Definition and Diagram of Symbols
Figure 1.
Schematic diagram of the power system operating coordinate system .
Figure 1.
Schematic diagram of the power system operating coordinate system .
a. Synchronised system operation before disturbance, and . The magenta dot indicates the operating point of the generator:.
b. The angle of rotation rate of the subsystems differ after the disturbance. are the per unit voltage of the port bus of the Kth and Lth generators, respectively, is the difference in the angle of rotation rate between the Kth and Lth generators. is defined as the coupling potential difference between generators Kth and Lth (yellow dotted line between Cyan dots). Correspondingly, is constructed to describe the synchronous potential difference between generators Kth and Lth (solid blue line between magenta square dots).
Extensive interconnections between generators would make stability analysis very difficult(see Figure S1). To solve this problem, the concept of a meta-generator is introduced here. At moment t, the instantaneous values of the n generators system are arranged in descending order by , relabelled, and then reconstituted as the n meta-generator system .
Data Sources and Experimental Procedures
In this study, the New England test system and 3-generator test system (
Figures S4,S5,S6) were used. The two models are simulated separately using a simulation software package. Here, the fault was set as a three-phase short circuit to ground. The disturbed operating point of each generator was calculated. To observe the movement pattern of the disturbed operating points, the parameters of the control elements are set to 0.
In advance, the fault location was fixed, and the fault duration was set. This experiment simulated the rotation rate and port bus voltage of the ith generator after different disturbances. Then, the angle of rotation rate of the ith generator was calculated. was increased in a fixed step length and , were calculated again until the system was destabilised. The faulty position was replaced, and the above steps were repeated.
Subsequently, was arranged and relabelled as . This was then averaged as follows:
The mean of over was found: and .
The mean of over was also found: . There are several definitions of mean, and the simplest, i.e., the arithmetic mean, was used here.
This work added adjacent meta-generator data
and
to the coordinate system
to assess the system stability (
Figure 1(b)) and time intervals of instability
(
Figure 1(d)).
An expression was fitted with
as the independent variable and
as the dependent variable (
Figure 3). The critical clearing time (CCT) and the unstable equilibrium point (UEP) were then calculated.
Near the boundary, was calculated at a finer scale.
Derivation of the Boundary Equation
As shown in
Figure 1,
,
.
Following the form of power in electricity , the coupling power is defined to characterise the coupling between the meta-generators. To describe the energy required for the generator to maintain synchronous stability, the synchronous power is constructed: . is the impedance between the Kth and Lth meta-generators.
When the system is synchronized, the meta-generators are not in balance and are still coupled (). When the system is disturbed, increases from 0, increases from 0, and changes. When the coupling power between the two meta-generators is sufficient to provide synchronous power, i.e., , the system is synchronous and stable. Conversely, when , there is not enough coupling power to maintain synchronization, and the system is unstable. It is observed that . The set of points where is the synchronous stability boundary.
In summary,
is the system stability boundary equation. When
, the system is stable. When
, the system is unstable. Geometrically,
describes a curved surface that, together with
, encloses a stable domain. In summary, the boundary equation
can be found, where
. The coordinate system
is established, and the boundary is visualized(
Figure 1).
To determine the stability of a power system of n generators, only n pairs of variables are needed, which are physically meaningful and easily obtainable.
Operating Point Behaviour on the Boundary
is the derivative of
of the meta-generators with respect to
. Near the boundary, the derivative of
of the partial meta-generators changes from positive to negative (
Figure 3). For this unusual phenomenon, on a finer scale,
is calculated sequentially for different
. The standard deviation of
is calculated separately (
Figure 2):
.
a and b correspond to New England test system, generator disturbed instability process Schematic diagram of the disturbed trajectory of the operating point crossing the boundary after a three-phase short-circuit ground fault at 12-node and 18-node in node IEEE39 with gradually increasing ∆t, respectively. (∆t increases from 0.04s, until destabilization)
The expressions for the disturbed operating points of the meta-generators and generators have the same form before and after permutation.
a. The projection of the disturbed trajectory in the
plane. The result of the fit is
, and the adjusted R-squared value is 1.
b. The projection of the disturbed trajectory in the
plane. The result of the fit is
and the adjusted R-squared value is 0.99905.
c. The projection of the disturbed trajectory in the
plane. The result of the fit is
and the adjusted R-squared value is 0.9993.
d. The projection of the disturbed trajectory in the
plane. The result of the fit is
and the adjusted R-squared value is 1.
e. The projection of the disturbed trajectory in the
plane. The result of the fit is
and the adjusted R-squared value is 0.99981.
The 18-node three-phase short-circuit ground fault, increase in fault time from 0.140s to 0.154s, and the trajectory of disturbed operating point near the boundary. The arrow shows the direction of increase of . The generator has the same barrier and attractor as the meta-generator.
a. In the plane, running points appear to cross the barrier before they reach the boundary, and the elliptical area marks the position of the barrier. From 0.147s onwards the interval between running points decreases in the direction of increasing
b. In the plane, the graph is presented as a critical state local attractor, which appears simultaneously with the synchronous barrier. The ellipse indicates the position of the attractor. The graph of the trajectory of the run point from 0.147s onwards is shown as an attractor (in the shaded area).
The perturbed trajectory of the generator shows the same result at the same time.
a. The same boundary equation applise to the 3-gen system. 4-node sets the location of the operating point after a three-phase short-circuit ground fault.
b. Results of the multiswing instability for Δt=0.245s.
c and d are the results of the 4-node three-phase ground fault simulation, respectively. It is synchronization at , out-of-Sync at , and out-of-Sync in .
Fitting results for perturbed trajectories for the 4-node trajectory of disturbed operating points after a three-phase short-circuit ground fault..
a. The projection of the disturbed trajectory in the plane. The result of the fit is . The adjusted R-squared value is 0.99997.
b. The projection of the disturbed trajectory in the plane. The result of the fit is , and the adjusted R-squared value is 0.97679.
c. The projection of the disturbed trajectory in the plane. The result of the fit is , and the adjusted R-squared value is 0.99519.
d. The projection of the disturbed trajectory in the plane. The result of the fit is , and the adjusted R-squared value is 0.99925.
e. The projection of the disturbed trajectory in the plane. The result of the fit is , and the adjusted R-squared value is 0.99973.
a. The standard deviation of δ decreases from ∆t=0.227s. It rises by 2200% at ∆t=0.245s, where there is an instability.
b. Derive from the fitted equation (e). Due to the monotonicity of with respect to , i.e. , changes from positive to negative and changes from greater than 1 to less than 1.
A three-phase short-circuit ground fault is set at the corresponding node. a, b, c, d, e correspond to the critical behaviour of the operating points after the failure of 6-node, 12-node, 24-node, 30-node & 36-node respectively. All the results show that near the boundary, there is always a significant decrease in . These results demonstrate a strong correlation between synchronisation stability boundary and spontaneous synchronisation.
f and g show that the behaviour of the operating points also show the phenomenon of synchronous barrier when faults are set at 6-node and 24-node (shaded area).
The meta-generator operating point data and are substituted into equation 3) to obtain , respectively. Substitute and into equation 4) to obtain and, respectively. CCT(sim) is obtained from professional software simulation. and are the simulation values of and , respectively. Notably, only a single piece of information from is used to calculate here, so it adds to the error.