for research question 1.
How often do you encounter interface risks between project stakeholders in a project |
|
Frequency |
Percent |
Valid Percent |
Cumulative Percent |
Valid |
Rarely |
11 |
5,4 |
5,4 |
5,4 |
Sometimes |
63 |
30,7 |
30,7 |
36,1 |
Often |
66 |
32,2 |
32,2 |
68,3 |
Always |
65 |
31,7 |
31,7 |
100,0 |
Total |
205 |
100,0 |
100,0 |
|
Table 6.
statistics for research question 1.
Table 6.
statistics for research question 1.
How often do you encounter interface risks between project stakeholders in a project |
N |
Mean |
Median |
Mode |
Std. Deviation |
Minimum |
Maximum |
Valid |
Missing |
205 |
0 |
3,90 |
4,00 |
4 |
0,913 |
2 |
5 |
Table 7.
responses on work culture related to interface risks.
Table 7.
responses on work culture related to interface risks.
Work culture related to interface risks |
Strongly disagree |
Disagree |
Neutral |
Agree |
Strongly agree |
Total |
Interface risks between project stakeholders can be classified as uncertainties |
Count |
1 |
15 |
39 |
129 |
21 |
205 |
Row N % |
0,5% |
7,3% |
19,0% |
62,9% |
10,2% |
100,0% |
Interface risks between project stakeholders can be classified as unidentified risks? |
Count |
1 |
12 |
57 |
118 |
17 |
205 |
Row N % |
0,5% |
5,9% |
27,8% |
57,6% |
8,3% |
100,0% |
Identification of hard interface risks encourages effective collaboration between project stakeholders |
Count |
1 |
2 |
11 |
119 |
72 |
205 |
Row N % |
0,5% |
1,0% |
5,4% |
58,0% |
35,1% |
100,0% |
Identification of soft interface risks encourages effective collaboration between project stakeholders |
Count |
0 |
6 |
27 |
107 |
65 |
205 |
Row N % |
0,0% |
2,9% |
13,2% |
52,2% |
31,7% |
100,0% |
Table 8.
KMO and Bartlett’s test for research objective 1 for B2 (consequences of poor and ineffective interface risks management approach).
Table 8.
KMO and Bartlett’s test for research objective 1 for B2 (consequences of poor and ineffective interface risks management approach).
KMO and Bartlett's Test |
Kaiser-Meyer-Olkin Measure of Sampling Adequacy. |
0,898 |
Bartlett's Test of Sphericity
|
Approx. Chi-Square |
1309,488 |
|
|
df |
78 |
|
|
|
|
|
|
Sig. |
<0,001 |
Table 9.
KMO and Bartlett’s test for research objective 2 for B3 (interface risks management approaches by organisations).
Table 9.
KMO and Bartlett’s test for research objective 2 for B3 (interface risks management approaches by organisations).
KMO and Bartlett's Test |
Kaiser-Meyer-Olkin Measure of Sampling Adequacy. |
0,915 |
Bartlett's Test of Sphericity |
Approx. Chi-Square |
4068,497 |
Df |
276 |
Sig. |
0,000 |
Table 10.
KMO and Bartlett’s test for research objective 3 for B4 (causes of interface risks).
Table 10.
KMO and Bartlett’s test for research objective 3 for B4 (causes of interface risks).
KMO and Bartlett's Test |
Kaiser-Meyer-Olkin Measure of Sampling Adequacy. |
0,917 |
Bartlett's Test of Sphericity |
Approx. Chi-Square |
2767,160 |
Df |
171 |
Sig. |
0,000 |
Table 11.
responses for the research objective 1 for B2 - the consequences of a poor and ineffective interface risks management approach.
Table 11.
responses for the research objective 1 for B2 - the consequences of a poor and ineffective interface risks management approach.
SECTION B2 |
To no extent |
Small extent |
Moderate extent |
Large extent |
Very large extent |
Total |
Stakeholders’ complaints |
Count |
1 |
5 |
42 |
101 |
56 |
205 |
Row N % |
0,5% |
2,4% |
20,5% |
49,3% |
27,3% |
100,0% |
Claims for damage |
Count |
0 |
8 |
40 |
94 |
63 |
205 |
Row N % |
0,0% |
3,9% |
19,5% |
45,9% |
30,7% |
100,0% |
Loss of profit |
Count |
1 |
2 |
18 |
87 |
97 |
205 |
Row N % |
0,5% |
1,0% |
8,8% |
42,4% |
47,3% |
100,0% |
Reputational damage of an organisation |
Count |
0 |
8 |
40 |
89 |
68 |
205 |
Row N % |
0,0% |
3,9% |
19,5% |
43,4% |
33,2% |
100,0% |
Industrial actions |
Count |
0 |
12 |
60 |
88 |
45 |
205 |
Row N % |
0,0% |
5,9% |
29,3% |
42,9% |
22,0% |
100,0% |
Project delays |
Count |
2 |
2 |
22 |
102 |
77 |
205 |
Row N % |
1,0% |
1,0% |
10,7% |
49,8% |
37,6% |
100,0% |
Regulatory infringements |
Count |
2 |
4 |
77 |
86 |
36 |
205 |
Row N % |
1,0% |
2,0% |
37,6% |
42,0% |
17,6% |
100,0% |
Poor workflow planning and development |
Count |
2 |
4 |
23 |
113 |
63 |
205 |
Row N % |
1,0% |
2,0% |
11,2% |
55,1% |
30,7% |
100,0% |
Project overall failure |
Count |
2 |
6 |
24 |
101 |
72 |
205 |
Row N % |
1,0% |
2,9% |
11,7% |
49,3% |
35,1% |
100,0% |
Poor quality |
Count |
1 |
5 |
43 |
118 |
38 |
205 |
Row N % |
0,5% |
2,4% |
21,0% |
57,6% |
18,5% |
100,0% |
Additional costs |
Count |
2 |
1 |
21 |
102 |
79 |
205 |
Row N % |
1,0% |
0,5% |
10,2% |
49,8% |
38,5% |
100,0% |
Poor safety standards |
Count |
1 |
5 |
35 |
116 |
48 |
205 |
Row N % |
0,5% |
2,4% |
17,1% |
56,6% |
23,4% |
100,0% |
Extension of project delivery time |
Count |
1 |
5 |
21 |
109 |
69 |
205 |
Row N % |
0,5% |
2,4% |
10,2% |
53,2% |
33,7% |
100,0% |
Table 12.
responses received for research objective 2 for B3 - the extent in which interface risks management approaches influence project goals and objectives and the successful execution of construction projects in South Africa.
Table 12.
responses received for research objective 2 for B3 - the extent in which interface risks management approaches influence project goals and objectives and the successful execution of construction projects in South Africa.
SECTION B3 |
To no extent |
Small extent |
Moderate extent |
Large extent |
Very large extent |
Total |
Alliancing and partnering agreements |
Count |
0 |
3 |
23 |
105 |
74 |
205 |
Row N % |
0,0% |
1,5% |
11,2% |
51,2% |
36,1% |
100,0% |
Identifying third parties’ dependencies to identify new interfaces |
Count |
0 |
8 |
46 |
108 |
43 |
205 |
Row N % |
0,0% |
3,9% |
22,4% |
52,7% |
21,0% |
100,0% |
Assessing third parties’ dependencies to identify new interfaces |
Count |
0 |
15 |
41 |
97 |
52 |
205 |
Row N % |
0,0% |
7,3% |
20,0% |
47,3% |
25,4% |
100,0% |
Identifying third parties’ dependencies to manage new interfaces |
Count |
1 |
6 |
56 |
101 |
41 |
205 |
Row N % |
0,5% |
2,9% |
27,3% |
49,3% |
20,0% |
100,0% |
Assessing third parties’ dependencies to manage new interfaces |
Count |
0 |
14 |
44 |
87 |
60 |
205 |
Row N % |
0,0% |
6,8% |
21,5% |
42,4% |
29,3% |
100,0% |
Defining standard methods and procedures |
Count |
1 |
6 |
26 |
102 |
70 |
205 |
Row N % |
0,5% |
2,9% |
12,7% |
49,8% |
34,1% |
100,0% |
Establishing a Building information Modelling (BIM) volume strategy |
Count |
0 |
7 |
23 |
92 |
83 |
205 |
Row N % |
0,0% |
3,4% |
11,2% |
44,9% |
40,5% |
100,0% |
Creating a virtual construction model during the construction phase |
Count |
2 |
9 |
23 |
104 |
67 |
205 |
Row N % |
1,0% |
4,4% |
11,2% |
50,7% |
32,7% |
100,0% |
Regular meetings between project stakeholders |
Count |
0 |
8 |
29 |
98 |
70 |
205 |
Row N % |
0,0% |
3,9% |
14,1% |
47,8% |
34,1% |
100,0% |
Identification of construction supply chain risks during interfaces establishments. |
Count |
1 |
4 |
19 |
119 |
62 |
205 |
Row N % |
0,5% |
2,0% |
9,3% |
58,0% |
30,2% |
100,0% |
Identification of interface risks in the conceptualisation stage of a project |
Count |
0 |
7 |
22 |
93 |
83 |
205 |
Row N % |
0,0% |
3,4% |
10,7% |
45,4% |
40,5% |
100,0% |
Identification of interface risks in the planning stage of a project |
Count |
0 |
4 |
17 |
108 |
76 |
205 |
Row N % |
0,0% |
2,0% |
8,3% |
52,7% |
37,1% |
100,0% |
Identification of interface risks in the execution stage of a project |
Count |
1 |
4 |
42 |
89 |
69 |
205 |
Row N % |
0,5% |
2,0% |
20,5% |
43,4% |
33,7% |
100,0% |
Identification of interface risks in the interface’s establishment phases |
Count |
0 |
5 |
24 |
117 |
59 |
205 |
Row N % |
0,0% |
2,4% |
11,7% |
57,1% |
28,8% |
100,0% |
Identification of interface risks in the execution stage |
Count |
0 |
7 |
40 |
88 |
70 |
205 |
Row N % |
0,0% |
3,4% |
19,5% |
42,9% |
34,1% |
100,0% |
Stakeholders’ management strategies to predict how the project will affect stakeholders |
Count |
0 |
8 |
30 |
133 |
34 |
205 |
Row N % |
0,0% |
3,9% |
14,6% |
64,9% |
16,6% |
100,0% |
Stakeholders mapping to predict how stakeholders will affect the project |
Count |
1 |
10 |
48 |
93 |
53 |
205 |
Row N % |
0,5% |
4,9% |
23,4% |
45,4% |
25,9% |
100,0% |
Clash avoidance as an integral part of the construction process for interface risk management |
Count |
0 |
7 |
41 |
118 |
39 |
205 |
Row N % |
0,0% |
3,4% |
20,0% |
57,6% |
19,0% |
100,0% |
Clash avoidance as an integral part of the design process for interface risk management |
Count |
0 |
13 |
55 |
88 |
49 |
205 |
Row N % |
0,0% |
6,3% |
26,8% |
42,9% |
23,9% |
100,0% |
Clash detection as an integral part of the construction process for interface risk management |
Count |
0 |
8 |
47 |
112 |
38 |
205 |
Row N % |
0,0% |
3,9% |
22,9% |
54,6% |
18,5% |
100,0% |
Clash detection as an integral part of the design process for interface risk management |
Count |
0 |
9 |
47 |
98 |
51 |
205 |
Row N % |
0,0% |
4,4% |
22,9% |
47,8% |
24,9% |
100,0% |
Conflicts resolution carried out by parties involved |
Count |
0 |
4 |
22 |
112 |
67 |
205 |
Row N % |
0,0% |
2,0% |
10,7% |
54,6% |
32,7% |
100,0% |
Collaboration between project stakeholders |
Count |
1 |
4 |
19 |
82 |
99 |
205 |
Row N % |
0,5% |
2,0% |
9,3% |
40,0% |
48,3% |
100,0% |
Interface risks management by all the parties involved |
Count |
0 |
4 |
15 |
102 |
84 |
205 |
Row N % |
0,0% |
2,0% |
7,3% |
49,8% |
41,0% |
100,0% |
Table 13.
responses to research objective 3 for B4 (what extent are the following the causes of interface risks on construction projects).
Table 13.
responses to research objective 3 for B4 (what extent are the following the causes of interface risks on construction projects).
SECTION B4 |
To no extent |
Small extent |
Moderate extent |
Large extent |
Very large extent |
Total |
Poor workflow planning and development |
Count |
1 |
3 |
11 |
110 |
80 |
205 |
Row N % |
0,5% |
1,5% |
5,4% |
53,7% |
39,0% |
100,0% |
Subcontractors’ negative attitudes towards teamwork |
Count |
1 |
3 |
39 |
114 |
48 |
205 |
Row N % |
0,5% |
1,5% |
19,0% |
55,6% |
23,4% |
100,0% |
Procurement delays |
Count |
1 |
4 |
40 |
104 |
56 |
205 |
Row N % |
0,5% |
2,0% |
19,5% |
50,7% |
27,3% |
100,0% |
Unpredictable and low delivery reliability |
Count |
1 |
6 |
37 |
115 |
46 |
205 |
Row N % |
0,5% |
2,9% |
18,0% |
56,1% |
22,4% |
100,0% |
Poor inventories |
Count |
1 |
8 |
37 |
102 |
57 |
205 |
Row N % |
0,5% |
3,9% |
18,0% |
49,8% |
27,8% |
100,0% |
Lack of knowledge sharing |
Count |
0 |
5 |
22 |
95 |
83 |
205 |
Row N % |
0,0% |
2,4% |
10,7% |
46,3% |
40,5% |
100,0% |
Poor understanding of the construction project process among project stakeholders |
Count |
1 |
5 |
17 |
106 |
76 |
205 |
Row N % |
0,5% |
2,4% |
8,3% |
51,7% |
37,1% |
100,0% |
Not updating changes in site layout with stakeholders |
Count |
1 |
5 |
37 |
109 |
53 |
205 |
Row N % |
0,5% |
2,4% |
18,0% |
53,2% |
25,9% |
100,0% |
Ineffective communication in site layout changes with stakeholders |
Count |
1 |
3 |
19 |
82 |
100 |
205 |
Row N % |
0,5% |
1,5% |
9,3% |
40,0% |
48,8% |
100,0% |
Disorganized construction supply chain management |
Count |
1 |
4 |
17 |
105 |
78 |
205 |
Row N % |
0,5% |
2,0% |
8,3% |
51,2% |
38,0% |
100,0% |
Neglecting the handover process between two activities involving different trades in the planning stage |
Count |
0 |
7 |
46 |
105 |
47 |
205 |
Row N % |
0,0% |
3,4% |
22,4% |
51,2% |
22,9% |
100,0% |
Excluding subcontractors during the planning stage of a project |
Count |
4 |
5 |
52 |
106 |
38 |
205 |
Row N % |
2,0% |
2,4% |
25,4% |
51,7% |
18,5% |
100,0% |
Clients’ negative attitudes toward project stakeholders |
Count |
3 |
4 |
36 |
101 |
61 |
205 |
Row N % |
1,5% |
2,0% |
17,6% |
49,3% |
29,8% |
100,0% |
Incompetency |
Count |
0 |
3 |
22 |
101 |
79 |
205 |
Row N % |
0,0% |
1,5% |
10,7% |
49,3% |
38,5% |
100,0% |
Absence of contractors in project coordination meetings |
Count |
1 |
7 |
33 |
108 |
56 |
205 |
Row N % |
0,5% |
3,4% |
16,1% |
52,7% |
27,3% |
100,0% |
Absence of subcontractors in project coordination meetings |
Count |
0 |
7 |
39 |
118 |
41 |
205 |
Row N % |
0,0% |
3,4% |
19,0% |
57,6% |
20,0% |
100,0% |
Absence of suppliers and vendors in project coordination meetings |
Count |
2 |
18 |
73 |
72 |
40 |
205 |
Row N % |
1,0% |
8,8% |
35,6% |
35,1% |
19,5% |
100,0% |
Absence of vendors in project coordination meetings |
Count |
3 |
25 |
69 |
84 |
24 |
205 |
Row N % |
1,5% |
12,2% |
33,7% |
41,0% |
11,7% |
100,0% |
Contractors’ negative attitudes toward project stakeholders |
Count |
0 |
8 |
39 |
112 |
46 |
205 |
Row N % |
0,0% |
3,9% |
19,0% |
54,6% |
22,4% |
100,0% |
Table 14.
Exploratory factor analysis for research objective 1 (consequences of poor and ineffective interface risks management approach).
Table 14.
Exploratory factor analysis for research objective 1 (consequences of poor and ineffective interface risks management approach).
Factor |
Initial Eigenvalues |
Extraction Sums of Squared Loadings |
Rotation Sums of Squared Loadings |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
1 |
6,206 |
47,742 |
47,742 |
5,732 |
44,093 |
44,093 |
3,373 |
25,946 |
25,946 |
2 |
1,438 |
11,063 |
58,805 |
0,973 |
7,483 |
51,576 |
3,332 |
25,630 |
51,576 |
3 |
0,917 |
7,053 |
65,858 |
|
|
|
|
|
|
4 |
0,715 |
5,498 |
71,355 |
|
|
|
|
|
|
5 |
0,593 |
4,559 |
75,914 |
|
|
|
|
|
|
6 |
0,536 |
4,120 |
80,034 |
|
|
|
|
|
|
7 |
0,503 |
3,868 |
83,903 |
|
|
|
|
|
|
8 |
0,454 |
3,493 |
87,395 |
|
|
|
|
|
|
9 |
0,422 |
3,246 |
90,641 |
|
|
|
|
|
|
10 |
0,402 |
3,091 |
93,732 |
|
|
|
|
|
|
11 |
0,336 |
2,587 |
96,318 |
|
|
|
|
|
|
12 |
0,253 |
1,943 |
98,261 |
|
|
|
|
|
|
13 |
0,226 |
1,739 |
100,000 |
|
|
|
|
|
|
Table 15.
exploratory factor analysis for research objective 2 (interface risks management approaches by organisations).
Table 15.
exploratory factor analysis for research objective 2 (interface risks management approaches by organisations).
Factor |
Initial Eigenvalues |
Extraction Sums of Squared Loadings |
Rotation Sums of Squared Loadings |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
1 |
11,460 |
47,748 |
47,748 |
11,120 |
46,333 |
46,333 |
6,373 |
26,553 |
26,553 |
2 |
2,787 |
11,613 |
59,361 |
2,456 |
10,235 |
56,569 |
4,029 |
16,786 |
43,339 |
3 |
1,581 |
6,589 |
65,950 |
1,272 |
5,298 |
61,867 |
3,740 |
15,582 |
58,922 |
4 |
1,209 |
5,037 |
70,987 |
0,844 |
3,517 |
65,383 |
1,551 |
6,462 |
65,383 |
5 |
0,947 |
3,944 |
74,931 |
|
|
|
|
|
|
6 |
0,741 |
3,089 |
78,021 |
|
|
|
|
|
|
7 |
0,590 |
2,459 |
80,479 |
|
|
|
|
|
|
8 |
0,522 |
2,174 |
82,653 |
|
|
|
|
|
|
9 |
0,494 |
2,057 |
84,710 |
|
|
|
|
|
|
10 |
0,479 |
1,994 |
86,704 |
|
|
|
|
|
|
11 |
0,445 |
1,856 |
88,560 |
|
|
|
|
|
|
12 |
0,376 |
1,568 |
90,128 |
|
|
|
|
|
|
13 |
0,318 |
1,325 |
91,452 |
|
|
|
|
|
|
14 |
0,290 |
1,210 |
92,662 |
|
|
|
|
|
|
15 |
0,258 |
1,075 |
93,738 |
|
|
|
|
|
|
16 |
0,233 |
0,970 |
94,708 |
|
|
|
|
|
|
17 |
0,210 |
0,877 |
95,585 |
|
|
|
|
|
|
18 |
0,200 |
0,835 |
96,420 |
|
|
|
|
|
|
19 |
0,188 |
0,785 |
97,204 |
|
|
|
|
|
|
20 |
0,170 |
0,707 |
97,911 |
|
|
|
|
|
|
21 |
0,151 |
0,631 |
98,542 |
|
|
|
|
|
|
22 |
0,141 |
0,587 |
99,129 |
|
|
|
|
|
|
23 |
0,122 |
0,509 |
99,637 |
|
|
|
|
|
|
24 |
0,087 |
0,363 |
100,000 |
|
|
|
|
|
|
Table 16.
below represents the exploratory factor analysis for research objective 3 (causes of interface risks).
Table 16.
below represents the exploratory factor analysis for research objective 3 (causes of interface risks).
Factor |
Initial Eigenvalues |
Extraction Sums of Squared Loadings |
Rotation Sums of Squared Loadings |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
Total |
% of Variance |
Cumulative % |
1 |
9,587 |
50,460 |
50,460 |
9,204 |
48,443 |
48,443 |
4,820 |
25,367 |
25,367 |
2 |
1,960 |
10,317 |
60,776 |
1,568 |
8,251 |
56,694 |
4,007 |
21,089 |
46,456 |
3 |
1,194 |
6,285 |
67,061 |
0,821 |
4,320 |
61,014 |
2,766 |
14,558 |
61,014 |
4 |
0,856 |
4,507 |
71,569 |
|
|
|
|
|
|
5 |
0,697 |
3,669 |
75,237 |
|
|
|
|
|
|
6 |
0,640 |
3,370 |
78,607 |
|
|
|
|
|
|
7 |
0,561 |
2,954 |
81,561 |
|
|
|
|
|
|
8 |
0,470 |
2,476 |
84,036 |
|
|
|
|
|
|
9 |
0,429 |
2,255 |
86,292 |
|
|
|
|
|
|
10 |
0,388 |
2,041 |
88,332 |
|
|
|
|
|
|
11 |
0,353 |
1,856 |
90,188 |
|
|
|
|
|
|
12 |
0,331 |
1,740 |
91,928 |
|
|
|
|
|
|
13 |
0,323 |
1,701 |
93,629 |
|
|
|
|
|
|
14 |
0,272 |
1,433 |
95,062 |
|
|
|
|
|
|
15 |
0,235 |
1,235 |
96,297 |
|
|
|
|
|
|
16 |
0,225 |
1,185 |
97,482 |
|
|
|
|
|
|
17 |
0,190 |
1,000 |
98,481 |
|
|
|
|
|
|
18 |
0,168 |
0,883 |
99,364 |
|
|
|
|
|
|
19 |
0,121 |
0,636 |
100,000 |
|
|
|
|
|
|
Table 17.
reliability statistics for research objective 1 – B2 (consequences of poor and ineffective interface risks management approach).
Table 17.
reliability statistics for research objective 1 – B2 (consequences of poor and ineffective interface risks management approach).
Reliability Statistics |
Cronbach's Alpha |
N of Items |
0,907 |
13 |
Table 18.
item-total statistics for research objective 1.
Table 18.
item-total statistics for research objective 1.
Item-Total Statistics |
|
Scale Mean if Item Deleted |
Scale Variance if Item Deleted |
Corrected Item-Total Correlation |
Cronbach's Alpha if Item Deleted |
B2.1 |
48,80 |
41,932 |
0,544 |
0,904 |
B2.2 |
48,78 |
41,420 |
0,577 |
0,902 |
B2.3 |
48,46 |
41,916 |
0,606 |
0,901 |
B2.4 |
48,75 |
40,433 |
0,666 |
0,898 |
B2.5 |
49,00 |
41,382 |
0,554 |
0,904 |
B2.6 |
48,59 |
41,253 |
0,653 |
0,899 |
B2.7 |
49,08 |
41,121 |
0,615 |
0,901 |
B2.8 |
48,68 |
41,178 |
0,656 |
0,899 |
B2.9 |
48,66 |
40,744 |
0,650 |
0,899 |
B2.10 |
48,90 |
41,328 |
0,667 |
0,899 |
B2.11 |
48,57 |
41,335 |
0,662 |
0,899 |
B2.12 |
48,81 |
41,420 |
0,645 |
0,900 |
B2.13 |
48,64 |
41,624 |
0,618 |
0,901 |
Table 19.
reliability statistics for research objective 2 - B3 (What are the interface risks management approaches by organisations).
Table 19.
reliability statistics for research objective 2 - B3 (What are the interface risks management approaches by organisations).
Reliability Statistics |
Cronbach's Alpha |
N of Items |
0,952 |
24 |
Table 20.
item-total statistics for research objective 2.
Table 20.
item-total statistics for research objective 2.
Item-Total Statistics |
|
Scale Mean if Item Deleted |
Scale Variance if Item Deleted |
Corrected Item-Total Correlation |
Cronbach's Alpha if Item Deleted |
B3.1 |
93,35 |
152,170 |
0,611 |
0,950 |
B3.2 |
93,66 |
151,499 |
0,588 |
0,950 |
B3.3 |
93,66 |
148,607 |
0,658 |
0,950 |
B3.4 |
93,72 |
151,057 |
0,595 |
0,950 |
B3.5 |
93,63 |
147,695 |
0,684 |
0,949 |
B3.6 |
93,43 |
150,207 |
0,643 |
0,950 |
B3.7 |
93,35 |
149,982 |
0,659 |
0,950 |
B3.8 |
93,47 |
150,662 |
0,576 |
0,951 |
B3.9 |
93,45 |
149,435 |
0,676 |
0,949 |
B3.10 |
93,41 |
150,881 |
0,682 |
0,949 |
B3.11 |
93,34 |
148,834 |
0,727 |
0,949 |
B3.12 |
93,32 |
151,621 |
0,654 |
0,950 |
B3.13 |
93,49 |
149,114 |
0,674 |
0,949 |
B3.14 |
93,45 |
150,327 |
0,719 |
0,949 |
B3.15 |
93,49 |
149,653 |
0,641 |
0,950 |
B3.16 |
93,63 |
151,205 |
0,683 |
0,949 |
B3.17 |
93,66 |
147,716 |
0,710 |
0,949 |
B3.18 |
93,65 |
151,062 |
0,651 |
0,950 |
B3.19 |
93,73 |
147,484 |
0,715 |
0,949 |
B3.20 |
93,69 |
150,822 |
0,642 |
0,950 |
B3.21 |
93,64 |
149,036 |
0,683 |
0,949 |
B3.22 |
93,39 |
151,896 |
0,630 |
0,950 |
B3.23 |
93,23 |
149,965 |
0,672 |
0,950 |
B3.24 |
93,27 |
152,896 |
0,574 |
0,951 |
Table 21.
reliability statistics for research objective 3 - B4 (causes of interface risks).
Table 21.
reliability statistics for research objective 3 - B4 (causes of interface risks).
Reliability Statistics |
Cronbach's Alpha |
N of Items |
0,945 |
19 |
Table 22.
item-total statistics for research objective 3 – B4 (causes of interface risks).
Table 22.
item-total statistics for research objective 3 – B4 (causes of interface risks).
Item-Total Statistics |
|
Scale Mean if Item Deleted |
Scale Variance if Item Deleted |
Corrected Item-Total Correlation |
Cronbach's Alpha if Item Deleted |
B4.1 |
72,19 |
99,701 |
0,645 |
0,942 |
B4.2 |
72,48 |
100,006 |
0,577 |
0,943 |
B4.3 |
72,45 |
98,082 |
0,672 |
0,942 |
B4.4 |
72,51 |
98,683 |
0,646 |
0,942 |
B4.5 |
72,47 |
96,966 |
0,705 |
0,941 |
B4.6 |
72,23 |
99,413 |
0,606 |
0,943 |
B4.7 |
72,25 |
97,700 |
0,730 |
0,941 |
B4.8 |
72,46 |
98,583 |
0,644 |
0,942 |
B4.9 |
72,13 |
98,631 |
0,654 |
0,942 |
B4.10 |
72,23 |
98,945 |
0,654 |
0,942 |
B4.11 |
72,54 |
97,642 |
0,705 |
0,941 |
B4.12 |
72,65 |
96,659 |
0,712 |
0,941 |
B4.13 |
72,44 |
97,973 |
0,627 |
0,943 |
B4.14 |
72,23 |
100,315 |
0,578 |
0,943 |
B4.15 |
72,45 |
96,690 |
0,752 |
0,940 |
B4.16 |
72,54 |
98,505 |
0,687 |
0,942 |
B4.17 |
72,84 |
95,338 |
0,703 |
0,941 |
B4.18 |
72,99 |
95,838 |
0,692 |
0,942 |
B4.19 |
72,52 |
97,525 |
0,725 |
0,941 |