Lean management technique | Lean management practice | Source |
Daily huddle meetings | Two-way communication | [15,44,45,46,47,48,51] |
Hazard identification and elimination | ||
Information sharing | ||
Review previous work | ||
Identify good and bad practice | ||
Two-way communication | ||
First run studies | Critical analysis of work methods | |
Use video files, photographs and illustrations to review work | ||
Mistaking proofing | Use of personal protective equipment | |
Use of hazard warning equipment | ||
Use of safeguards | ||
Visual inspection | ||
Use of audible devices | ||
Use of visual tools | ||
5S housekeeping | Organising | |
Cleanliness and orderliness | ||
Improved circulation around the workplace | ||
Eliminate emplacements | ||
Improved visualization | Use of graphical dashboards and digital billboards | |
Use of safety borders and demarcations | ||
Standardise work procedure | ||
Use of safety signs and labels | ||
Use of lights for activities performed at night | ||
Last planner system | Providing necessary work equipment | |
Involvement of workers in safety planning | ||
Eliminate all potential work constraints | ||
Correlate work methods with workers’ abilities and skills | ||
Schedule site activities and simultaneous supervision plan | ||
Empower safety workers in schedule planning | ||
Undertake pre-task hazard analysis | ||
Select the most appropriate and safest method |
Attribute | Sub-attribute | Responses | % Responses |
Professional roles | Company director | 28 | 25.5 |
Safety officer/manager | 9 | 8.2 | |
Project manager | 29 | 26.4 | |
Quantity surveyor | 27 | 25.5 | |
Sit engineer/agent | 7 | 6.4 | |
Site manager | 1 | 0.9 | |
General experience in construction | 1-5 years | 20 | 18.2 |
6-10 years | 30 | 27.3 | |
11-15 years | 21 | 19.1 | |
Over 15 years | 32 | 29.1 | |
Experience in OSC | 1-5 years | 33 | 30 |
6-10 years | 35 | 31.8 | |
11-15 years | 16 | 14.5 | |
Over 15 years | 19 | 17.3 | |
Size of company | Small | 29 | 26.4 |
Medium | 47 | 42.7 | |
Large | 27 | 24.5 | |
Work undertaken by company | Building | 22 | 21.4 |
Civil | 14 | 13.6 | |
Building and Civil | 67 | 65 | |
Code | LMPs | MS | SD | Rank | Shapiro-Wilk test (p- value) | Kruskal-Walli’s test (p- value) |
LMP1 | Use of personal protective equipment | 4.41 | 0.619 | 1 | 0.001 | 0.311 |
LMP2 | Involvement of workers in safety planning | 4.35 | 0.652 | 2 | 0.001 | 0.897 |
LMP3 | Providing necessary work equipment | 4.30 | 0.639 | 3 | 0.001 | 0.305 |
LMP4 | Use of hazard warning equipment | 4.30 | 0.725 | 4 | 0.001 | 0.321 |
LMP5 | Critical analysis of work methods | 4.28 | 0.569 | 5 | 0.001 | 0.726 |
LMP6 | Two-way communication | 4.28 | 0.569 | 6 | 0.001 | 0.975 |
LMP7 | Use of safeguards | 4.28 | 0.736 | 7 | 0.001 | 0.403 |
LMP8 | Visual inspection | 4.25 | 0.606 | 8 | 0.001 | 0.780 |
LMP9 | Illumination | 4.25 | 0.637 | 9 | 0.001 | 0.603 |
LMP10 | Use video files, photographs and illustrations to review work | 4.25 | 0.670 | 10 | 0.001 | 0.833 |
LMP11 | Organising | 4.25 | 0.532 | 11 | 0.001 | 0.427 |
LMP12 | Use of graphical dashboards and digital billboards | 4.24 | 0.633 | 12 | 0.001 | 0.318 |
LMP13 | Use of audible devices | 4.23 | 0.675 | 13 | 0.001 | 0.128 |
LMP14 | Improved circulation around the workplace | 4.23 | 0.689 | 14 | 0.001 | 0.559 |
LMP15 | Cleanliness and orderliness | 4.23 | 0.703 | 15 | 0.001 | 0.920 |
LMP16 | Hazard identification and elimination | 4.23 | 0.716 | 16 | 0.001 | 0.511 |
LMP17 | Use of safety borders and demarcations | 4.23 | 0.770 | 17 | 0.001 | 0.027 |
LMP18 | Information sharing | 4.22 | 0.576 | 18 | 0.001 | 0.866 |
LMP19 | Eliminate all potential work constraints | 4.22 | 0.625 | 19 | 0.001 | 0.452 |
LMP20 | Correlate work methods with workers’ abilities and skills | 4.22 | 0.685 | 20 | 0.001 | 0.104 |
LMP21 | Review previous work | 4.21 | 0.618 | 21 | 0.001 | 0.511 |
LMP22 | Identify good and bad practice | 4.21 | 0.635 | 22 | 0.001 | 0.378 |
LMP23 | Select the most appropriate and safest method | 4.20 | 0.632 | 23 | 0.001 | 0.331 |
LMP24 | Eliminate emplacements | 4.20 | 0.705 | 24 | 0.001 | 0.422 |
LMP25 | Standardise work procedure | 4.19 | 0.482 | 25 | 0.001 | 0.713 |
LMP26 | Use of visual tools | 4.19 | 0.728 | 26 | 0.001 | 0.542 |
LMP27 | Use of safety signs and labels | 4.18 | 0.751 | 27 | 0.001 | 0.159 |
LMP28 | Schedule site activities and simultaneous supervision plan | 4.17 | 0.596 | 28 | 0.001 | 0.606 |
LMP29 | Empower and involve safety workers in schedule planning | 4.17 | 0.663 | 29 | 0.001 | 0.783 |
LMP30 | Undertake pre-task hazard analysis | 4.14 | 0.715 | 30 | 0.001 | 0.852 |
Code | LMTs/LMPs | Mean | SD | LMP rank | Av. MS | Av. SD | LMT rank |
Mistaking proofing | |||||||
LMP1 | Use of personal protective equipment | 4.41 | 0.619 | 1 | 4.33 | 0.682 | 1 |
LMP4 | Use of hazard warning equipment | 4.30 | 0.725 | 4 | |||
LMP7 | Use of safeguards | 4.28 | 0.736 | 7 | |||
LMP8 | Visual inspection | 4.25 | 0.606 | 8 | |||
LMP13 | Use of audible devices | 4.23 | 0.675 | 13 | |||
LMP26 | Use of visual tools | 4.19 | 0.728 | 26 | |||
First run studies | |||||||
LMP5 | Critical analysis of work methods | 4.28 | 0.569 | 5 | 4.27 | 0.620 | 2 |
LMP10 | Use video files, photographs and illustrations to review work | 4.25 | 0.670 | 10 | |||
Daily huddle meeting | |||||||
LMP6 | Two-way communication | 4.28 | 0.569 | 6 | 4.23 | 0.623 | 3 |
LMP16 | Hazard identification and elimination | 4.23 | 0.716 | 16 | |||
LMP18 | Information sharing | 4.22 | 0.576 | 18 | |||
LMP21 | Review previous work | 4.21 | 0.618 | 21 | |||
LMP22 | Identify good and bad practice | 4.21 | 0.635 | 22 | |||
5S housekeeping | |||||||
LMP11 | Organising | 4.25 | 0.532 | 11 | 4.23 | 0.657 | 4 |
LMP14 | Improved circulation around the workplace | 4.23 | 0.689 | 14 | |||
LMP15 | Cleanliness and orderliness | 4.23 | 0.703 | 15 | |||
LMP24 | Eliminate emplacements | 4.20 | 0.705 | 24 | |||
Last planner system | 4.22 | 0.651 | 5 | ||||
LMP2 | Involvement of workers in safety planning | 4.35 | 0.652 | 2 | |||
LMP3 | Providing necessary work equipment | 4.30 | 0.639 | 3 | |||
LMP19 | Eliminate all potential work constraints | 4.22 | 0.625 | 19 | |||
LMP20 | Correlate work methods with workers’ abilities and skills | 4.22 | 0.685 | 20 | |||
LMP23 | Select the most appropriate and safest method | 4.20 | 0.632 | 23 | |||
LMP28 | Schedule site activities and simultaneous supervision plan | 4.17 | 0.596 | 28 | |||
LMP29 | Empower safety workers in schedule planning | 4.17 | 0.663 | 29 | |||
LMP30 | Undertake pre-task hazard analysis | 4.14 | 0.715 | 30 | |||
Improved visualisation | |||||||
LMP9 | Use of lights for activities performed at night | 4.25 | 0.637 | 9 | 4.22 | 0.655 | 6 |
LMP12 | Use of graphical dashboards and digital billboards | 4.24 | 0.633 | 12 | |||
LMP17 | Use of safety borders and demarcations | 4.23 | 0.770 | 17 | |||
LMP25 | Standardise work procedure | 4.19 | 0.482 | 25 | |||
LMP27 | Use of safety signs and labels | 4.18 | 0.751 | 27 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |