Altmetrics
Downloads
95
Views
70
Comments
0
Submitted:
28 April 2024
Posted:
01 May 2024
You are already at the latest version
No. | FIDIC Sub-Clause | Claim Description | Claim Party | Sort of Claim (Additional) | |||
---|---|---|---|---|---|---|---|
Employer (E) |
Contractor (C) | Cost (C) |
Profit (P) | Time (T) |
|||
1 | 4.2.a | Failure to extend validity of the performance security | E | C | |||
2 | 4.2.b | Failure to pay agreed amount due. | E | C | |||
3 | 4.14 | Avoidance of Interference | E | C | |||
4 | 4.16 | Damages, losses and expenses resulting from Transport | E | C | |||
5 | 4.19 | Payment of electricity, water or gas | E | C | |||
6 | 4.2 | Employer's equipment or free-issue materials | E | C | |||
7 | 7.5 | Rejection of defective plant and / or materials | E | C | |||
8 | 7.6 | Contractor's failure to remedy defects | E | C | |||
9 | 8.6 | Revised methods of working due to poor rate of progress | E | C | |||
10 | 8.7 | Delay damages | E | C | |||
11 | 9.4 | Failed tests on completion | E | C | |||
12 | 11.4 | A failure to rectify defects | E | C | |||
13 | 15.4 | Termination by employer | E | C | |||
14 | 18.1 | Contractor's failure to insure | E | C | |||
15 | 18.2 | Contractor's inability to insure | E | C | |||
16 | 1.9 | Delayed drawings or instructions | C | C | P | T | |
17 | 2.1 | Right of access to, or possession of the site | C | C | P | T | |
18 | 4.2 | Delay of performance security payment after performance certificate issuing | C | C | P | T | |
19 | 4.7 | Errors in setting out information | C | C | P | T | |
20 | 4.12 | Unforeseen physical conditions | C | C | T | ||
21 | 4.24 | Fossils, ancient artifacts, archaeological or geological items | C | C | T | ||
22 | 7.4 | Additional tests instructed by the engineer | C | C | P | T | |
23 | 8.4.a | A variation or significant change to the quantities | C | T | |||
24 | 8.4.c | Unusual bad weather | C | T | |||
25 | 8.4.d | Shortage of personnel or goods | C | T | |||
26 | 8.4.e | Employer's delay or impediment | C | T | |||
27 | 8.5 | Delays caused by authorities | C | T | |||
28 | 8.9 | Suspension and/or resuming work after suspension | C | C | T | ||
29 | 10.2 | The Employer using part of the works | C | C | P | ||
30 | 10.3 | Prevention from undertaking tests on completion | C | C | P | T | |
31 | 12.4 | An omission of works | C | C | T | ||
32 | 13.2 | An adopted value engineering proposal | C | C | P | ||
33 | 13.7 | Changes in legislation | C | C | T | ||
34 | 14.8 | Delayed payment | C | C | |||
35 | 16.1 | Suspension initiated by the contractor | C | C | P | T | |
36 | 16.4 | Termination initiated by the contractor | C | C | P | ||
37 | 17.1 | Damage or injury caused by Employer's personnel agents | C | C | |||
38 | 17.4 | Ambiguity in Documents | C | C | P | T | |
39 | 17.4 | Loss or damage to the works caused by Employer's Risks (poor design etc.) | C | C | P | T | |
40 | 18.1 | Insurances supplied by the Employer's | C | C | |||
41 | 19.4 | Force Majeure | C | C | P | T | |
42 | 19.6 | Optional payment and release due to termination | C | C | P | ||
43 | 5.2 | Refusal of contractor objection to nomination | C | C | P | T | |
44 | 11.8 | An instruction to search for defect | C | C | P | T | |
45 | 8.3 | Acceleration of Works | C | C | P | T | |
46 | 8.10 | Payment for plant and material in event of suspension | C | C | |||
47 | 16.2 | Client’s Breach of Contract | C | C | P | ||
48 | 16.2 | Inflation / Price Escalation | C | C | P | ||
49 | 16.2 | Currency Fluctuation | C | C | P | ||
50 | 5.2 | Default of Nominated Subcontractor or Suppliers | C | C | P | T | |
51 | 19.6 | Rectification of Damage Due to Unexpected Risk | C | C | P | T |
No. | List of Causes | No. | List of Causes |
---|---|---|---|
01 | Inadequate/ Inaccurate Design Information | 16 | Inappropriate/ Unexpected Cost Control (Target) |
02 | Inadequate Design Documentation | 17 | Inappropriate/ Unexpected Quality Control (Target) |
03 | Inadequate Brief | 18 | Poor Communications Among Project Participants |
04 | Unclear & Inadequate Specifications | 19 | Lack of Information for Decision Making; (Decisiveness) |
05 | Inappropriate Contract Type (Strategy) | 20 | Slow Client Response |
06 | Inappropriate Contract Form | 21 | Changes by Client |
07 | Inadequate Contract Administration | 22 | Lack of Competence of Project Participants |
08 | Inadequate Contract Documentation | 23 | Poor Workmanship |
09 | Incomplete Tender Information | 24 | Inadequate Site Investigation |
10 | Inappropriate Contractor Selection | 25 | Unrealistic Information Expectations ( By Contractor) |
11 | Unrealistic Tender Pricing | 26 | Lack of Team Spirit Among Participants |
12 | Unrealistic Client Expectations | 27 | Personality Clashes Among Project Participants |
13 | Inappropriate Payment Method | 28 | Poor Management By One or More Project Participants |
14 | Inappropriate Document Control | 29 | Adversarial Culture Among project Participants |
15 | Inappropriate/ Unexpected Time Control | 30 | Uncontrollable External Events |
31 | Exaggerated Claims |
Code# | Type | Type Frequency | Type Frequency Index | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Very Low | Low | Average | High | Very High | Mean | RII | Rank | |||
T16 | Delayed drawings or instructions | 1 | 5 | 48 | 16 | 6 | 3.28 | 65.53 | 1 | |
T23 | A variation or significant change to the quantities | 3 | 4 | 44 | 19 | 6 | 3.28 | 65.53 | 2 | |
T38 | Ambiguity in Documents | 5 | 13 | 43 | 11 | 4 | 2.95 | 58.95 | 3 | |
T45 | Acceleration of Works | 3 | 10 | 54 | 9 | 0 | 2.91 | 58.16 | 4 | |
T31 | An omission of work forming | 3 | 18 | 48 | 7 | 0 | 2.78 | 55.53 | 5 | |
T34 | Delayed payment | 2 | 25 | 43 | 4 | 2 | 2.72 | 54.47 | 6 | |
T25 | Shortage of personnel or goods | 2 | 38 | 29 | 4 | 3 | 2.58 | 51.58 | 7 | |
T07 | Rejection of defective plant and / or materials | 3 | 36 | 30 | 7 | 0 | 2.54 | 50.79 | 8 | |
T09 | Revised methods of working due to slow progress | 3 | 38 | 28 | 6 | 1 | 2.53 | 50.53 | 9 | |
T10 | Delay damages | 3 | 36 | 33 | 2 | 2 | 2.53 | 50.53 | 10 |
Code# | Type | Type Impact | Type Impact Index | ||||||
---|---|---|---|---|---|---|---|---|---|
Very Low | Low | Average | High | Very High | Mean | RII | Rank | ||
T39 | Loss or damage to the works caused Employer's Risks (War, riots, munitions, poor design .. | 6 | 2 | 4 | 18 | 46 | 4.26 | 85.26 | 1 |
T47 | Client’s Breach of Contract | 4 | 5 | 2 | 21 | 44 | 4.26 | 85.26 | 2 |
T16 | Delayed drawings or instructions | 1 | 3 | 7 | 34 | 31 | 4.20 | 83.95 | 3 |
T41 | Force Majeure | 3 | 7 | 7 | 24 | 35 | 4.07 | 81.32 | 4 |
T27 | Delays caused by authorities | 2 | 4 | 3 | 46 | 21 | 4.05 | 81.05 | 5 |
T38 | Ambiguity in Documents | 1 | 4 | 7 | 42 | 22 | 4.05 | 81.05 | 6 |
T33 | Changes in legislation | 7 | 3 | 2 | 40 | 24 | 3.93 | 78.68 | 7 |
T23 | A variation or change of the quantities | 2 | 1 | 16 | 42 | 15 | 3.88 | 77.63 | 8 |
T26 | Employer's delay or impediment | 4 | 1 | 23 | 41 | 7 | 3.61 | 72.11 | 9 |
T48 | Inflation / Price Escalation | 3 | 2 | 27 | 34 | 10 | 3.61 | 72.11 | 10 |
Code | Cause Description | Clients | Consultants | Contractors | Overall |
---|---|---|---|---|---|
C01 | Inadequate/ Inaccurate Design Information | 100.00% | 100.00% | 93.80% |
98.68% |
C21 | Changes by Client | 100.00% |
97.70% |
87.50% |
96.05% |
C19 | Lack of Information for Decision Making; (Decisiveness) | 100.00% |
93.00% |
93.80% |
94.74% |
C23 | Poor Workmanship | 100.00% |
90.70% |
100.00% |
94.74% |
C30 | Uncontrollable External Events | 100.00% |
93.00% |
93.80% |
94.74% |
C02 | Inadequate Design Documentation | 94.10% |
95.30% |
87.50% |
93.42% |
C04 | Unclear & Inadequate Specifications | 94.10% |
97.70% |
81.30% |
93.42% |
C16 | Inappropriate/ Unexpected Cost Control (Target) | 100.00% |
93.00% |
87.50% |
93.42% |
C09 | Incomplete Tender Information | 88.20% |
95.30% |
87.50% |
92.11% |
C15 | Inappropriate/ Unexpected Time Control (Target) | 100.00% |
93.00% |
81.30% |
92.11% |
C22 | Lack of Competence of Project Participants | 94.10% |
93.00% |
81.30% |
92.11% |
C05 | Inappropriate Contract Type (Strategy) | 88.20% |
95.30% |
81.30% |
90.79% |
C08 | Inadequate Contract Documentation | 94.10% |
93.00% |
81.30% |
90.79% |
C18 | Poor Communications Among Project Participants | 100.00% |
90.70% |
81.30% |
90.79% |
C20 | Slow Client Response | 100.00% |
90.70% |
81.30% |
90.79% |
C31 | Exaggerated Claims | 100.00% |
93.00% |
75.00% |
90.79% |
C07 | Inadequate Contract Administration | 88.20% |
95.30% |
75.00% |
89.47% |
C11 | Unrealistic Tender Pricing | 100.00% |
86.00% |
87.50% |
89.47% |
C14 | Inappropriate Document Control | 100.00% |
86.00% |
87.50% |
89.47% |
C24 | Inadequate Site Investigation | 94.10% |
88.40% |
87.50% |
89.47% |
C03 | Inadequate Brief | 94.10% |
88.40% |
81.30% |
88.16% |
C12 | Unrealistic Client Expectations | 100.00% |
86.00% |
81.30% |
88.16% |
C17 | Inappropriate/ Unexpected Quality Control (Target) | 100.00% |
81.40% |
93.80% |
88.16% |
C26 | Lack of Team Spirit Among Participants | 94.1% | 90.70% | 75.00% |
88.16% |
C28 | Poor Management By One or More Project Participants | 94.1% | 86.00% |
87.50% |
88.16% |
C10 | Inappropriate Contractor Selection | 94.1% | 88.40% |
75.00% |
86.84% |
C06 | Inappropriate Contract Form | 88.20% |
88.40% |
75.00% |
85.53% |
C25 | Unrealistic Information Expectations ( By the Contractor) | 94.10% | 86.00% |
75.00% |
85.53% |
C27 | Personality Clashes Among Project Participants | 94.10% |
86.00% |
75.00% |
85.53% |
C29 | Adversarial (industry) Culture Among project Participants | 94.10% |
86.00% |
75.00% |
85.53% |
C13 | Inappropriate Payment Method | 94.10% |
86.00% |
68.80% |
84.21% |
Code # |
Cause Description |
Cause Significance | Cause Significance Index | ||||||
---|---|---|---|---|---|---|---|---|---|
Very Low | Low | Average | High | Very High | Mean | RII | Rank | ||
C15 | Inappropriate/ Unexpected Time Control (Target) | 3 | 3 | 7 | 16 | 47 | 4.33 | 86.58 | 1 |
C10 | Inappropriate Contractor Selection | 1 | 3 | 8 | 23 | 41 | 4.32 | 86.32 | 2 |
C05 | Inappropriate Contract Type | 4 | 3 | 8 | 12 | 49 | 4.30 | 86.05 | 3 |
C16 | Inappropriate/ Unexpected Cost Control (Target) | 3 | 4 | 7 | 15 | 47 | 4.30 | 86.05 | 3 |
C21 | Changes by Client | 3 | 3 | 6 | 20 | 44 | 4.30 | 86.05 | 3 |
C19 | Lack of (Decisiveness) | 2 | 6 | 5 | 18 | 45 | 4.29 | 85.79 | 4 |
C20 | Slow Client Response | 2 | 5 | 5 | 28 | 36 | 4.20 | 83.95 | 5 |
C17 | Inappropriate/ Unexpected QC | 5 | 2 | 10 | 22 | 37 | 4.11 | 82.11 | 6 |
C01 | Inadequate/ Inaccurate Design | 2 | 3 | 7 | 38 | 26 | 4.09 | 81.84 | 7 |
C06 | Inappropriate Contract Form | 5 | 4 | 6 | 25 | 36 | 4.09 | 81.84 | 7 |
Code # |
Cause Description |
Cause Avoid-ability | Cause Avoid-ability Index | ||||||
---|---|---|---|---|---|---|---|---|---|
Very Low | Low | Average | High | Very High | Mean | RII | Rank | ||
C10 | Inappropriate Contractor Selection | 2 | 5 | 23 | 41 | 5 | 3.55 | 71.05 | 1 |
C13 | Inappropriate Payment Method | 4 | 3 | 20 | 47 | 2 | 3.53 | 70.53 | 2 |
C06 | Inappropriate Contract Form | 3 | 7 | 25 | 31 | 10 | 3.50 | 70.00 | 3 |
C05 | Inappropriate Contract Type (Strategy) | 3 | 6 | 31 | 24 | 12 | 3.47 | 69.47 | 4 |
C01 | Inadequate/ Inaccurate Design Information | 2 | 5 | 34 | 31 | 4 | 3.39 | 67.89 | 5 |
C24 | Inadequate Site Investigation | 1 | 5 | 39 | 26 | 5 | 3.38 | 67.63 | 6 |
C04 | Unclear & Inadequate Specifications | 1 | 7 | 40 | 25 | 3 | 3.29 | 65.79 | 7 |
C02 | Inadequate Design Documentation | 1 | 8 | 44 | 19 | 4 | 3.22 | 64.47 | 8 |
C08 | Inadequate Contract Documentation | 1 | 10 | 42 | 21 | 2 | 3.17 | 63.42 | 9 |
C07 | Inadequate Contract Administration | 4 | 4 | 51 | 15 | 2 | 3.09 | 61.84 | 10 |
C09 | Incomplete Tender Information | 1 | 8 | 53 | 11 | 3 | 3.09 | 61.84 | 10 |
Code |
Type |
Role of the Respondents (PC01) |
Managerial Level (PC02) |
Personal Experience (PC03) |
Organization/ Firm’s Experience (Years) (PC04) |
Organization/ Firm’s Annual Number of Projects (PC05) | Organization/ Firm’s Number of Employees (PC06) | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Kruskal- Wallis H |
(P-Value) | Kruskal- Wallis H |
(P-Value) | Kruskal- Wallis H |
(P-Value) | Kruskal- Wallis H |
(P-Value) |
Kruskal- Wallis H |
(P-Value) | Kruskal- Wallis H |
(P-Value) | |||
T12 | A failure to rectify defects | 3.757 | 0.153 | 0.880 | 0.644 | 10.716 | 0.030 | .0.27 | 0.866 | 1.495 | 0.828 | 1.233 | 0.873 | |
T14 | Contractor's failure to insure | 0.389 | 0.823 | 1.935 | 0.380 | 4.351 | 0.361 | 12.058 | 0.017 | 6.596 | 0.159 | 2.853 | 0.583 | |
T16 | Delayed drawings or instructions | 0.741 | 0.690 | 2.696 | 0.260 | 1.402 | 0.844 | 13.614 | 0.009 | 6.451 | 0.168 | 1.103 | 0.894 | |
T36 | Termination initiated by the contractor | 5.676 | 0.059 | 2.776 | 0.250 | 3.372 | 0.498 | 10.077 | 0.039 | 2.345 | 0.673 | 15.413 | 0.004 | |
T39 | Loss or damage to the works caused Employer's Risks | 1.232 | 0.540 | 0.949 | 0.622 | 6.340 | 0.175 | 7.578 | 0.108 | 14.220 | 0.007 | 6.147 | 0.188 |
Code |
Type |
Role of the Respondents (PC01) | Managerial Level (PC02) | Personal Experience (PC03) | Firm’s Experience in business) (PC04) |
Firm’s Annual Number of Projects (PC05) | Firm’s Number of Employees (PC06) | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | |||
T02 | Failure to pay agreed amount due. | 9.810 | 0.007 | 0.853 | 0.653 | 5.711 | 0.222 | 12.868 | 0.012 | 1.668 | 0.797 | 0.941 | 0.919 | |
T11 | Failed tests on completions | 12.143 | 0.002 | 0.980 | 0.613 | 1.286 | 0.864 | 11.567 | 0.021 | 4.106 | 0.392 | 1.291 | 0.863 | |
T16 | Delayed drawings or instructions | 4.236 | 0.120 | 1.286 | 0.526 | 6.177 | 0.186 | 5.823 | 0.213 | 13.615 | 0.009 | 10.538 | 0.032 | |
T21 | Fossils, archaeological or geological | 6.722 | 0.035 | 0.806 | 0.668 | 0.793 | 0.939 | 7.127 | 0.129 | 1.836 | 0.766 | 4.559 | 0.336 | |
T22 | Additional tests by the engineer | 4.437 | 0.109 | 6.532 | 0.038 | 4.671 | 0.323 | 1.841 | 0.765 | 3.470 | 0.482 | 1.201 | 0.878 | |
T25 | Shortage of personnel or goods | 4.334 | 0.115 | 6.174 | 0.046 | 6.841 | 0.145 | 2.121 | 0.713 | 2.726 | 0.605 | 1.870 | 0.760 | |
T26 | Employer's delay or impediment | 2.120 | 0.346 | 4.185 | 0.123 | 0.414 | 0.981 | 1.632 | 0.803 | 2.038 | 0.729 | 10.035 | 0.040 | |
T27 | Delays caused by authorities | 6.376 | 0.041 | 1.003 | 0.606 | 1.882 | 0.757 | 4.640 | 0.326 | 11.746 | 0.019 | 5.343 | 0.254 | |
T29 | Employer using works partially | 0.105 | 0.949 | 7.149 | 0.028 | 3.864 | 0.425 | 4.435 | 0.350 | 5.405 | 0.248 | 2.994 | 0.559 | |
T32 | Adopt value engineering proposal | 2.326 | 0.312 | 7.327 | 0.026 | 0.248 | 0.993 | 2.123 | 0.713 | 3.247 | 0.517 | 0.491 | 0.974 | |
T38 | Ambiguity in Documents | 6.357 | 0.042 | 0.663 | 0.718 | 2.917 | 0.572 | 1.028 | 0.906 | 0.964 | 0.915 | 4.404 | 0.354 | |
T39 | Loss or damage to the works caused Employer's Risks | 3.103 | 0.212 | 2.344 | 0.310 | 5.551 | 0.235 | 3.117 | 0.538 | 12.596 | 0.013 | 9.185 | 0.057 | |
T43 | Refusal of contractor objection to nomination | 6.020 | 0.049 | 2.210 | 0.331 | 6.101 | 0.192 | 3.929 | 0.416 | 2.498 | 0.645 | 1.374 | 0.849 | |
T45 | Acceleration of Works | 6.446 | 0.040 | 1.929 | 0.381 | 7.492 | 0.112 | 4.239 | 0.375 | 3.131 | 0.536 | 2.153 | 0.708 | |
T47 | Client’s Breach of Contract | 4.435 | 0.109 | 0.294 | 0.863 | 1.745 | 0.783 | 5.417 | 0.247 | 8.780 | 0.067 | 10.051 | 0.040 | |
T49 | Currency Fluctuation | 10.413 | 0.005 | 2.801 | 0.246 | 9.776 | 0.044 | 6.154 | 0.188 | 2.455 | 0.653 | 3.481 | 0.481 |
Code |
Cause |
Role of the Respondents (PC01) | Managerial Level (PC02) | Personal Experience (PC03) | Organization/ Firm’s Experience (PC04) | Organization/ Firm’s Annual Number of Projects (PC05) | Organization/ Firm’s Number of Employees (PC06) | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Kruskal-Wallis H | .(P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | .(P-Value) | Kruskal-Wallis H | .(P-Value) | Kruskal-Wallis H | .(P-Value) | ||
C02 | Inadequate Design. | 1.221 | 0.543 | 2.181 | 0.336 | 5.071 | 0.280 | 4.855 | 0.303 | 6.433 | 0.169 | 13.818 | 0.008 |
C03 | Inadequate Brief | 0.997 | 0.608 | 0.045 | 0.978 | 4.924 | 0.295 | 9.823 | 0.044 | 12.967 | 0.011 | 14.055 | 0.007 |
C04 | Unclear & Inadequate Specs. | 4.941 | 0.085 | 1.826 | 0.401 | 2.462 | 0.651 | 21.749 | 0.000 | 5.655 | 0.226 | 5.367 | 0.252 |
C05 | Inappropriate Contract Type | 2.773 | 0.250 | 1.178 | 0.555 | 7.109 | 0.130 | 7.520 | 0.111 | 16.349 | 0.003 | 4.917 | 0.296 |
C06 | Inappropriate Contract Form | 2.015 | 0.365 | 2.237 | 0.327 | 6.817 | 0.146 | 20.442 | 0.000 | 17.144 | 0.002 | 14.043 | 0.007 |
C07 | Inadequate Contract Administration | 5.267 | 0.072 | 1.334 | 0.513 | 2.020 | 0.732 | 14.674 | 0.005 | 4.553 | 0.336 | 0.854 | 0.931 |
C08 | Inadequate Contract Documents | 2.433 | 0.296 | 2.508 | 0.285 | 8.510 | 0.075 | 18.180 | 0.001 | 8.729 | 0.068 | 9.314 | 0.054 |
C09 | Incomplete Tender Information | 1.577 | 0.455 | 0.046 | 0.977 | 5.389 | 0.250 | 6.898 | 0.141 | 11.187 | 0.025 | 11.288 | 0.024 |
C10 | Inappropriate Contractor Selection | 2.707 | 0.258 | 3.805 | 0.149 | 10.949 | 0.027 | 15.995 | 0.003 | 7.654 | 0.105 | 6.037 | 0.196 |
C11 | Unrealistic Tender Pricing | 2.557 | 0.278 | 3.768 | 0.152 | 13.541 | 0.009 | 13.012 | 0.011 | 12.290 | 0.015 | 11.334 | 0.023 |
C12 | Unrealistic Client Expectations | 3.224 | 0.199 | 2.811 | 0.245 | 14.404 | 0.006 | 14.668 | 0.005 | 15.187 | 0.004 | 7.866 | 0.097 |
C13 | Inappropriate Payment Method | 4.218 | 0.121 | 1.526 | 0.466 | 6.919 | 0.140 | 10.975 | 0.027 | 9.080 | 0.059 | 16.076 | 0.003 |
C14 | Inappropriate Document Control | 2.581 | 0.275 | 1.700 | 0.427 | 11.051 | 0.026 | 15.091 | 0.005 | 7.038 | 0.134 | 16.094 | 0.003 |
C16 | Inappropriate/ Unexpected Cost Control (Target) | 2.024 | 0.364 | 1.731 | 0.421 | 7.469 | 0.113 | 5.733 | 0.220 | 5.949 | 0.203 | 13.823 | 0.008 |
C17 | Inappropriate/ Unexpected Quality Control (Target) | 4.758 | 0.093 | 0.106 | 0.948 | 8.535 | 0.074 | 11.844 | 0.019 | 9.188 | 0.057 | 19.021 | 0.001 |
C18 | Poor Communications | 3.506 | 0.173 | 0.358 | 0.836 | 6.813 | 0.146 | 4.159 | 0.385 | 2.665 | 0.615 | 13.069 | 0.011 |
C19 | Lack of (Decisiveness) | 1.221 | 0.543 | 0.804 | 0.669 | 11.500 | 0.021 | 7.138 | 0.129 | 7.686 | 0.104 | 10.905 | 0.028 |
C20 | Slow Client Response | 3.472 | 0.176 | 4.648 | 0.098 | 11.252 | 0.024 | 11.589 | 0.021 | 8.602 | 0.072 | 13.742 | 0.008 |
C21 | Changes by Client | 3.959 | 0.138 | 1.537 | 0.464 | 6.285 | 0.179 | 9.489 | 0.050 | 5.426 | 0.246 | 4.777 | 0.311 |
C24 | Inadequate Site Investigations | 0.464 | 0.793 | 0.011 | 0.995 | 6.324 | 0.176 | 9.965 | 0.041 | 7.853 | 0.097 | 23.056 | 0.000 |
C25 | Unrealistic Expectations ( By the Contractor) | 2.574 | 0.276 | 0.726 | 0.696 | 6.848 | 0.144 | 10.994 | 0.027 | 11.313 | 0.023 | 19.155 | 0.001 |
C27 | Personality Clashes of Participants | 2.463 | 0.292 | 0.866 | 0.648 | 5.909 | 0.206 | 9.581 | 0.048 | 9.259 | 0.055 | 25.707 | 0.000 |
C28 | Poor Management By Participants | 0.738 | 0.692 | 0.047 | 0.977 | 8.442 | 0.077 | 10.064 | 0.039 | 5.525 | 0.238 | 13.343 | 0.010 |
C29 | Adversarial Cultural Affairs | 2.141 | 0.343 | 0.640 | 0.726 | 6.980 | 0.137 | 13.252 | 0.010 | 9.925 | 0.042 | 19.660 | 0.001 |
C30 | Uncontrollable External Events | 1.213 | 0.545 | 0.857 | 0.651 | 11.095 | 0.026 | 7.143 | 0.129 | 3.248 | 0.517 | 10.913 | 0.028 |
C31 | Exaggerated Claims | 7.108 | 0.029 | 1.228 | 0.541 | 7.047 | 0.133 | 7.527 | 0.111 | 7.732 | 0.102 | 4.664 | 0.324 |
Code |
Cause |
Role of the Respondents (PC01) |
Managerial Level (PC02) |
Personal Experience (PC03) |
Organization/ Firm’s Experience (Firm’s Number of Years) (PC04) | Organization/ Firm’s Annual Number of Projects (PC05) |
Organization/ Firm’s Number of Employees (PC06) |
|||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Kruskal-Wallis H |
P-Value |
Kruskal-Wallis H |
P-Value |
Kruskal-Wallis H |
P-Value |
Kruskal-Wallis H |
P-Value |
Kruskal-Wallis H |
P-Value |
Kruskal-Wallis H |
P-Value |
|||
C01 | Inadequate/ Inaccurate Design | 8.92 | 0.012 | 0.372 | 0.830 | 2.069 | 0.723 | 4.038 | 0.401 | 12.699 | 0.013 | 8.493 | 0.075 | |
C03 | Inadequate Brief | 9.09 | 0.01 | 1.894 | 0.388 | 7.387 | 0.117 | 7.114 | 0.130 | 3.263 | 0.515 | 6.746 | 0.150 | |
C04 | Unclear & Inadequate Specifications | 5.04 | 0.080 | 2.802 | 0.246 | 11.111 | 0.025 | 12.551 | 0.014 | 6.064 | 0.194 | 7.515 | 0.111 | |
C05 | Inappropriate Contract Type | 6.95 | 0.031 | 0.702 | 0.704 | 7.852 | 0.097 | 7.395 | 0.116 | 12.882 | 0.012 | 18.944 | 0.001 | |
C06 | Inappropriate Contract Form | 3.002 | 0.223 | 2.110 | 0.348 | 5.036 | 0.284 | 3.565 | 0.468 | 9.563 | 0.048 | 11.976 | 0.018 | |
C07 | Inadequate Contract Administration | 8.91 | 0.012 | 0.579 | 0.749 | 3.059 | 0.548 | 4.436 | 0.350 | 7.796 | 0.099 | 17.400 | 0.002 | |
C08 | Inadequate Contract Docs. | 1.83 | 0.400 | 2.267 | 0.322 | 4.009 | 0.405 | 4.619 | 0.329 | 4.800 | 0.308 | 12.948 | 0.012 | |
C09 | Incomplete Tender Information | 6.14 | 0.046 | 2.411 | 0.300 | 6.970 | 0.138 | 7.981 | 0.092 | 3.713 | 0.446 | 4.670 | 0.323 | |
C10 | Inappropriate Contractor Selection | 2.00 | 0.367 | 2.025 | 0.363 | 10.113 | 0.039 | 8.103 | 0.088 | 13.516 | 0.009 | 16.415 | 0.003 | |
C11 | Unrealistic Tender Pricing | 6.71 | 0.035 | 0.233 | 0.890 | 8.069 | 0.089 | 11.710 | 0.020 | 2.540 | 0.637 | 8.474 | 0.076 | |
C12 | Unrealistic Client Expectations | 9.49 | 0.009 | 1.183 | 0.554 | 1.880 | 0.758 | 5.153 | 0.272 | 5.957 | 0.202 | 9.015 | 0.061 | |
C13 | Inappropriate Payment Method | 4.63 | 0.099 | 0.846 | 0.655 | 3.483 | 0.480 | 2.253 | 0.689 | 7.175 | 0.127 | 12.042 | 0.017 | |
C14 | Inappropriate Document Control | 1.72 | 0.421 | 0.108 | 0.947 | 4.141 | 0.387 | 1.238 | 0.872 | 5.515 | 0.238 | 4.552 | 0.336 | |
C15 | Inappropriate/ Unexpected Time Control (Target) | 7.34 | 0.025 | 0.011 | 0.995 | 7.869 | 0.096 | 7.247 | 0.123 | 14.352 | 0.006 | 21.28 | 0.000 | |
C16 | Inappropriate/ Unexpected Cost Control (Target) | 4.14 | 0.126 | 1.456 | 0.483 | 5.846 | 0.211 | 5.821 | 0.213 | 10.956 | 0.027 | 13.44 | 0.009 | |
C17 | Inappropriate/ Unexpected Quality Control (Target) | 4.85 | 0.088 | 2.925 | 0.232 | 5.286 | 0.259 | 7.227 | 0.124 | 7.661 | 0.105 | 21.705 | 0.000 | |
C18 | Poor Communications | 6.59 | 0.037 | 1.379 | 0.502 | 3.132 | 0.536 | 10.064 | 0.039 | 3.327 | 0.505 | 2.739 | 0.602 | |
C19 | Lack of Decisiveness | 4.63 | 0.099 | 2.345 | 0.310 | 3.896 | 0.420 | 4.594 | 0.332 | 8.482 | 0.075 | 15.25 | 0.004 | |
C20 | Slow Client Response | 10.96 | 0.004 | 0.819 | 0.664 | 9.864 | 0.043 | 4.353 | 0.360 | 16.149 | 0.003 | 6.914 | 0.140 | |
C21 | Changes by Client | 4.271 | 0.118 | 1.245 | 0.536 | 6.882 | 0.142 | 7.331 | 0.119 | 13.584 | 0.009 | 15.214 | 0.004 | |
C23 | Poor Workmanship | 7.948 | 0.019 | 0.668 | 0.716 | 3.692 | 0.449 | 7.843 | 0.098 | 4.764 | 0.312 | 1.142 | 0.888 | |
C24 | Inadequate Site Investigation | 0.837 | 0.658 | 0.320 | 0.852 | 1.904 | 0.753 | 8.113 | 0.088 | 5.419 | 0.247 | 12.387 | 0.015 | |
C28 | Poor Management | 6.953 | 0.031 | 0.240 | 0.887 | 8.590 | 0.072 | 3.515 | 0.476 | 2.022 | 0.732 | 6.483 | 0.166 | |
C29 | Adversarial Cultural Affairs | 15.06 | 0.001 | 0.075 | 0.963 | 4.051 | 0.399 | 7.528 | 0.110 | 10.968 | 0.027 | 10.025 | 0.040 |
Code |
Cause |
Role of the Respondents (PC01) |
Managerial Level (PC02) |
Personal Experience (PC03) |
Organization/ Firm’s Experience (Firm’s Number of Years) (PC04) |
Organization/ Firm’s Annual Number of Projects (PC05) |
Organization/ Firm’s Number of Employees (PC06) | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | Kruskal-Wallis H | (P-Value) | |||
C02 | Inadequate Design | 0.336 | 0.845 | 0.989 | 0.610 | 3.995 | 0.407 | 10.590 | 0.032 | 9.109 | 0.058 | 2.490 | 0.646 | |
C06 | Inappropriate Contract Form | 9.055 | 0.011 | 5.086 | 0.079 | 5.691 | 0.223 | 11.693 | 0.020 | 6.923 | 0.140 | 6.264 | 0.180 | |
C08 | Inadequate Contract Documents | 8.158 | 0.017 | 1.232 | 0.540 | 3.889 | 0.421 | 1.588 | 0.811 | 2.193 | 0.700 | 5.175 | 0.270 | |
C09 | Incomplete Tender Information | 2.093 | 0.351 | 2.717 | 0.257 | 13.175 | 0.010 | 4.111 | 0.391 | 1.753 | 0.781 | 2.316 | 0.678 | |
C10 | Inappropriate Contractor Selection | 2.769 | 0.250 | 2.121 | 0.346 | 9.798 | 0.044 | 1.463 | 0.833 | 3.212 | 0.523 | 2.881 | 0.578 | |
C13 | Inappropriate Payment Method | 1.031 | 0.597 | 0.153 | 0.927 | 5.576 | 0.233 | 10.797 | 0.029 | 7.427 | 0.115 | 13.673 | 0.008 | |
C21 | Changes by Client | 6.743 | 0.034 | 4.693 | 0.096 | 1.210 | 0.876 | 1.191 | 0.880 | 2.101 | 0.717 | 5.204 | 0.267 | |
C30 | Uncontrollable External Events | 0.378 | 0.828 | 1.468 | 0.480 | 10.300 | 0.036 | 2.847 | 0.584 | 2.727 | 0.604 | 3.585 | 0.465 |
TYPE (Frequency) | T16 | T23 | T38 | T45 | T31 | T34 | T25 | T07 | T09 | T10 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|
CAUSE (SIGNIFICANCE) |
Correlation ( Coefficients) |
Delayed drawings or instructions | A variation or significant change to the quantities | Ambiguity in Documents | Acceleration of Works | An omission of work forming | Delayed payments | Shortage of personnel or goods | Rejection of defective plant and / or materials | Revised methods of working due to slow progress | Delay damages | |
C21 | Changes by Client | Correlation | .397** | .242* | .280* | .148 | .366** | .046 | .033 | .054 | -.025 | .114 |
Sig. (2-tailed) | .000 | .035 | .014 | .202 | .001 | .694 | .780 | .644 | .830 | .325 | ||
C10 | Significance Inappropriate Contractor Selection | Correlation | .346** | .279* | .236* | .126 | .411** | .018 | .070 | -.002 | -.005 | .179 |
Sig. (2-tailed) | .002 | .015 | .041 | .277 | .000 | .880 | .546 | .984 | .969 | .122 | ||
C05 | Significance Inappropriate Contract Type (Strategy) | Correlation | .291* | .328** | .251* | .102 | .460** | .034 | -.038 | .066 | .049 | .140 |
Sig. (2-tailed) | .011 | .004 | .028 | .382 | .000 | .768 | .742 | .574 | .674 | .227 | ||
C15 | Significance Inappropriate/ Unexpected Time Control | Correlation | .229* | .258* | .146 | .135 | .320** | .037 | -.005 | .140 | .093 | .187 |
Sig. (2-tailed) | .046 | .025 | .209 | .244 | .005 | .748 | .968 | .229 | .423 | .106 | ||
C16 | Significance Inappropriate/ Unexpected Cost Control | Correlation | .268* | .306** | .133 | .220 | .426** | .157 | .084 | .200 | .204 | .240* |
Sig. (2-tailed) | .019 | .007 | .253 | .056 | .000 | .175 | .472 | .083 | .078 | .037 | ||
C19 | Significance Lack of Decisiveness | Correlation | .320** | .333** | .179 | .266* | .426** | .019 | -.036 | .125 | .147 | .119 |
Sig. (2-tailed) | .005 | .003 | .123 | .020 | .000 | .868 | .760 | .281 | .206 | .306 | ||
C17 | Significance Inappropriate/ Unexpected QC (Target) | Correlation | .304** | .250* | .142 | .077 | .297** | .021 | -.085 | .051 | .039 | .096 |
Sig. (2-tailed) | .008 | .029 | .223 | .507 | .009 | .855 | .463 | .662 | .736 | .408 | ||
C20 | Significance Slow Client Response | Correlation | .389** | .321** | .334** | .099 | .457** | .211 | .132 | .142 | -.016 | .196 |
Sig. (2-tailed) | .001 | .005 | .003 | .393 | .000 | .067 | .256 | .222 | .890 | .089 | ||
C01 | Significance Inadequate/ Inaccurate Design Information | Correlation | .297** | .192 | .237* | .062 | .317** | .177 | .168 | .236* | .240* | .207 |
Sig. (2-tailed) | .009 | .096 | .039 | .595 | .005 | .127 | .146 | .040 | .037 | .073 | ||
C06 | Significance Inappropriate Contract Form | Correlation | .263* | .291* | .265* | .197 | .440** | .259* | .004 | -.015 | -.025 | .246* |
Sig. (2-tailed) | .022 | .011 | .021 | .088 | .000 | .024 | .975 | .897 | .827 | .032 |
TYPE (Impact) | T39 | T47 | T16 | T41 | T27 | T38 | T33 | T23 | T26 | T48 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|
CAUSE (SIGNIFICANCE) |
Correlation ( Coefficients) |
Loss or damage to the works caused Employer's Risks | Client’s Breach of Contract | Delayed drawings or instructions | Force Majeure | Delays caused by authorities | Ambiguity in Documents | Changes in legislation | A variation or change of quantities | Employer's delay or impediment | Inflation / Price Escalation |
|
C21 | Changes by Client | Correlation | .447** | .424** | .470** | .389** | .548** | .468** | .529** | .252* | .392** | .136 |
Sig. (2-tailed) | .000 | 0.000 | .000 | .001 | .000 | .000 | .000 | .028 | .000 | .240 | ||
C10 | Inappropriate Contractor Selection | Correlation | .559** | .417** | .385** | .462** | .595** | .490** | .432** | .174 | .479** | .189 |
Sig. (2-tailed) | .000 | .000 | .001 | .000 | .000 | .000 | .000 | .133 | .000 | .102 | ||
C05 | Inappropriate Contract Type | Correlation | .501** | .481** | .433** | .438** | .560** | .507** | .542** | .295** | .457** | .276* |
Sig. (2-tailed) | .000 | .000 | .000 | .000 | .000 | .000 | .000 | .010 | .000 | .016 | ||
C15 | Inappropriate/ Unexpected Time Control | Correlation | .461** | .492** | .487** | .398** | .581** | .391** | .410** | .256* | .383** | .313** |
Sig. (2-tailed) | .000 | .000 | .000 | .000 | .000 | .000 | .000 | .026 | .001 | .006 | ||
C16 | Inappropriate/ Unexpected Cost Control | Correlation | .438** | .453** | .453** | .390** | .539** | .469** | .519** | .345** | .357** | .136 |
Sig. (2-tailed) | .000 | .000 | .000 | .000 | .000 | .000 | .000 | .002 | .002 | .243 | ||
C19 | Lack of Information for (Decisiveness) | Correlation | .556** | .561** | .377** | .309** | .538** | .448** | .486** | .207 | .462** | .336** |
Sig. (2-tailed) | .000 | .000 | .001 | .007 | .000 | .000 | .000 | .073 | .000 | .003 | ||
C17 | Inappropriate/ Unexpected QC | Correlation | .447** | .413** | .489** | .412** | .455** | .457** | .474** | .287* | .404** | .098 |
Sig. (2-tailed) | .000 | .000 | .000 | .000 | .000 | .000 | .000 | .012 | .000 | .402 | ||
C20 | Slow Client Response | Correlation | .360** | .398** | .438** | .331** | .539** | .503** | .445** | .280* | .451** | .162 |
Sig. (2-tailed) | .001 | .000 | .000 | .004 | .000 | .000 | .000 | .014 | .000 | .162 | ||
C01 | Inadequate/ Inaccurate Design Information | Correlation | .402** | .473** | .312** | .420** | .486** | .355** | .418** | .273* | .417** | .224 |
Sig. (2-tailed) | .000 | .000 | .006 | .000 | .000 | .002 | .000 | .017 | .000 | .052 | ||
C06 | Inappropriate Contract Form | Correlation | .566** | .414** | .443** | .304** | .557** | .585** | .499** | .182 | .455** | .115 |
Sig. (2-tailed) | .000 | .000 | .000 | .008 | .000 | .000 | .000 | .116 | .000 | .324 |
TYPE (Frequency) | T16 | T23 | T38 | T45 | T31 | T34 | T25 | T07 | T09 | T10 | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|
CAUSE AVOIDABILITY |
CORRELATION ( Coefficients) |
Delayed drawings or instructions | A variation or significant change to the quantities | Ambiguity in Documents | Acceleration of Works | An omission of work forming | Delayed payment | Shortage of personnel or goods | Rejection of defective plant and / or materials | Revised methods of working due to poor progress |
Delay damages |
|
C10 | Inappropriate Contractor Selection | Correlation | .066 | .231* | .283* | .064 | .100 | -.075 | -.034 | .141 | .127 | .114 |
Sig. (2-tailed) | .570 | .045 | .013 | .584 | .390 | .521 | .772 | .225 | .273 | .325 | ||
C13 | Inappropriate Payment Method | Correlation | .096 | .084 | .268* | .334** | .405** | -.022 | .208 | .101 | .133 | .136 |
Sig. (2-tailed) | .411 | .473 | .019 | .003 | .000 | .852 | .072 | .385 | .251 | .243 | ||
C06 | Inappropriate Contract Form | Correlation | .229* | .318** | .294** | .142 | .458** | .083 | -.010 | .082 | .173 | .286* |
Sig. (2-tailed) | .046 | .005 | .010 | .221 | .000 | .478 | .933 | .479 | .135 | .012 | ||
C05 | Inappropriate Contract Type | Correlation | .333** | .170 | .168 | .157 | .264* | .096 | -.081 | .046 | .348** | .192 |
Sig. (2-tailed) | .003 | .142 | .147 | .175 | .021 | .412 | .489 | .695 | .002 | .097 | ||
C01 | Inadequate/ Inaccurate Design | Correlation | -.067 | .020 | .149 | .162 | .109 | .077 | .024 | .198 | .262* | .173 |
Sig. (2-tailed) | .566 | .863 | .198 | .163 | .348 | .509 | .834 | .086 | .022 | .136 | ||
C24 | Inadequate Site Investigation | Correlation | .055 | .197 | .250* | .012 | .162 | -.080 | -.076 | .214 | .259* | .212 |
Sig. (2-tailed) | .635 | .088 | .029 | .920 | .161 | .494 | .513 | .064 | .024 | .066 | ||
C04 | Unclear & Inadequate Specifications | Correlation | -.041 | .027 | .068 | .035 | -.025 | .012 | -.067 | .117 | .235* | .070 |
Sig. (2-tailed) | .724 | .814 | .560 | .765 | .831 | .915 | .567 | .313 | .041 | .546 | ||
C02 | Inadequate/ Inaccurate Design Information | Correlation | .148 | .175 | .290* | .091 | .181 | .109 | .032 | .393** | .361** | .373** |
Sig. (2-tailed) | .202 | .131 | .011 | .432 | .117 | .350 | .782 | .000 | .001 | .001 | ||
C08 | Inadequate Contract Documentation | Correlation | .139 | .162 | .227* | .276* | .176 | .170 | .008 | .211 | .397** | .335** |
Sig. (2-tailed) | .230 | .163 | .048 | .016 | .129 | .141 | .945 | .068 | .000 | .003 | ||
C07 | Inadequate Contract Administration | Correlation | .055 | -.163 | .148 | -.062 | .201 | .010 | .022 | .169 | .094 | -.032 |
Sig. (2-tailed) | .639 | .158 | .203 | .597 | .082 | .930 | .852 | .145 | .421 | .782 | ||
C09 | Incomplete Tender Information | Correlation | .101 | .216 | .051 | .192 | .180 | .022 | .056 | .164 | .329** | .167 |
Sig. (2-tailed) | .387 | .060 | .664 | .096 | .120 | .851 | .629 | .156 | .004 | .150 |
CAUSE AVOIDABILITY | TYPE (IMPACT) | T39 | T47 | T16 | T41 | T27 | T38 | T33 | T23 | T26 | T48 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
CORRELATION | Loss of works caused Employer's Risks | Client’s Breach of Contract | Delayed drawings or instructions | Force Majeure | Delays caused by authorities | Ambiguity in Documents | Changes in legislation | A variation or significant change to the quantities | Employer's delay or impediment | Inflation / Price Escalation | ||
C10 | Inappropriate Contractor Selection | Correlation Coefficient | .222 | .307** | .305** | .244* | .308** | .185 | .359** | .227* | .179 | .294** |
Sig. (2-tailed) | .054 | .007 | .007 | .034 | .007 | .109 | .001 | .048 | .121 | .010 | ||
C13 | Inappropriate Payment Method | Correlation Coefficient | .143 | .370** | .206 | .240* | .271* | .360** | .226* | .205 | .190 | .042 |
Sig. (2-tailed) | .216 | .001 | .074 | .037 | .018 | .001 | .050 | .076 | .099 | .717 | ||
C06 | Inappropriate Contract Form | Correlation Coefficient | .301** | .354** | .330** | .237* | .510** | .520** | .434** | .186 | .459** | .150 |
Sig. (2-tailed) | .008 | .002 | .004 | .039 | .000 | .000 | .000 | .109 | .000 | .195 | ||
C05 | Inappropriate Contract Type (Strategy) | Correlation | .251* | .275* | .295** | .183 | .388** | .298** | .352** | .145 | .258* | .198 |
Sig. (2-tailed) | .029 | .016 | .010 | .113 | .001 | .009 | .002 | .212 | .025 | .087 | ||
C01 | Inadequate/ Inaccurate Design Information | Correlation | .070 | .295** | .055 | .066 | .073 | .176 | .299** | .132 | .165 | .088 |
Sig. (2-tailed) | .548 | .010 | .635 | .572 | .533 | .128 | .009 | .256 | .153 | .449 | ||
C24 | Inadequate Site Investigation | Correlation | .164 | .266* | .222 | .184 | .302** | .254* | .306** | .303** | .248* | .241* |
Sig. (2-tailed) | .156 | .020 | .054 | .111 | .008 | .027 | .007 | .008 | .030 | .036 | ||
C04 | Unclear & Inadequate Specifications | Correlation | .043 | .166 | .006 | -.008 | .073 | .064 | .160 | .210 | .063 | .104 |
Sig. (2-tailed) | .712 | .151 | .957 | .949 | .531 | .580 | .169 | .069 | .590 | .369 | ||
C02 | Inadequate/ Inaccurate Design Information | Correlation | .178 | .183 | .142 | .325** | .381** | .229* | .415** | .145 | .344** | .116 |
Sig. (2-tailed) | .125 | .115 | .221 | .004 | .001 | .046 | .000 | .212 | .002 | .318 | ||
C08 | Inadequate Contract Documentation | Correlation | .219 | .310** | .227* | .191 | .434** | .278* | .483** | .193 | .305** | .342** |
Sig. (2-tailed) | .058 | .006 | .048 | .099 | .000 | .015 | .000 | .094 | .007 | .003 | ||
C07 | Inadequate Contract Administration | Correlation | .016 | .190 | .086 | .048 | .152 | .127 | .277* | .071 | .171 | .183 |
Sig. (2-tailed) | .893 | .099 | .458 | .679 | .190 | .276 | .015 | .540 | .140 | .113 | ||
C09 | Incomplete Tender Information | Correlation | .097 | .095 | .062 | .176 | .116 | -.033 | .164 | .214 | .135 | .115 |
Sig. (2-tailed) | .403 | .414 | .592 | .128 | .317 | .779 | .157 | .063 | .247 | .322 |
Identity (Role of the Respondents) | Frequency | Percent | Valid % | Cumulative % | |
---|---|---|---|---|---|
Client | Not Sure | 1 | 5.9 | 5.9 | 5.9 |
Yes | 16 | 94.1 | 94.1 | 100.0 | |
Total | 17 | 100.0 | 100.0 | ||
Client Representative/Consultant | No | 3 | 7.0 | 7.0 | 7.0 |
Not Sure | 2 | 4.7 | 4.7 | 11.6 | |
Yes | 38 | 88.4 | 88.4 | 100.0 | |
Total | 43 | 100.0 | 100.0 | ||
Contractor | No | 1 | 6.3 | 6.3 | 6.3 |
Yes | 15 | 93.8 | 93.8 | 100.0 | |
Total | 16 | 100.0 | 100.0 |
Identity (Role of the Respondents) | Frequency | Percent | Valid % | Cumulative % | |
---|---|---|---|---|---|
Client | No | 1 | 5.9 | 5.9 | 5.9 |
Not Sure | 1 | 5.9 | 5.9 | 11.8 | |
Yes | 15 | 88.2 | 88.2 | 100.0 | |
Total | 17 | 100.0 | 100.0 | ||
Client Representative/Consultant | No | 1 | 2.3 | 2.3 | 2.3 |
Not Sure | 1 | 2.3 | 2.3 | 4.7 | |
Yes | 41 | 95.3 | 95.3 | 100.0 | |
Total | 43 | 100.0 | 100.0 | ||
Contractor | No | 1 | 6.3 | 6.3 | 6.3 |
Yes | 15 | 93.8 | 93.8 | 100.0 | |
Total | 16 | 100.0 | 100.0 |
Identity (Role of the Respondents) | Frequency | Valid % | Cumulative % | |
---|---|---|---|---|
Client | No | 1 | 5.9 | 5.9 |
Yes | 16 | 94.1 | 100.0 | |
Total | 17 | 100.0 | ||
Client Representative/Consultant | No | 1 | 2.3 | 2.3 |
Not Sure | 6 | 14.0 | 16.3 | |
Yes | 36 | 83.7 | 100.0 | |
Total | 43 | 100.0 | ||
Contractor | Not Sure | 1 | 6.3 | 6.3 |
Yes | 15 | 93.8 | 100.0 | |
Total | 16 | 100.0 |
Identity (Role of the Respondents) | Frequency | Valid % | Cumulative % | |
---|---|---|---|---|
Client | No | 2 | 11.8 | 11.8 |
Not Sure | 2 | 11.8 | 23.5 | |
Yes | 13 | 76.5 | 100.0 | |
Total | 17 | 100.0 | ||
Client Representative/Consultant | No | 1 | 2.3 | 2.3 |
Not Sure | 8 | 18.6 | 20.9 | |
Yes | 34 | 79.1 | 100.0 | |
Total | 43 | 100.0 | ||
Contractor | Not Sure | 2 | 12.5 | 12.5 |
Yes | 14 | 87.5 | 100.0 | |
Total | 16 | 100.0 |
Cluster | Cause | Count |
---|---|---|
0 | T45, T40, T35, T25, T24 | 5 |
1 | T1, T49, T44, T42, T41, T27, T50, T20, T18, T26, T51, T6, T5, T4, T3, T15, T14 | 17 |
2 | T47, T48, T34, T2, T7, T39, T38, T37, T8, T46, T43, T33, T31, T17, T19, T13, T21, T22, T32, T12, T10, T9, T28, T29, T30, T11 | 26 |
3 | T23, T36, T16 | 3 |
No. | Frequent Types of Variations and Claims | No. | List of Causes |
---|---|---|---|
01 | Delayed drawings or instructions | 01 | Loss or damage to the works caused Employer's Risks munitions, poor design etc.) (T39) |
02 | A variation or significant change to the quantities | 02 | Client’s Breach of Contract |
03 | Ambiguity in documents | 03 | Delayed drawings or instructions |
04 | Acceleration of Works | 04 | Force Majeure |
05 | Omission of work forming | 05 | Delays caused by authorities |
06 | Delayed payment | 06 | Ambiguity in Documents |
07 | Shortage of personnel or goods | 07 | Changes in legislation |
08 | Rejection of defective plant and / materials |
08 | A variation or significant change to the quantities. |
09 | Revised methods of working due to poor rate of progress (T09) | 09 | Employer's delay or impediment |
10 | Delay damages | 10 | Inflation / Price Escalation |
No. | Significant Causes of Variations and Claims | No. | Avoidable Causes of Variations and Claims |
---|---|---|---|
01 | Changes by Client (C21) | 01 | Inappropriate Contractor Selection (C10) |
02 | Inappropriate Contractor Selection (C10) | 02 | Inappropriate Payment Method (C13) |
03 | Inappropriate Contract Type (Strategy) (C05) | 03 | Inappropriate Contract Form (C06) |
04 | Inappropriate/ Unexpected Time Control (Target) (C15) | 04 | Inappropriate Contract Type (Strategy) (C05) |
05 | Inappropriate/ Unexpected Cost Control (Target) (C16) | 05 | Inadequate/ Inaccurate Design Information (C01) |
06 | Lack of Information for Decision Making; (Decisiveness) (C19) | 06 | Inadequate Site Investigation (C24) |
07 | Inappropriate/ Unexpected Quality Control (Target) (C17) | 07 | Unclear & Inadequate Specifications (C04) |
08 | Slow Client Response (C20) | 08 | Inadequate Design Documentation (C02) |
09 | Inadequate/ Inaccurate Design Information (C01) | 09 | Inadequate Contract Documentation (C08) |
10 | Inappropriate Contract Form (C06) | 10 | Inadequate Contract Administration (C07) |
# | Avoidable Causes of Variations and Claims | Recommended Mitigation/ Response Strategy |
---|---|---|
1 | Changes by Client (C21) |
|
2 | Inappropriate Contractor Selection (C10) |
|
3 | Inappropriate Contract Type/Strategy - C05 |
|
4 | Inappropriate/Unexpected Time Control (Target)-(C15) |
|
5 | Inappropriate/Unexpected Cost Control (Target)- C16 |
|
6 | Lack of Information for Decision-Making;Decisiveness-(C19) |
|
7 | Inappropriate/Unexpected Quality Control (Target)-(C17) |
|
8 | Slow Client Response- (C20) |
|
9 | Inadequate/Inaccurate Design Information- (C01) |
|
10 | Inappropriate Contract Form- (C06) |
|
11 | Inappropriate Payment Method- (C13) |
|
12 | Inadequate Site Investigations- (C24) |
|
13 | Unclear & Inadequate Specifications- (C04) |
|
14 | Inadequate Design Documentation- (C02) |
|
15 | Inadequate Contract Documentation-(C08) |
|
16 | Inadequate Contract Administration-(C07) |
|
17 | Incomplete Tender Information-(C09) |
|
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 MDPI (Basel, Switzerland) unless otherwise stated